HOPKINS SH 19 (0400-02-053)

Items: 49

County: HOPKINS
Length: N/A
Highway: SH 19
District: PARIS
Control Number: 0400-02-053
DBE Goal: N/A
Project: NH 2019(503)
Guaranty: N/A
Time: 48 WORKING DAYS
Engineer's Estimate: $764,387.29
Date: 02/06/2019 (7 years ago)
Contract Number: N/A
Type: INTERSECTION & OPERATIONAL IMPROVMN
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (7)
E
Engineer's Estimate
$764,387.29
$837,425.93
Over/Under Est: 9.56% $73,038.64
Over/Under Est: 13.62% $104,106.56
Amt Left: 3.71% $31,067.92
Over/Under Est: 16.87% $128,969.16
Amt Left: 6.68% $55,930.52
Delta: -2.86% -$24,862.60
Over/Under Est: 21.68% $165,712.27
Amt Left: 11.07% $92,673.63
Delta: -4.11% -$36,743.11
Over/Under Est: 29.85% $228,179.26
Amt Left: 18.53% $155,140.62
Delta: -6.72% -$62,466.99
$1,173,770.45
Over/Under Est: 53.56% $409,383.16
Amt Left: 40.16% $336,344.52
Delta: -18.26% -$181,203.90
$1,201,223.00
Over/Under Est: 57.15% $436,835.71
Amt Left: 43.44% $363,797.07
Delta: -2.34% -$27,452.55

