TRAVIS SH 71 (0700-03-149)

Items: 50

County: TRAVIS
Length: N/A
Highway: SH 71
District: AUSTIN
Control Number: 0700-03-149
DBE Goal: 0.0%
Project: F 2024(143)
Guaranty: N/A
Time: 170 WORKING DAYS
Engineer's Estimate: $7,238,185.61
Date: 12/06/2023 (2 years ago)
Contract Number: N/A
Type: INSTALL ADVANCED TRAFFIC MANAGEMENT SYSTEM
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (3)
E
Engineer's Estimate
$7,238,185.61
1
Awarded
$5,173,659.92
Over/Under Est: -28.52% -$2,064,525.69
$5,374,784.17
Over/Under Est: -25.74% -$1,863,401.44
Amt Left: 3.89% $201,124.25
$7,223,924.20
Over/Under Est: -0.2% -$14,261.41
Amt Left: 39.63% $2,050,264.28
Delta: -34.40% -$1,849,140.03
Subcontractor Percentage Amount
JBS UNDERGROUND, LLC 25.57% $1,322,904.88
ALL IN CONSTRUCTION, L.L.C. 3.86% $199,703.28
BUYERS BARRICADES AUSTIN, LLC 0.28% $14,486.25
NELSON LEWIS, INC. 0.00% $0.00
Total: 29.71% $1,537,094.41

