6341-86-001
|
ANGELINA
|
LUFKIN
|
$291,250
|
US0059
|
RMC - 634186001
|
02/27/2019
|
11/15/2023
|
INSTL OF WATERBASE STRIPING
|
STRIPING TECHNOLOGY, L.P.
($262,750)
|
|
|
6338-71-001
|
ATASCOSA
|
SAN ANTONIO
|
$3,011,641
|
US0281
|
RMC - 633871001
|
02/06/2019
|
11/15/2023
|
PAVMT REPAIR
|
TEXAS MATERIALS GROUP, INC.
($2,675,424)
|
|
|
6333-82-001
|
AUSTIN
|
YOAKUM
|
$277,284
|
SH0036
|
RMC - 633382001
|
02/26/2019
|
11/15/2023
|
STRUCTURAL AND EROSION REPAIRS
|
CHAMPION INFRASTRUCTURE, LLC
($312,421)
|
|
|
2136-01-015
|
BELL
|
WACO
|
$4,194,503
|
FM 2268
|
BR 2019(313)
|
02/06/2019
|
11/15/2023
|
REPL BR & APPRS
|
CAPITAL EXCAVATION COMPANY
($5,238,854)
|
|
|
0024-09-024
|
BEXAR
|
SAN ANTONIO
|
$6,016,898
|
SS 371
|
C 24-9-24
|
02/05/2019
|
11/15/2023
|
SURF & PAVMT MRK
|
ANGEL BROTHERS HOLDINGS CORP.
($6,242,921)
|
|
|
0291-10-110
|
BEXAR
|
SAN ANTONIO
|
$2,116,136
|
SH 16
|
NH 2019(511)
|
02/06/2019
|
11/15/2023
|
RECON EXIST CULVERT
|
DAN WILLIAMS COMPANY
($2,107,962)
|
|
|
0465-02-026
|
BEXAR
|
SAN ANTONIO
|
$2,621,772
|
FM 1518
|
C 465-2-26
|
02/05/2019
|
11/15/2023
|
SURF & PAVMT MRK
|
ANGEL BROTHERS HOLDINGS CORP.
($2,220,997)
|
|
|
0521-03-060
|
BEXAR
|
SAN ANTONIO
|
$3,385,793
|
SL 13
|
C 521-3-60
|
02/06/2019
|
11/15/2023
|
BSE RPR, MILL, SC, SURF & PAV'T MRK
|
ANGEL BROTHERS HOLDINGS CORP.
($3,075,679)
|
|
|
0915-00-191
|
BEXAR
|
SAN ANTONIO
|
$1,493,471
|
VA
|
C 915-00-191
|
02/06/2019
|
11/15/2023
|
DISTRICTWIDE NON-SITE SPECIFIC TRAF...
|
THE LEVY COMPANY, INC.
($1,540,868)
|
|
|
2452-04-016
|
BEXAR
|
SAN ANTONIO
|
$23,174,045
|
SL 1604
|
STP 2019(510)
|
02/05/2019
|
11/15/2023
|
EXPAND FROM 2 LANES TO 4 LANE DIVIDE...
|
MARIO SINACOLA & SONS EXCAVATING, INC.
($20,172,902)
|
|
|
6341-52-001
|
BEXAR
|
SAN ANTONIO
|
$127,599
|
IH0010
|
RMC - 634152001
|
02/13/2019
|
11/15/2023
|
CONC RAIL REPAIR
|
CURRAN CONTRACTING COMPANY
($117,027)
|
|
|
6339-67-001
|
BRAZORIA
|
HOUSTON
|
$450,316
|
SH0288
|
RMC - 633967001
|
02/06/2019
|
11/15/2023
|
MOW HWY ROW (NORTH)
|
C-CO HOLDINGS LIMITED LIABILITY COMPANY
($446,201)
|
|
|
6339-75-001
|
BRAZORIA
|
HOUSTON
|
$387,217
|
FM0521
|
RMC - 633975001
|
02/05/2019
|
11/15/2023
|
MOW HWY ROW (SOUTH FM'S)
|
RELIANT SAND AND CONSTRUCTION, INC.
($385,752)
|
|
|
0054-06-104
|
BROWN
|
BROWNWOOD
|
$1,220,868
|
US 67
|
STP 2019(474)HES
|
02/05/2019
|
11/15/2023
|
PROFILE CENTER AND EDGELINE
|
STRIPE-A-ZONE, INC.
($1,059,136)
|
|
|
0923-00-060
|
BROWN
|
BROWNWOOD
|
$888,556
|
VA
|
C 923-00-60
|
02/06/2019
|
11/15/2023
|
THERMOPLASTIC STRIPING
|
L&L COMPANY
($978,221)
|
|
|
0432-01-065
|
CALHOUN
|
YOAKUM
|
$1,009,685
|
SH 185
|
STP 2019(501)
|
02/05/2019
|
11/15/2023
|
ADD TURN LANES & RESURF
|
REXCO CONSTRUCTION SERVICES, INC.
