Bid Cobra

WILLIAMSON US 183 (0273-04-045)

Items: 122

County: WILLIAMSON
Length: 11.7210 MILES
Highway: US 183
District: AUSTIN
Control Number: 0273-04-045
DBE Goal: 0.0%
Project: F 2026(117)
Guaranty: $100,000.00
Time: 186 WORKING DAYS
Engineer's Estimate: $19,572,839.89
Date: 11/05/2025 (7 months ago)
Contract Number: 11253005
Type: HIGHWAY IMPROVEMENT
Project ID: A00063983
Contract Type: Federal
Project Description: WIDEN WITH CONTINUOUS LEFT TURN LANE AND SHOULDERS
Mail/Deliver Bids To: N/A
KYLE RUSSELL
JEREMY MIKES
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (8)
E
Engineer's Estimate
$19,572,839.89
$14,639,581.45
Over/Under Est: -25.2% -$4,933,258.44
Over/Under Est: -24.98% -$4,890,017.72
Amt Left: 0.3% $43,240.72
$15,140,468.24
Over/Under Est: -22.65% -$4,432,371.65
Amt Left: 3.42% $500,886.79
Delta: -3.12% -$457,646.07
$15,440,401.85
Over/Under Est: -21.11% -$4,132,438.04
Amt Left: 5.47% $800,820.40
Delta: -1.98% -$299,933.61
$15,578,367.00
Over/Under Est: -20.41% -$3,994,472.89
Amt Left: 6.41% $938,785.55
Delta: -0.89% -$137,965.15
Over/Under Est: -19.89% -$3,892,900.46
Amt Left: 7.11% $1,040,357.98
Delta: -0.65% -$101,572.43
$15,689,948.00
Over/Under Est: -19.84% -$3,882,891.89
Amt Left: 7.17% $1,050,366.55
Delta: -0.06% -$10,008.57
$16,484,000.59
Over/Under Est: -15.78% -$3,088,839.30
Amt Left: 12.6% $1,844,419.14
Delta: -5.06% -$794,052.59
Subcontractor Percentage Amount
LONE STAR PAVING COMPANY 41.93% $6,138,376.50
ENVIRONMENTAL SAFETY SERVICES, INC. 9.02% $1,320,490.25
D. I. J. CONSTRUCTION, INC. 1.44% $210,809.97
BUYERS BARRICADES AUSTIN, LLC 0.44% $64,414.16
*AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. 0.17% $24,887.29
Total: 53.00% $7,758,978.17