Bid Items & Bid Tabulations

49 Total 0 of 49
HOPKINS  |  SH 19  |  PARIS  |  0400-02-053  |  02/06/2019  |  $764,387.29  |  NH 2019(503)  |  INTERS & OPERATIONAL IMPROVMN  |  48 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
SAMMY GIST ENTERPRISES, INC.
B & E CONSTRUCTION INC
RICHARD DRAKE CONSTRUCTION COMPANY, L.P.
LONGVIEW BRIDGE AND ROAD, LTD.
EAST TEXAS BRIDGE, INC.
RK HALL, LLC
FNH CONSTRUCTION, LLC
PREPARING ROW
STA 21.000 $1,500.000 $467.500 $1,000.000 $500.000 $600.000 $1,000.000 $935.000 $3,700.000
REMOVING CONC (DRIVEWAYS)
SY 143.000 $10.500 $20.000 $15.000 $26.250 $35.000 $20.000 $16.500 $20.000
EXCAVATION (SPECIAL)
CY 900.000 $9.250 $10.000 $15.000 $55.400 $14.500 $20.000 $39.660 $30.000
SUBGRADE WIDENING (ORD COMP)
STA 21.000 $300.000 $1,000.000 $200.000 $880.000 $950.000 $500.000 $2,061.100 $450.000
EMBANKMENT (FINAL)(DENS CONT)(TY A)
CY 719.000 $13.000 $30.000 $25.000 $30.000 $13.750 $20.000 $67.080 $30.000
BACKFILL (TY B)
STA 21.000 $115.000 $150.000 $170.000 $450.000 $315.000 $400.000 $397.210 $250.000
ROAD GRADER WORK (ORD COMP)
STA 21.000 $175.000 $350.000 $155.000 $250.000 $365.000 $350.000 $794.430 $250.000
BLOCK SODDING
SY 3,690.000 $4.500 $3.850 $5.000 $3.750 $4.150 $4.000 $4.130 $6.500
STRAW/HAY MLCH SEED(PERM)(RURAL)(CLAY)
SY 5,358.000 $0.250 $0.673 $1.000 $0.850 $0.420 $0.700 $0.420 $2.000
VEGETATIVE WATERING
MG 152.000 $10.500 $10.000 $10.000 $50.000 $5.000 $20.000 $78.400 $58.000
SALV, HAUL & STKPL RCL APH PV (0 TO 2")
SY 8,268.000 $6.500 $2.000 $5.000 $3.250 $3.000 $3.000 $2.090 $15.000
SALV,HAUL & STKPL RCL APH PV (2")
SY 1,950.000 $1.150 $2.000 $3.000 $3.500 $4.350 $3.000 $4.130 $20.000
D-GR HMA(SQ) TY-B PG64-22
TON 2,239.000 $80.000 $113.850 $100.000 $106.400 $115.000 $105.000 $130.470 $90.000
D-GR HMA(SQ) TY-C PG64-22
TON 1,454.000 $100.000 $100.900 $110.000 $94.300 $115.000 $110.000 $132.500 $110.000
D-GR HMA(SQ) TY-F PG64-22
TON 154.000 $150.000 $155.950 $170.000 $145.750 $200.000 $175.000 $249.130 $140.000
RC PIPE (CL III)(18 IN)
LF 516.000 $40.000 $38.500 $48.000 $55.000 $42.000 $50.000 $55.000 $85.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 32.000 $575.000 $632.500 $720.000 $620.000 $615.000 $750.000 $715.000 $85.000
REMOV STR (PIPE)
EA 15.000 $285.000 $275.000 $360.000 $1,650.000 $300.000 $400.000 $330.000 $500.000
MOBILIZATION
LS 1.000 $68,742.890 $65,000.000 $41,356.850 $71,250.000 $90,000.000 $80,000.000 $93,663.230 $100,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 3.000 $2,500.000 $2,000.000 $5,000.000 $2,200.000 $3,800.000 $5,000.000 $11,974.250 $8,500.000
ROCK FILTER DAMS (INSTALL) (TY 1)
LF 120.000 $29.000 $37.400 $30.000 $43.000 $23.000 $45.000 $23.100 $30.000
ROCK FILTER DAMS (REMOVE)
LF 120.000 $12.000 $11.000 $8.000 $11.000 $9.000 $22.000 $8.800 $15.000
BACKHOE WORK (EROSION & SEDMT CONT)
HR 40.000 $110.000 $25.000 $65.000 $85.000 $200.000 $100.000 $171.210 $150.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 180.000 $2.350 $3.300 $3.000 $6.500 $3.850 $5.500 $3.850 $4.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 180.000 $1.150 $1.100 $1.000 $1.100 $2.200 $3.000 $2.200 $2.000
INTERSECTIONS (ACP)
SY 2,673.000 $25.000 $18.000 $27.000 $14.700 $30.000 $50.000 $18.920 $35.000
DRIVEWAYS (CONC)
SY 100.000 $65.000 $110.000 $95.000 $100.000 $85.000 $100.000 $104.500 $85.000
DRIVEWAYS (ACP)
SY 753.000 $25.000 $30.000 $45.000 $19.250 $40.000 $50.000 $68.030 $42.000
MAILBOX INSTALL-S (TWG-POST) TY 4
EA 4.000 $229.000 $236.500 $750.000 $225.000 $235.000 $450.000 $236.500 $650.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 1.000 $600.000 $488.000 $600.000 $465.000 $490.000 $650.000 $488.400 $650.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 11.000 $550.000 $626.000 $610.000 $580.000 $625.000 $750.000 $625.900 $650.000
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
EA 7.000 $675.000 $757.000 $650.000 $710.000 $755.000 $975.000 $756.800 $650.000
REMOVE SM RD SN SUP&AM
EA 17.000 $78.000 $88.000 $85.000 $85.000 $90.000 $130.000 $88.000 $50.000
WK ZN PAV MRK NON-REMOV (W)24"(SLD)
LF 40.000 $3.000 $5.500 $5.000 $7.000 $5.500 $5.500 $7.700 $20.000
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 5,775.000 $0.150 $1.100 $1.000 $0.750 $1.100 $1.100 $0.830 $1.000
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 200.000 $0.950 $1.000 $4.000 $1.500 $1.200 $2.000 $1.160 $5.000
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 250.000 $1.150 $1.000 $5.000 $1.500 $1.200 $2.000 $1.160 $5.000
REFL PAV MRK TY I (W)8"(SLD)(090MIL)
LF 2,200.000 $0.500 $0.935 $2.000 $1.250 $0.950 $1.000 $1.380 $6.000
REFL PAV MRK TY I (W)24"(SLD)(090MIL)
LF 82.000 $5.500 $6.600 $10.000 $10.000 $6.600 $6.600 $11.000 $20.000
REFL PAV MRK TY I (W)(ARROW)(090MIL)
EA 9.000 $85.000 $165.000 $120.000 $165.000 $165.000 $165.000 $181.500 $250.000
REFL PAV MRK TY I (W)(WORD)(090MIL)
EA 7.000 $110.000 $198.000 $160.000 $185.000 $200.000 $200.000 $203.500 $250.000
REF PAV MRK TY I(W)36"(YLD TRI)(090MIL)
EA 20.000 $17.000 $60.500 $20.000 $97.000 $60.000 $60.000 $106.700 $500.000
RE PM W/RET REQ TY I (W)4"(SLD)(090MIL)
LF 4,650.000 $0.200 $1.650 $1.000 $1.000 $1.650 $1.650 $0.980 $1.000
RE PM W/RET REQ TY I (Y)4"(BRK)(090MIL)
LF 240.000 $0.210 $3.300 $5.000 $3.750 $3.300 $3.300 $4.130 $1.000
RE PM W/RET REQ TY I (Y)4"(SLD)(090MIL)
LF 5,825.000 $0.200 $1.650 $1.000 $1.000 $1.650 $1.650 $0.980 $1.000
REFL PAV MRKR TY I-C
EA 90.000 $2.500 $5.500 $10.000 $10.000 $5.500 $5.500 $11.000 $15.000
REFL PAV MRKR TY II-A-A
EA 75.000 $3.250 $5.500 $11.000 $10.000 $5.500 $5.500 $11.000 $15.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 180.000 $90.000 $175.000 $120.000 $120.000 $65.000 $100.000 $123.330 $150.000
TMA (STATIONARY)
DAY 96.000 $200.000 $140.000 $210.000 $300.000 $100.000 $200.000 $486.580 $450.000
Totals: $764,387.290 $837,425.934 $868,493.850 $893,356.450 $930,099.560 $992,566.550 $1,173,770.450 $1,201,223.000