CALLAHAN SH 36 (0181-03-025)

Items: 23

County: CALLAHAN
Length: N/A
Highway: SH 36
District: ABILENE
Control Number: 0181-03-025
DBE Goal: N/A
Project: STP 2019(443)HES
Guaranty: N/A
Time: 68 WORKING DAYS
Engineer's Estimate: $1,948,115.06
Date: 02/05/2019 (7 years ago)
Contract Number: N/A
Type: MILLED EDGELINE RUMBLE STRIPS
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (6)
E
Engineer's Estimate
$1,948,115.06
$1,298,584.91
Over/Under Est: -33.34% -$649,530.15
Over/Under Est: -28.62% -$557,577.09
Amt Left: 7.08% $91,953.06
Over/Under Est: -28.31% -$551,498.18
Amt Left: 7.55% $98,031.97
Delta: -0.44% -$6,078.91
Over/Under Est: -11.5% -$224,016.60
Amt Left: 32.77% $425,513.55
Delta: -23.45% -$327,481.58
Over/Under Est: -8.97% -$174,728.07
Amt Left: 36.56% $474,802.08
Delta: -2.86% -$49,288.53
Over/Under Est: 3.91% $76,116.64
Amt Left: 55.88% $725,646.79
Delta: -14.14% -$250,844.71

Bid Items & Bid Tabulations

23 Total 0 of 23
CALLAHAN  |  SH 36  |  ABILENE  |  0181-03-025  |  02/05/2019  |  $1,948,115.06  |  STP 2019(443)HES  |  MILLED EDGELINE RUMBLE STRIPS  |  68 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
FLAT LINE, INC.
SURFACE PREPARATION TECHNOLOGIES, LLC
DOUBLE A CONTRACTING, L.P.
TRP CONSTRUCTION GROUP, LLC
STRIPING TECHNOLOGY, L.P.
TOTAL HIGHWAY MAINTENANCE, LLC
MOBILIZATION
LS 1.000 $100,000.000 $500.000 $102,000.000 $10,000.000 $150,000.000 $75,000.000 $125,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 4.000 $5,000.000 $10.000 $10.000 $4,500.000 $20,000.000 $10,000.000 $18,000.000
RUMBLE STRIPS (SHOULDER)
LF 791,569.000 $0.140 $0.115 $0.130 $0.120 $0.150 $0.210 $0.160
RUMBLE STRIPS (CENTERLINE)
LF 258,820.000 $0.120 $0.140 $0.130 $0.170 $0.170 $0.240 $0.180
INSTL DEL ASSM (D-SW)SZ 1(FLX)SRF
EA 17.000 $150.000 $175.000 $200.000 $73.000 $43.000 $175.000 $245.000
REFL PAV MRK TY I (W)4"(DOT)(100MIL)
LF 348.000 $5.000 $1.000 $1.000 $1.320 $1.350 $1.000 $2.000
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 2,504.000 $2.000 $1.000 $1.000 $0.750 $0.840 $1.000 $1.700
REFL PAV MRK TY I (Y)24"(SLD)(100MIL)
LF 1,318.000 $10.000 $4.500 $4.500 $5.000 $6.100 $5.300 $6.000
RE PM W/RET REQ TY I (W)4"(BRK)(100MIL)
LF 14,970.000 $1.000 $0.250 $0.250 $0.350 $0.390 $0.420 $0.450
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 858,707.000 $0.300 $0.240 $0.240 $0.260 $0.320 $0.380 $0.400
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
LF 94,750.000 $0.300 $0.250 $0.250 $0.270 $0.380 $0.420 $0.450
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 626,918.000 $0.300 $0.240 $0.240 $0.270 $0.320 $0.380 $0.400
REF PROF PAV MRK TY I(W)4"(SLD)(100MIL)
LF 833,969.000 $1.000 $0.570 $0.550 $0.585 $0.550 $0.600 $0.740
REF PROF PAV MRK TY I(Y)4"(BRK)(100MIL)
LF 60,120.000 $0.800 $0.600 $0.600 $0.650 $0.650 $1.000 $0.850
REF PROF PAV MRK TY I(Y)4"(SLD)(100MIL)
LF 181,030.000 $0.650 $0.600 $0.550 $0.590 $0.550 $0.600 $0.740
PREFAB PAV MRK TY C (W) (24") (SLD)
LF 1,199.000 $15.000 $14.000 $14.000 $12.000 $13.500 $13.500 $15.750
PREFAB PAV MRK TY C (W) (ARROW)
EA 19.000 $300.000 $250.000 $250.000 $190.000 $222.000 $180.000 $279.000
PREFAB PAV MRK TY C (W) (WORD)
EA 9.000 $350.000 $250.000 $250.000 $250.000 $295.000 $225.000 $354.000
PRE PM TY C(ACC PRK)(BL&WH)(W/BORDR)LG
EA 1.000 $500.000 $250.000 $250.000 $325.000 $257.000 $250.000 $595.000
REFL PAV MRKR TY I-C
EA 1,066.000 $5.000 $3.000 $3.000 $2.750 $3.250 $2.800 $3.650
REFL PAV MRKR TY II-A-A
EA 16,184.000 $3.000 $2.400 $2.800 $2.650 $3.250 $2.800 $3.650
PREFORMED CENTERLINE RUMBLE STRIP
LF 15,345.000 $5.000 $5.750 $5.750 $5.500 $6.000 $3.500 $5.250
TMA (MOBILE OPERATION)
DAY 68.000 $250.000 $10.000 $10.000 $170.000 $500.000 $200.000 $289.000
Totals: $1,948,115.060 $1,298,584.915 $1,390,537.970 $1,396,616.885 $1,724,098.460 $1,773,386.990 $2,024,231.700