($1,252,352)
|
|
|
0181-03-025
|
CALLAHAN
|
ABILENE
|
$1,948,115
|
SH 36
|
STP 2019(443)HES
|
02/05/2019
|
11/15/2023
|
MILLED EDGELINE RUMBLE STRIPS
|
FLAT LINE, INC.
($1,298,585)
|
|
|
0169-05-041
|
CARSON
|
AMARILLO
|
$15,490,402
|
US 60
|
NH 2013(613)
|
02/06/2019
|
11/15/2023
|
REHAB EXISITNG ROADWAY
|
RK HALL, LLC
($16,325,738)
|
|
|
0508-02-120
|
CHAMBERS
|
BEAUMONT
|
$34,921,671
|
IH 10
|
STP 2018(953)MM
|
02/05/2019
|
11/15/2023
|
CONSTRUCT OVERPASS AND RECONFIGURE I...
|
COPASA INC
($35,023,919)
|
|
|
0137-10-022
|
CLAY
|
WICHITA FALLS
|
$2,104,517
|
FM 174
|
STP 2019(504)HES
|
02/05/2019
|
11/15/2023
|
PROVIDE ADDITIONAL PAVED SURF WIDTH
|
BLYTHE CONSTRUCTION, INC.
($2,328,204)
|
|
|
0016-05-119
|
COMAL
|
SAN ANTONIO
|
$28,477,165
|
IH 35
|
NH 2019(507)
|
02/06/2019
|
11/15/2023
|
GRADING, STRUCTS, BASE & SURF
|
BRIDGES AND ROADS, LLC
($25,398,551)
|
|
|
6335-01-001
|
COMAL
|
SAN ANTONIO
|
$117,154
|
FM0306
|
BPM - 633501001
|
02/13/2019
|
11/15/2023
|
RIPRAP REPAIR
|
DALRYMPLE GRAVEL AND CONTRACTING COMPANY, INC.
($106,177)
|
|
|
1357-01-026
|
COOKE
|
WICHITA FALLS
|
$2,682,062
|
FM 2896
|
SSW 1357-1-26
|
02/06/2019
|
11/15/2023
|
PROVIDE ADDITIONAL PAVED SURF WIDTH
|
JAGOE-PUBLIC COMPANY
($2,595,534)
|
|
|
6342-78-001
|
CROCKETT
|
SAN ANGELO
|
$268,378
|
IH0010
|
RMC - 634278001
|
02/20/2019
|
11/15/2023
|
BRIDGE AND RAIL REPAIR
|
RELMCO, INC.
($223,179)
|
|
|
1158-01-009
|
CULBERSON
|
EL PASO
|
$2,597,422
|
FM 2185
|
C 1158-1-9
|
02/05/2019
|
11/15/2023
|
ROADWAY REHAB
|
DAN WILLIAMS COMPANY
($2,339,707)
|
|
|
2451-02-012
|
CULBERSON
|
EL PASO
|
$22,909,056
|
RM 652
|
STP 2019(065)
|
02/06/2019
|
11/15/2023
|
FULL DEPTH REHAB
|
JOHNSON BROS. CORPORATION, A SOUTHLAND COMPANY
($22,480,669)
|
|
|
0009-11-243
|
DALLAS
|
DALLAS
|
$1,070,904
|
IH 30
|
C 9-11-243
|
02/05/2019
|
11/15/2023
|
FULL DEPTH CONC. PAV REPAIR & PAV MA...
|
HIGHWAY 19 CONSTRUCTION LLC
($1,381,126)
|
|
|
0047-07-230
|
DALLAS
|
DALLAS
|
$1,484,220
|
US 75
|
STP 2019(498)HES
|
02/06/2019
|
11/15/2023
|
INSTL OF TRAF SIG
|
AMERICAN LIGHTING AND SIGNALIZATION, LLC
($1,655,509)
|
|
|
0092-14-092
|
DALLAS
|
DALLAS
|
$3,132,829
|
IH 345
|
C 92-14-92
|
02/05/2019
|
11/15/2023
|
FULL DEPTH CONC REPAIR ON FRONTAGE R...
|
NEW WORLD CONTRACTING, LLC
($3,472,553)
|
|
|
6333-41-001
|
DALLAS
|
DALLAS
|
$336,284
|
US0075
|
BPM - 633341001
|
02/05/2019
|
11/15/2023
|
BRIDGE REPAIR
|
GIBSON & ASSOCIATES, INC.
($335,030)
|
|
|
6337-65-001
|
DALLAS
|
DALLAS
|
$631,611
|
IH0045
|
RMC - 633765001
|
02/05/2019
|
11/15/2023
|
RETROREFLECTORIZED PAVMT MRK & MARKE...
|
PMI PAVEMENT MARKING, LLC
($595,804)
|
|
|
6337-66-001
|
DALLAS
|
DALLAS
|
$876,075
|
IH0030
|
RMC - 633766001
|
02/06/2019
|
11/15/2023
|
RETROREFLECTORIZED PAVMT MRK & MARKE...
|
PMI PAVEMENT MARKING, LLC
($759,054)
|
|
|
0195-02-077
|
DENTON
|
DALLAS
|
$1,089,738
|
IH 35
|
C 195-2-77
|
02/06/2019
|
11/15/2023
|
FULL DEPTH CONC REPAIR
|
SILVER CREEK CONSTRUCTION, INC.