Bid Items & Bid Tabulations

50 Total 0 of 50
TRAVIS  |  SH 71  |  AUSTIN  |  0700-03-149  |  12/06/2023  |  $7,238,185.61  |  F 2024(143)  |  INSTL ADVANCED TRAF MGT SYSTEM  |  170 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
SICE, INC.
THE LEVY COMPANY, INC.
LIGHT IT UP ELECTRIC
DRILL SHAFT (42 IN)
LF 23.000 $547.350 $772.107 $584.710 $768.000
DRILL SHAFT (48 IN)
LF 231.000 $561.570 $1,047.988 $634.370 $775.000
RIPRAP (CONC)(6 IN)
CY 10.000 $900.000 $1,158.094 $913.700 $1,200.000
MOBILIZATION
LS 1.000 $563,268.290 $348,711.027 $369,247.580 $445,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 9.000 $10,279.660 $10,968.203 $20,771.350 $16,000.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 10,000.000 $7.860 $2.985 $5.670 $5.400
BIODEG EROSN CONT LOGS (REMOVE)
LF 10,000.000 $2.400 $0.659 $1.150 $1.200
CONDT (PVC) (SCH 40) (2")
LF 1,705.000 $19.350 $36.767 $22.870 $19.200
CONDT (PVC) (SCH 40) (3") (CONC ENCSE)
LF 49,130.000 $16.050 $18.190 $21.390 $30.580
CONDT (PVC) (SCH 80) (2") (BORE)
LF 1,240.000 $31.530 $47.934 $25.420 $45.270
CONDT (PVC) (SCH 80) (3") (BORE)
LF 12,470.000 $49.030 $15.783 $24.060 $38.650
CONDT (RM) (3")
LF 1,060.000 $54.060 $105.137 $93.200 $93.000
ELEC CONDR (NO.14) INSULATED
LF 32,380.000 $1.210 $0.688 $0.810 $1.760
ELEC CONDR (NO.8) BARE
LF 280.000 $1.370 $1.527 $1.240 $1.420
ELEC CONDR (NO.8) INSULATED
LF 560.000 $1.650 $1.692 $1.270 $1.680
ELEC CONDR (NO.6) BARE
LF 450.000 $1.640 $1.633 $1.500 $2.570
ELEC CONDR (NO.6) INSULATED
LF 900.000 $2.020 $1.838 $1.620 $2.530
ELEC CONDR (NO.4) BARE
LF 680.000 $2.630 $2.309 $2.170 $3.200
ELEC CONDR (NO.4) INSULATED
LF 1,535.000 $2.920 $2.437 $2.340 $4.150
ELEC CONDR (NO.2) BARE
LF 400.000 $4.170 $3.446 $3.090 $5.300
ELEC CONDR (NO.2) INSULATED
LF 800.000 $4.520 $3.799 $3.330 $6.800
GROUND BOX TY A (122311)W/APRON
EA 25.000 $2,138.010 $1,137.686 $1,297.870 $1,350.000
ELC SRV TY D 120/240 060(NS)GS(N)SP(O)
EA 11.000 $6,850.000 $5,835.004 $6,336.460 $8,400.000
ELC SRV TY D 120/240 125(NS)GS(N)SP(O)
EA 1.000 $7,000.000 $6,646.941 $6,632.200 $9,197.000
INS OH SN SUP(40 FT BAL TEE)
EA 1.000 $33,689.080 $54,023.019 $51,206.200 $62,000.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 4.000 $12,408.640 $12,484.580 $1,223.370 $2,200.000
FIBER OPTIC CBL (SNGLE-MODE)(12 FIBER)
LF 2,160.000 $3.780 $5.508 $5.060 $2.400
FIBER OPTIC CBL (SNGLE-MODE)(144 FIBER)
LF 32,915.000 $5.550 $5.261 $3.450 $2.970
FIBER OPTIC SPLICE ENCLOSURE
EA 16.000 $2,377.670 $1,884.238 $1,482.950 $3,200.000
FIBER OPTIC PATCH PANEL (12 POSITION)
EA 12.000 $3,915.670 $1,149.286 $867.260 $2,850.000
FIBER OPTIC CABLE ROAD MARKER
EA 16.000 $121.000 $186.754 $51.470 $620.000
FIBER OPTIC PATCH PANEL (144 POSITION)
EA 2.000 $1,545.880 $9,698.185 $3,297.310 $12,800.000
ITS GRND MNT CAB (TY 6) (CONF 2)
EA 1.000 $18,166.670 $17,676.276 $15,874.520 $16,000.000
CCTV FIELD EQUIPMENT (ANALOG)
EA 11.000 $8,641.390 $7,404.127 $7,904.000 $8,700.000
CCTV MOUNT (POLE)
EA 11.000 $587.670 $422.622 $180.160 $418.000
ITS MULTI-DUCT CND (PVC-40)(CONC ENCSE)
LF 49,130.000 $45.000 $24.482 $26.170 $40.000
ITS MULTI-DUCT CND (PVC-80)(BORE)
LF 12,470.000 $74.130 $24.488 $28.510 $33.000
ITS MULTI-DUCT CND (RMC)
LF 1,060.000 $108.060 $162.117 $115.550 $112.000
GROUND BOX (PREPARE)
EA 8.000 $471.040 $658.093 $188.430 $450.000
INSTALL DMS (POLE MTD CABINET)
EA 1.000 $15,562.000 $5,232.039 $8,972.800 $22,000.000
ITS POLE (60 FT)(90 MPH)
EA 11.000 $33,426.490 $25,123.925 $22,660.800 $32,000.000
ITS POLE MNT CAB (TY 2)(CONF 1)
EA 11.000 $5,947.690 $5,084.364 $4,975.600 $9,600.000
ETHERNET SWITCH (INSTALL ONLY)
EA 12.000 $82.010 $150.654 $324.880 $500.000
MPEG 4 VIDEO ENCODER (INSTALL ONLY)
EA 11.000 $100.000 $150.654 $292.710 $500.000
TERMINAL SERVER (INSTALL ONLY)
EA 12.000 $100.000 $150.654 $292.710 $500.000
TMA (STATIONARY)
DAY 160.000 $279.830 $528.721 $220.920 $630.000
ITS GND BOX(PCAST) TY 1 (243660)W/APRN
EA 42.000 $4,828.900 $5,447.871 $6,548.490 $6,400.000
ITS GND BOX(PCAST) TY 2 (366060)W/APRN
EA 16.000 $8,800.000 $7,983.953 $10,324.780 $9,800.000
INSTALL OF CELLULAR MODEM
EA 12.000 $1,360.000 $831.372 $292.710 $560.000
SUBSURFACE UTIL LOCATE (OUTSIDE RDBED)
EA 10.000 $1,461.400 $2,095.136 $1,900.000 $3,500.000
Totals: $7,238,185.610 $5,173,660.057 $5,374,784.170 $7,223,924.200