| Control Number | County | Highway | Bid Date | Low Bidder | Pay Estimates | % of Contract | Amount | % Complete | Contract Amount |
|---|---|---|---|---|---|---|---|---|---|
| 0273-04-045 | WILLIAMSON | US 183 | 11/05/2025 | JOE BLAND CONSTRUCTION LLC | 04/26 | 03/26 | 02/26 | 0.44% | $64,414.16 | 1.00% | $14,639,581.45 |
| 0272-06-031 | LAMPASAS | US 183 | 10/09/2025 | BIG CREEK CONSTRUCTION, LTD. | 04/26 | 03/26 | 02/26 | 01/26 | 0.20% | $109,520.82 | 14.00% | $54,760,408.87 |
| 0172-06-107 | TARRANT | US 287 | 08/08/2025 | LIGHT IT UP ELECTRIC | 05/26 | 04/26 | 03/26 | 02/26 | 01/26 | 0.00% | $0.00 | 36.00% | $1,430,726.80 |
| 0071-06-063 | GILLESPIE | US 87 | 07/02/2025 | TEXAS MATERIALS GROUP, INC. | 05/26 | 04/26 | 0.30% | $27,472.46 | 0.00% | $9,157,488.33 |
| 6468-25-001 | TRAVIS | US0183 | 05/14/2025 | DIGG COMMERCIAL, LLC | 04/26 | 03/26 | 02/26 | 01/26 | 12/25 | 3.40% | $4,997.12 | 7.00% | $146,974.00 |
| 1926-01-019 | CORYELL | FM 1829 | 02/06/2025 | BIG CREEK CONSTRUCTION, LTD. | 04/26 | 03/26 | 02/26 | 01/26 | 12/25 | 0.42% | $20,379.44 | 96.00% | $4,852,247.93 |
| 0035-03-047 | CONCHO | US 83 | 11/07/2024 | 3LW CIVIL LLC | 05/26 | 04/26 | 03/26 | 02/26 | 01/26 | 0.17% | $25,478.48 | 89.00% | $14,987,340.80 |
| 0914-00-507 | TRAVIS | VA | 07/10/2024 | TAYLOR CONTRACTING LLC | 04/26 | 03/26 | 02/26 | 01/26 | 12/25 | 3.89% | $100,082.19 | 88.00% | $2,572,807.00 |
| 0914-00-534 | TRAVIS | VA | 07/09/2024 | GARRET SHIELDS INFRASTRUCTURE | 04/26 | 03/26 | 02/26 | 01/26 | 12/25 | 0.00% | $0.00 | 116.00% | $1,968,905.00 |
| 6405-46-001 | TRAVIS | US0183 | 06/05/2024 | DIGG COMMERCIAL, LLC | 04/26 | 03/26 | 02/26 | 01/26 | 12/25 | 1.06% | $3,909.59 | 214.00% | $368,829.15 |
| 1308-01-025 | BELL | FM 1123 | 05/02/2024 | C. E. BARKER, LTD. | 04/26 | 03/26 | 02/26 | 01/26 | 12/25 | 0.16% | $8,298.60 | 100.00% | $5,186,627.56 |
| 0015-13-438 | TRAVIS | IH 35 | 05/02/2024 | HARPER BROTHERS CONSTRUCTION LLC | 05/26 | 04/26 | 03/26 | 02/26 | 01/26 | 0.12% | $42,242.25 | 71.00% | $35,201,874.49 |
| 0914-05-214 | WILLIAMSON | 3219 246 | 04/05/2024 | DAN WILLIAMS COMPANY | 02/25 | 01/25 | 12/24 | 11/24 | 10/24 | 0.52% | $10,504.48 | 100.00% | $2,020,092.67 |
| 6453-45-001 | TRAVIS | IH0035 | 03/13/2024 | AMERICAN INFRASTRUCTURE MAINTENANCE MANAGEMENT LLC | 03/25 | 02/25 | 01/25 | 12/24 | 11/24 | 7.71% | $136,043.27 | 98.00% | $1,764,504.11 |
| 0252-03-054 | BLANCO | US 281 | 03/06/2024 | TEXAS MATERIALS GROUP, INC. | 04/26 | 03/26 | 02/26 | 01/26 | 12/25 | 0.00% | $0.00 | 82.00% | $12,200,595.32 |
| 0986-01-046 | WILLIAMSON | FM 619 | 01/05/2024 | AUSTIN ENGINEERING CO., INC. | 08/25 | 07/25 | 06/25 | 05/25 | 04/25 | 3.01% | $43,246.61 | 98.00% | $1,436,764.60 |
| 0909-22-197 | MCLENNAN | CS | 01/04/2024 | ELECNOR BELCO ELECTRIC, INC. | 08/25 | 07/25 | 06/25 | 05/25 | 04/25 | 1.12% | $8,358.41 | 98.00% | $746,286.59 |
| 0700-03-149 | TRAVIS | SH 71 | 12/06/2023 | SICE, INC. | 04/26 | 03/26 | 02/26 | 01/26 | 12/25 | 0.28% | $14,486.25 | 13.00% | $5,173,660.07 |
| 1200-04-016 | WILLIAMSON | FM 1466 | 09/07/2023 | JOE BLAND CONSTRUCTION, L.P. | 04/26 | 03/26 | 02/26 | 01/26 | 12/25 | 1.20% | $71,626.10 | 98.00% | $5,968,841.75 |
| 0683-02-074 | TRAVIS | RM 620 | 08/03/2023 | SICE, INC. | 04/26 | 03/26 | 02/26 | 01/26 | 12/25 | 0.77% | $50,962.29 | 101.00% | $6,618,479.67 |
| 0113-07-072 | HAYS | US 290 | 06/28/2023 | E-Z BEL CONSTRUCTION, LLC | 12/24 | 11/24 | 10/24 | 09/24 | 08/24 | 0.17% | $3,333.34 | 100.00% | $1,960,789.39 |
| 6405-58-001 | TRAVIS | US0183 | 06/14/2023 | DIGG COMMERCIAL, LLC | 11/25 | 10/25 | 09/25 | 08/25 | 07/25 | 0.00% | $0.00 | 79.00% | $144,242.98 |