($1,062,400)
|
|
|
6336-77-001
|
DENTON
|
DALLAS
|
$680,453
|
IH0035
|
RMC - 633677001
|
02/05/2019
|
11/15/2023
|
FLEXIBLE PAVMT REPAIR
|
JAGOE-PUBLIC COMPANY
($895,600)
|
|
|
6338-59-001
|
DENTON
|
DALLAS
|
$866,840
|
IH0035W
|
RMC - 633859001
|
02/05/2019
|
11/15/2023
|
VEGETATION MANGAEMENT
|
CROSS PLUS CONSTRUCTION, LLC
($1,034,090)
|
|
|
0042-07-066
|
DONLEY
|
CHILDRESS
|
$4,779,818
|
US 287
|
NH 2019(592)
|
02/06/2019
|
11/15/2023
|
ASPHIC CONC OVERLAY
|
J. LEE MILLIGAN, INC.
($4,527,707)
|
|
|
6341-34-001
|
ECTOR
|
ODESSA
|
$196,320
|
IH0020
|
RMC - 634134001
|
02/12/2019
|
11/15/2023
|
BRUSH RMVL/DRAINAGE EASEMENT CLEANIN...
|
BK FIELD OPERATIONS LLC
($167,765)
|
|
|
6341-62-001
|
ECTOR
|
ODESSA
|
$80,000
|
IH0020
|
RMC - 634162001
|
02/12/2019
|
11/15/2023
|
CULVERT CLEANING
|
E.V.G. ENTERPRISE
($97,500)
|
|
|
0092-05-051
|
ELLIS
|
DALLAS
|
$1,213,647
|
IH 45
|
STP 2019(499)MM
|
02/05/2019
|
11/15/2023
|
CONSTRUCT INTERS IMPRVS
|
ACCELERATED CRITICAL PATH, INC.
($1,593,213)
|
|
|
6320-78-001
|
ELLIS
|
DALLAS
|
$424,826
|
US0287
|
RMC - 632078001
|
02/05/2019
|
11/15/2023
|
ON-CALL REFLECTORIZED PAVMT MRK
|
TRP CONSTRUCTION GROUP, LLC
($531,308)
|
|
|
6333-06-001
|
ELLIS
|
DALLAS
|
$178,443
|
US0287
|
BPM - 633306001
|
02/12/2019
|
11/15/2023
|
BPM - BRIDGE REPAIR
|
SCOTT TUCKER CONSTRUCTION COMPANY, LLC
($198,227)
|
|
|
0924-00-100
|
EL PASO
|
EL PASO
|
$2,057,697
|
VA
|
STP 2019(575)
|
02/05/2019
|
11/15/2023
|
FY 2019 STRIPING PROJECT
|
MIJELUM, L.L.C.
($1,965,160)
|
|
|
6341-00-001
|
EL PASO
|
EL PASO
|
$649,470
|
IH0010
|
RMC - 634100001
|
02/06/2019
|
11/15/2023
|
ROADWAY SPALL & FULL DEPTH REPAIR
|
SYNERGY PROJECT CONTRACTORS, INC.
($689,827)
|
|
|
6341-01-001
|
EL PASO
|
EL PASO
|
$536,950
|
IH0010
|
RMC - 634101001
|
02/06/2019
|
11/15/2023
|
ROADWAY SPALL & FULL DEPTH REPAIR
|
SYNERGY PROJECT CONTRACTORS, INC.
($542,137)
|
|
|
0257-06-027
|
ERATH
|
FORT WORTH
|
$5,268,158
|
SH 6
|
C 257-6-27
|
02/06/2019
|
11/15/2023
|
GR, DR, STR, BS, HMAC, PAV MARK
|
JAY MILLS CONTRACTING, INCORPORATED
($5,364,691)
|
|
|
6334-39-001
|
ERATH
|
FORT WORTH
|
$213,868
|
US0377
|
RMC - 633439001
|
02/12/2019
|
11/15/2023
|
REFLECTORIZED PAV MRKINGS AND MRKS
|
REPUBLIC TRAFFIC SAFETY, INC.
($221,553)
|
|
|
0382-02-036
|
FALLS
|
WACO
|
$7,215,206
|
SH 7
|
STP 2019(441)
|
02/06/2019
|
11/15/2023
|
MILL/OVLY
|
BIG CREEK CONSTRUCTION, LTD.
($6,187,425)
|
|
|
0045-05-048
|
FANNIN
|
PARIS
|
$216,959
|
SH 56
|
STP 2019(502)HES
|
02/05/2019
|
11/15/2023
|
TRAF CONTROL DEVICES
|
NORTH TEXAS TRAFFIC SYSTEMS CONSTRUCTION
($205,853)
|
|
|
0057-03-041
|
FREESTONE
|
BRYAN
|
$2,053,056
|
US 84
|
STP 2019(496)HES
|
02/06/2019
|
11/15/2023
|
PROFILE EDGELINE MRK
|
STRIPING TECHNOLOGY, L.P.
($1,651,842)
|
|
|
0915-18-024
|
FRIO
|
SAN ANTONIO
|
$557,192
|
CR
|
BR 2007(141)
|
02/05/2019
|
11/15/2023
|
REPLACE BRIDGE AND APPROACHES
|
ENCINO LANDSCAPE, INC.
($572,307)
|
|
|
0051-09-120
|
GALVESTON
|
HOUSTON
|
$3,283,657
|
FM 3005
|
C 51-9-120
|
02/05/2019
|
11/15/2023
|
BASE REP, MILL, SC, O/L, STRIPING
|
ANGEL BROTHERS HOLDINGS CORP.
($2,837,928)
|
|
|
0367-03-037
|
GALVESTON
|
HOUSTON
|
$7,024,267
|
SH 87
|
C 367-3-37
|
02/06/2019
|
11/15/2023
|
BASE REPAIR,MILL & O/L
|
ANGEL BROTHERS HOLDINGS CORP.
($7,833,851)
|
|
|
6339-40-001
|
GOLIAD
|
CORPUS CHRISTI
|
$292,700
|
US0059
|
RMC - 633940001
|
02/12/2019
|
11/15/2023
|
MOW
|
HAMMOND LAND DEVELOPMENT, LLC
($246,500)
|
|
|
6340-24-001
|
GONZALES
|
YOAKUM
|
$3,817,537
|
UA0090
|
RMC - 634024001
|
02/05/2019
|
11/15/2023
|
ON CALL PAVMT REPAIRS
|
BRANNAN PAVING CO., LTD.
($3,598,022)
|
|
|
6340-25-001
|
GONZALES
|
YOAKUM
|
$1,110,500
|
UA0090
|
RMC - 634025001
|
02/05/2019
|
11/15/2023
|
ON CALL SPOT REPAIRS
|
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.
($876,200)
|
|
|
6341-31-001
|
GONZALES
|
YOAKUM
|
$834,271
|
UA0090
|
RMC - 634131001
|
02/05/2019
|
11/15/2023
|
THERMOPLASTIC PAVMT MRK
|
D. I. J. CONSTRUCTION, INC.
($770,109)
|
|
|
6328-94-001
|
GRAYSON
|
PARIS
|
$624,950
|
FM0120
|
RMC - 632894001
|
02/05/2019
|
11/15/2023
|
BORE AND REPLACE PIPE
|
HIGHWAY 19 CONSTRUCTION LLC
($680,119)
|
|
|
6341-05-001
|
GRAYSON
|
PARIS
|
$1,485,577
|
US0075
|
RMC - 634105001
|
02/06/2019
|
11/15/2023
|
SITE SPECIFIC TY I STRIPING
|
STRIPING TECHNOLOGY, L.P.
($1,414,475)
|
|
|
6334-79-001
|
HALE
|
LUBBOCK
|
$464,440
|
IH0027
|
RMC - 633479001
|
02/05/2019
|
11/15/2023
|
MOW
|
TEXAS BLACKTOPS LLC
($463,926)
|
|
|
6342-06-001
|
HALE
|
LUBBOCK
|
$296,500
|
IH0027
|
RMC - 634206001
|
02/06/2019
|
11/15/2023
|
CALL OUT TRAF CONTROL SERVICES
|
BARRICADES UNLIMITED
($390,850)
|
|
|
0027-13-212
|
HARRIS
|
HOUSTON
|
$5,280,884
|
IH 69
|
NH 2019(365)
|
02/05/2019
|
11/15/2023
|
HIGH MAST AND UNDERPASS LIGHTING UPG...
|
SICE, INC.
($4,728,768)
|
|
|
0271-15-090
|
HARRIS
|
HOUSTON
|
$1,093,630
|
IH 610
|
C 271-15-90
|
02/06/2019
|
11/15/2023
|
UGRADE STORM SEWERS
|
ANGEL BROTHERS HOLDINGS CORP.
($1,159,847)
|
|
|
6340-50-001
|
HARRIS
|
HOUSTON
|
$259,988
|
IH0069
|
RMC - 634050001
|
02/12/2019
|
11/15/2023
|
REFL PAVMT MRK (GRAPHICS)
|
PMI PAVEMENT MARKING, LLC
($242,946)
|
|
|
6340-76-001
|
HARRIS
|
HOUSTON
|
$289,833
|
SL0008
|
RMC - 634076001
|
02/12/2019
|
11/15/2023
|
PUMP STATION & DRAINAGE SYSTEM CLEAN...
|
AIMS COMPANIES
($239,994)
|
|
|
0366-01-076
|
HAYS
|
AUSTIN
|
$982,023
|
SL 82
|
STP 2019(578)
|
02/05/2019
|
11/15/2023
|
MILL, SEAL AND INLAY
|
ANGEL BROTHERS HOLDINGS CORP.
($1,025,322)
|
|
|
0164-01-072
|
HENDERSON
|
TYLER
|
$148,860
|
SH 31
|
NH 2019(089)
|
02/05/2019
|
11/15/2023
|
RECNSTRCT PIPE ENTRNCE,ADD LNDSCPING...
|
ENCINO LANDSCAPE, INC.
($144,985)
|
|
|
0039-17-201
|
HIDALGO
|
PHARR
|
$2,366,368
|
IH 2
|
NH 2019(694)
|
02/05/2019
|
11/15/2023
|
PAVMT REHAB OF FRONTAGE ROADS
|
FOREMOST PAVING, INC.
($2,966,778)
|
|
|
6318-30-001
|
HIDALGO
|
PHARR
|
$1,054,565
|
FM0088
|
BPM - 631830001
|
02/05/2019
|
11/15/2023
|
BRIDGE PREVENT MAINT
|
VALLEY INFRASTRUCTURE, INC.
($1,227,644)
|
|
|
0400-02-053
|
HOPKINS
|
PARIS
|
$764,387
|
SH 19
|
NH 2019(503)
|
02/06/2019
|
11/15/2023
|
INTERS & OPERATIONAL IMPROVMN
|
SAMMY GIST ENTERPRISES, INC.
($837,426)
|
|
|
6330-13-001
|
HOUSTON
|
LUFKIN
|
$269,800
|
US0287
|
RMC - 633013001
|
02/27/2019
|
11/15/2023
|
TREE TRIM AND TREE AND BRUSH RMVL
|
L & M MOWING CONTRACTORS, LLC
($247,007)
|
|
|
6340-51-001
|
HOUSTON
|
LUFKIN
|
$192,700
|
US0287
|
RMC - 634051001
|
02/13/2019
|
11/15/2023
|
MOW OF RIGHT-OF-WAY AND LITTER RMVL
|
SOUTHERN EDGE CONTRACTORS LLC
($164,760)
|
|
|
0009-06-051
|
HUNT
|
PARIS
|
$2,288,838
|
SH 66
|
STP 2019(512)HES
|
02/06/2019
|
11/15/2023
|
SAFETY RELATED PROJECTS
|
SAMMY GIST ENTERPRISES, INC.
($2,841,098)
|
|
|
6341-46-001
|
HUNT
|
PARIS
|
$209,155
|
FM1903
|
RMC - 634146001
|
02/14/2019
|
11/15/2023
|
CONC CURB AND FLUME
|
J.R. POPE COMPANY, INC.
($196,128)
|
|
|
0200-04-024
|
JASPER
|
BEAUMONT
|
$11,758,396
|
US 69
|
NH 2019(629)
|
02/06/2019
|
11/15/2023
|
OVERLAY EXIST ROADWAY
|
HERITAGE ASPHALT COMPANY LLC
($10,120,117)
|
|
|
6338-52-001
|
JEFFERSON
|
BEAUMONT
|
$1,198,164
|
US0069
|
RMC - 633852001
|
02/06/2019
|
11/15/2023
|
DISTRICTWIDE SWEEPING
|
SWEEPING SERVICES OF TEXAS - OPERATING, L.P.
($977,222)
|
|
|
0172-10-015
|
JOHNSON
|
FORT WORTH
|
$808,266
|
US 287
|
C 172-10-15
|
02/05/2019
|
11/15/2023
|
GR, BS, DR, PAV
|
AUSTIN BRIDGE & ROAD SERVICES, LP
($709,937)
|
|
|
2815-01-008
|
KAUFMAN
|
DALLAS
|
$4,142,849
|
FM 2757
|
C 2815-1-8
|
02/06/2019
|
11/15/2023
|
REHAB EXIST PAVMT AND ADD SHOULDERS
|
LONGVIEW BRIDGE AND ROAD, LTD.
($3,946,271)
|
|
|
6341-03-001
|
KINNEY
|
LAREDO
|
$291,409
|
US0277
|
RMC - 634103001
|
02/12/2019
|
11/15/2023
|
INSTL TRAF SIG AND FLASH BEACON
|
TRIPLE H FIELD SERVICES, LLC
($302,620)
|
|
|
6342-77-001
|
LAMAR
|
PARIS
|
$60,000
|
BU0271B
|
RMC - 634277001
|
02/14/2019
|
11/15/2023
|
JANITORIAL MAINT
|
KLEEN SWEEP SERVICES
($30,011)
|
|
|
6342-07-001
|
LAMB
|
LUBBOCK
|
$387,000
|
US0084
|
RMC - 634207001
|
02/06/2019
|
11/15/2023
|
CALL OUT TRAF CONTROL
|
BARRICADES UNLIMITED
($539,150)
|
|
|
6341-02-001
|
LA SALLE
|
LAREDO
|
$299,969
|
IH0035
|
RMC - 634102001
|
02/12/2019
|
11/15/2023
|
INSTL OF TRAF SIG
|
TRIPLE H FIELD SERVICES, LLC
($303,621)
|
|
|
0952-01-060
|
LIBERTY
|
BEAUMONT
|
$2,879,633
|
FM 1008
|
C 952-1-60
|
02/05/2019
|
11/15/2023
|
WIDEN/TWO-COURSE SURF TREATMENT
|
ANGEL BROTHERS HOLDINGS CORP.
($2,730,449)
|
|
|
6333-79-001
|
LIBERTY
|
BEAUMONT
|
$835,081
|
SH0105
|
RMC - 633379001
|
02/05/2019
|
11/15/2023
|
OVERLAY AND PAVMT REPAIR
|
ANGEL BROTHERS HOLDINGS CORP.
($780,012)
|
|
|
0783-01-098
|
LUBBOCK
|
LUBBOCK
|
$12,274,262
|
SL 289
|
C 783-1-98
|
02/06/2019
|
11/15/2023
|
MILL,INLAY,FABRIC,SMA,& STRIPING
|
ALLEN BUTLER CONSTRUCTION, INC.
($13,802,666)
|
|
|
0880-04-032
|
LUBBOCK
|
LUBBOCK
|
$19,047,325
|
FM 179
|
STP 2013(649)
|
02/05/2019
|
11/15/2023
|
GRADE, BASE, ACP
|
ALLEN BUTLER CONSTRUCTION, INC.
($18,836,295)
|
|
|
0905-00-092
|
LUBBOCK
|
LUBBOCK
|
$4,028,195
|
VA
|
C 905-00-92
|
02/06/2019
|
11/15/2023
|
PAVMT MARKERS
|
L&L COMPANY
($4,451,653)
|
|
|
6342-05-001
|
LUBBOCK
|
LUBBOCK
|
$539,000
|
IH0027
|
RMC - 634205001
|
02/06/2019
|
11/15/2023
|
CALL OUT TRAF CONTROL
|
BARRICADES UNLIMITED
($650,350)
|
|
|
1842-01-016
|
MARTIN
|
ODESSA
|
$1,216,324
|
FM 26
|
C 1842-1-16
|
02/05/2019
|
11/15/2023
|
IMPROVE DRAINAGE
|
RK HALL, LLC
($935,181)
|
|
|
0209-01-063
|
MCLENNAN
|
WACO
|
$856,847
|
SL 2
|
NH 2019(440)
|
02/05/2019
|
11/15/2023
|
MILL/OVLY
|
TEXAS MATERIALS GROUP, INC.
($1,014,137)
|
|
|
6335-03-001
|
MEDINA
|
SAN ANTONIO
|
$22,714
|
SH0173
|
BPM - 633503001
|
02/13/2019
|
11/15/2023
|
BRIDGE PREVENT MAINT
|
SHANNON-MONK, INC.
($29,550)
|
|
|
6337-15-001
|
MONTGOMERY
|
HOUSTON
|
$468,091
|
IH0045
|
RMC - 633715001
|
02/05/2019
|
11/15/2023
|
GUARDRAIL REPAIR
|
ISI CONTRACTING, INC.
($451,885)
|
|
|
6337-16-001
|
MONTGOMERY
|
HOUSTON
|
$265,600
|
IH0045
|
RMC - 633716001
|
02/12/2019
|
11/15/2023
|
ASPH PAVMT REPAIR
|
MAIN LANE INDUSTRIES LTD.
($257,100)
|
|
|
2560-01-083
|
NACOGDOCHES
|
LUFKIN
|
$1,590,357
|
SL 224
|
C 2560-1-83
|
02/06/2019
|
11/15/2023
|
RESURF WITH THIN OVERLAY MIXTURE
|
DREWERY CONSTRUCTION COMPANY, INCORPORATED
($1,560,111)
|
|
|
2590-02-010
|
NACOGDOCHES
|
LUFKIN
|
$3,995,249
|
FM 2609
|
STP 2019(446)
|
02/05/2019
|
11/15/2023
|
RECON AND WIDEN PAVMT
|
PINTO CONSTRUCTION CO., INC.
($3,823,596)
|
|
|
6333-09-001
|
NAVARRO
|
DALLAS
|
$262,728
|
IH0045
|
BPM - 633309001
|
02/12/2019
|
11/15/2023
|
BPM - BRIDGE REPAIR
|
CHAMPION INFRASTRUCTURE, LLC
($249,287)
|
|
|
6337-36-001
|
NAVARRO
|
DALLAS
|
$350,900
|
FM0739
|
RMC - 633736001
|
02/05/2019
|
11/15/2023
|
TREE AND BRUSH RMVL AND TRIM
|
BOEN LANDSCAPING & IRRIGATION, LLC
($276,986)
|
|
|
6335-67-001
|
NEWTON
|
BEAUMONT
|
$824,166
|
FM2829
|
RMC - 633567001
|
02/05/2019
|
11/15/2023
|
FM 2829 OVERLAY
|
TEXAS MATERIALS GROUP, INC.
($735,834)
|
|
|
1069-01-035
|
NUECES
|
CORPUS CHRISTI
|
$3,585,320
|
SH 357
|
STP 2019(572)HES
|
02/05/2019
|
11/15/2023
|
IMPROVE TRAF SIG AND INTERCON SIG
|
FLORIDA TRAFFIC CONTROL DEVICES, INC.
($3,511,807)
|
|
|
6341-63-001
|
NUECES
|
CORPUS CHRISTI
|
$1,001,303
|
US0077
|
RMC - 634163001
|
02/05/2019
|
11/15/2023
|
ILLUM MAINATENANCE
|
TRAF-TEX, INC.
($969,970)
|
|
|
0710-02-068
|
ORANGE
|
BEAUMONT
|
$7,686,177
|
FM 105
|
C 710-2-68
|
02/06/2019
|
11/15/2023
|
MILL, ACP, JOINT SEAL
|
HERITAGE ASPHALT COMPANY LLC
($4,885,039)
|
|
|
1601-01-033
|
PARKER
|
FORT WORTH
|
$482,911
|
FM 730
|
CM 2019(500)
|
02/06/2019
|
11/15/2023
|
SIGNAL & INTERS IMPRVS
|
AMERICAN LIGHTING AND SIGNALIZATION, LLC
($552,724)
|
|
|
6327-81-001
|
PARKER
|
FORT WORTH
|
$120,533
|
IH0020
|
RMC - 632781001
|
02/12/2019
|
11/15/2023
|
ASBESTOS ABATEMENT
|
CHAMPION INFRASTRUCTURE, LLC
($156,286)
|
|
|
6338-69-001
|
PARKER
|
FORT WORTH
|
$377,738
|
IH0020
|
RMC - 633869001
|
02/05/2019
|
11/15/2023
|
REFLECTORIZED PVMNT MRK AND MARKERS
|
REPUBLIC TRAFFIC SAFETY, INC.
($325,062)
|
|
|
6340-52-001
|
POLK
|
LUFKIN
|
$278,424
|
US0059
|
RMC - 634052001
|
02/13/2019
|
11/15/2023
|
MOW OF RIGHT-OF-WAY AND LITTER REMVA...
|
ROY LEE WALKER
($259,659)
|
|
|
0041-07-106
|
POTTER
|
AMARILLO
|
$4,987,164
|
US 87
|
BR 2019(457)
|
02/06/2019
|
11/15/2023
|
BRIDGE REPL AND APPROACHES
|
STATELINE CONSTRUCTION, LLC
($4,976,890)
|
|
|
0235-03-034
|
REAL
|
SAN ANGELO
|
$1,015,497
|
SH 55
|
STP 2019(508)HES
|
02/05/2019
|
11/15/2023
|
PROFILE EDGELINE AND CENTERLINE MRK
|
TRP CONSTRUCTION GROUP, LLC
($1,009,258)
|
|
|
0180-02-040
|
REFUGIO
|
CORPUS CHRISTI
|
$12,352,440
|
SH 35
|
STP 2019(579)HES
|
02/06/2019
|
11/15/2023
|
SAFETY TRT FIXED OBJECTS, INSTL PASS...
|
HUNTER INDUSTRIES, LTD.
($12,619,232)
|
|
|
0049-14-012
|
ROBERTSON
|
BRYAN
|
$2,034,389
|
FM 46
|
STP 2019(497)
|
02/05/2019
|
11/15/2023
|
GRDG, WDN, STRCS, BASE, SURF, SGNS,...
|
KNIFE RIVER CORPORATION - SOUTH
($1,723,097)
|
|
|
0009-04-071
|
ROCKWALL
|
DALLAS
|
$1,094,108
|
SH 66
|
C 9-4-71
|
02/06/2019
|
11/15/2023
|
FULL DEPTH CONC PAVMT REPAIR
|
ROY JORGENSEN ASSOCIATES, INC.
($1,154,288)
|
|
|
0158-01-082
|
RUNNELS
|
SAN ANGELO
|
$14,638,666
|
US 67
|
NH 2019(396)
|
02/06/2019
|
11/15/2023
|
ACP OVERLAY
|
KIEWIT INFRASTRUCTURE SOUTH CO.
($16,352,620)
|
|
|
6341-93-001
|
SAN AUGUSTINE
|
LUFKIN
|
$184,549
|
US0096
|
RMC - 634193001
|
02/27/2019
|
11/15/2023
|
MOW RIGHT OF WAY AND LITTER RMVL
|
P-VILLE, INCORPORATED
($181,463)
|
|
|
6340-53-001
|
SAN JACINTO
|
LUFKIN
|
$160,956
|
US0059
|
RMC - 634053001
|
02/13/2019
|
11/15/2023
|
MOW OF RIGHT-OF-WAY AND LITTER REMVA...
|
ROY LEE WALKER
($139,906)
|
|
|
0867-07-013
|
SAN SABA
|
BROWNWOOD
|
$2,432,790
|
RM 501
|
STP 2019(478)HES
|
02/06/2019
|
11/15/2023
|
UPGRADE GUARDRAIL
|
BIG CREEK CONSTRUCTION, LTD.
($3,876,626)
|
|
|
0066-03-041
|
SHERMAN
|
AMARILLO
|
$14,893,378
|
US 287
|
NH 2019(458)
|
02/05/2019
|
11/15/2023
|
OVERLAY
|
RK HALL, LLC
($14,540,199)
|
|
|
6341-13-001
|
SMITH
|
TYLER
|
$3,143,855
|
SH0064
|
RMC - 634113001
|
02/05/2019
|
11/15/2023
|
MILL & INLAY
|
LONGVIEW BRIDGE AND ROAD, LTD.
($3,363,242)
|
|
|
0908-00-088
|
TAYLOR
|
ABILENE
|
$2,552,057
|
VA
|
NH 2019(516)
|
02/05/2019
|
11/15/2023
|
FY 2019 TRAF CONTROL DEVICES
|
FLAT LINE, INC.
($1,682,111)
|
|
|
6342-08-001
|
TERRY
|
LUBBOCK
|
$296,500
|
US0062
|
RMC - 634208001
|
02/06/2019
|
11/15/2023
|
CALL OUT TRAF CONTROL SERVICES
|
BARRICADES UNLIMITED
($418,850)
|
|
|
6327-15-001
|
TRAVIS
|
AUSTIN
|
$4,053,070
|
FM0734
|
RMC - 632715001
|
02/05/2019
|
11/15/2023
|
REPAIR, REPLACE, AND UPGRADE MBGF
|
K-BAR SERVICES, INC.
($4,550,444)
|
|
|
6339-63-001
|
TRAVIS
|
AUSTIN
|
$276,572
|
RM2244
|
RMC - 633963001
|
02/26/2019
|
11/15/2023
|
CULVERT REPL
|
CHAMPION INFRASTRUCTURE, LLC
($318,874)
|
|
|
0200-07-054
|
TYLER
|
BEAUMONT
|
$5,852,881
|
US 69
|
NH 2019(676)
|
02/05/2019
|
11/15/2023
|
MILL AND OVERLAY
|
TEXAS MATERIALS GROUP, INC.
($4,390,336)
|
|
|
0200-08-056
|
TYLER
|
BEAUMONT
|
$328,925
|
US 69
|
STP 2019(509)HES
|
02/06/2019
|
11/15/2023
|
SAFETY TREAT FIXED OBJECTS
|
ODUM SERVICES, LLC
($348,025)
|
|
|
0520-05-050
|
UPSHUR
|
ATLANTA
|
$4,133,448
|
SH 155
|
C 520-5-50
|
02/05/2019
|
11/15/2023
|
PLANING, ACP & PAV MRKS
|
MADDEN CONTRACTING COMPANY, LLC.
($3,772,059)
|
|
|
6338-56-001
|
VAL VERDE
|
LAREDO
|
$333,505
|
US0277
|
RMC - 633856001
|
02/05/2019
|
11/15/2023
|
GUARDRAIL REPAIRS
|
K-BAR SERVICES, INC.
($358,785)
|
|
|
6341-12-001
|
VAN ZANDT
|
TYLER
|
$289,497
|
SH0110
|
RMC - 634112001
|
02/12/2019
|
11/15/2023
|
GUARDRAIL
|
R & G CONSTRUCTION, LLC
($265,678)
|
|
|
6340-77-001
|
WALKER
|
BRYAN
|
$441,225
|
SH0030
|
RMC - 634077001
|
02/05/2019
|
11/15/2023
|
SPOT BASE REPAIR
|
ISI CONTRACTING, INC.
($513,435)
|
|
|
6320-47-001
|
WASHINGTON
|
BRYAN
|
$532,510
|
SH0105
|
BPM - 632047001
|
02/05/2019
|
11/15/2023
|
SCOUR REPAIR
|
SJ&J CONSTRUCTION, LLC
($510,520)
|
|
|
3173-01-004
|
WHARTON
|
YOAKUM
|
$3,444,828
|
FM 3086
|
C 3173-1-4
|
02/06/2019
|
11/15/2023
|
RESTORE EXIST ROADWAY
|
ANGEL BROTHERS HOLDINGS CORP.
($3,597,289)
|
|
|
6327-24-001
|
WHARTON
|
YOAKUM
|
$20,880
|
FM0102
|
RMC - 632724001
|
02/20/2019
|
11/15/2023
|
WHARTON AO/MAINT OFFICE JANITORIAL S...
|
MAXPRO ENTERPRISE LLC
($17,220)
|
|
|
6323-20-001
|
WICHITA
|
WICHITA FALLS
|
$259,402
|
SH0025
|
RMC - 632320001
|
02/14/2019
|
11/15/2023
|
CULVERT MAINT & MODIFICATION
|
EARTH BUILDERS, L.P.
($278,371)
|
|
|
0440-01-042
|
WILLIAMSON
|
AUSTIN
|
$6,825,458
|
SH 138
|
STP 2019(506)
|
02/05/2019
|
11/15/2023
|
ADD SHOULDERS AND REHAB ROADWAY
|
TTG UTILITIES, LP
($7,208,328)
|
|
|
2211-02-030
|
WILLIAMSON
|
AUSTIN
|
$188,338
|
FM 1460
|
CC 2211-2-30
|
02/06/2019
|
11/15/2023
|
INSTL MEDIAN BREAK AND LEFT TURN LAN...
|
ANGEL BROTHERS HOLDINGS CORP.
($251,066)
|
|
|
6337-29-001
|
WISE
|
FORT WORTH
|
$561,560
|
US0380
|
RMC - 633729001
|
02/05/2019
|
11/15/2023
|
THERMOPLSDTIC STRIPING AND HANDWORK
|
STRIPE-A-ZONE, INC.
($532,264)
|