Bid Items & Bid Tabulations

122 Total 0 of 122
WILLIAMSON  |  US 183  |  AUSTIN  |  0273-04-045  |  11/05/2025  |  $19,572,839.89  |  F 2026(117)  |  HWY IMPRV  |  186 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
JOE BLAND CONSTRUCTION LLC
TEXAS MATERIALS GROUP, INC.
HUNTER INDUSTRIES, LTD.
DAN WILLIAMS COMPANY
POSILLICO CIVIL, INC.
AARON CONCRETE CONTRACTORS, LLC
CHASCO CONSTRUCTORS
TEXAS ROAD LLC
PREPARING ROW
STA 293.000 $3,000.000 $750.000 $350.000 $732.600 $2,750.000 $218.000 $250.000 $500.000 $500.000
REMOV CONC (DRIVEWAYS)
SY 1,035.000 $25.000 $25.000 $20.000 $16.500 $16.000 $20.000 $18.000 $25.000 $39.000
REMOV CONC (MISC)
SY 44.000 $20.000 $30.000 $31.000 $29.700 $45.000 $142.000 $21.000 $20.000 $53.000
RMV (16") TRT/UNTRT BASE & ASPH PAV
SY 7,576.000 $12.000 $6.000 $8.020 $9.900 $6.500 $19.000 $12.000 $27.000 $9.000
EXCAV (ROADWAY)
CY 28,582.000 $14.000 $15.000 $11.750 $14.300 $15.000 $7.000 $4.500 $22.000 $22.000
EMBANK (FNL)(OC)(TY B)
CY 20,449.000 $20.000 $7.000 $8.500 $13.200 $16.000 $8.000 $4.500 $19.000 $9.000
FURN & PLACE TOPSOIL (4")
SY 77,641.000 $2.500 $2.000 $2.800 $2.040 $2.000 $1.000 $2.000 $2.000 $6.000
BROADCAST SEED (PERM_RURAL_CLAY)
SY 77,641.000 $0.300 $0.500 $0.160 $0.170 $0.250 $0.500 $0.300 $0.250 $0.330
BROADCAST SEED (TEMP_WARM)
SY 38,820.500 $0.400 $0.200 $0.140 $0.150 $0.130 $0.500 $0.150 $0.200 $0.280
BROADCAST SEED (TEMP_COOL)
SY 38,820.500 $0.400 $0.200 $0.140 $0.150 $0.170 $0.500 $0.200 $0.200 $0.280
VEGETATIVE WATERING
TGL 1,419.000 $30.000 $45.000 $67.000 $23.100 $5.000 $38.000 $32.000 $25.000 $50.000
SOIL RET BLKT(SL_MOD_CLAY_LONG)
SY 2,049.000 $4.500 $1.250 $3.270 $3.340 $1.000 $3.000 $1.150 $3.500 $1.940
SOIL RET BLKT(CHAN_PERM_4 PSF)
SY 68,272.000 $7.000 $2.000 $1.750 $1.790 $1.800 $2.000 $2.000 $2.000 $3.890
SOIL RET BLKT(CHAN_PERM_8 PSF)
SY 7,320.000 $10.000 $4.500 $2.720 $2.780 $4.000 $3.000 $4.500 $3.000 $3.890
PROOF ROLLING
HR 100.000 $100.000 $900.000 $110.000 $99.000 $80.000 $161.000 $135.000 $110.000 $120.000
FL BS (CMP IN PLC)(TY A GR 5)(FNAL POS)
CY 26,046.000 $80.000 $68.000 $52.000 $61.860 $55.000 $31.000 $68.000 $58.000 $57.000
PRIME COAT(MC-30 OR AE-P)
GAL 18,030.000 $4.500 $4.000 $4.200 $4.950 $3.300 $3.000 $6.000 $3.500 $3.680
D-GR HMA TY-B PG64-22
TON 18,945.000 $110.000 $80.000 $83.200 $95.150 $74.000 $75.000 $88.000 $77.000 $81.300
D-GR HMA TY-B PG64-22 (LEVEL-UP)
TON 452.000 $130.000 $92.000 $180.000 $102.300 $90.000 $89.000 $220.000 $92.000 $97.450
D-GR HMA TY-D PG76-22
TON 18,969.000 $145.000 $95.000 $103.700 $98.450 $91.000 $91.000 $111.000 $93.000 $99.130
D-GR HMA TY-D PG76-22 (LEVEL-UP)
TON 6,611.000 $130.000 $108.000 $102.000 $102.850 $100.000 $102.000 $122.000 $104.000 $110.820
TOM-C PG76-22 SAC-B
TON 12,942.000 $145.000 $117.000 $123.750 $116.050 $111.000 $111.000 $143.000 $115.000 $121.400
FLEXIBLE PAVEMENT STRUCTURE REPAIR(8")
SY 6,283.000 $60.000 $55.000 $54.000 $59.320 $52.000 $53.000 $61.000 $65.000 $57.920
PLANE & TEXT ASPH CONC PAV(0" TO 2")
SY 146,615.000 $2.500 $1.500 $1.650 $1.660 $1.150 $1.000 $0.750 $1.250 $1.270
CUT & RESTORING PAV
SY 1,035.000 $260.000 $200.000 $160.000 $161.480 $385.000 $309.000 $200.000 $510.000 $320.000
TRENCH EXCAVATION PROTECTION
LF 541.000 $10.000 $6.000 $1.000 $5.770 $10.000 $16.000 $3.000 $10.000 $18.000
DRILL SHAFT (RDWY ILL POLE) (30 IN)
LF 20.000 $300.000 $435.000 $400.000 $478.060 $450.000 $437.000 $490.000 $465.000 $491.580
RIPRAP (CONC)(5 IN)
CY 1,581.000 $575.000 $385.000 $635.000 $607.000 $475.000 $592.000 $600.000 $850.000 $330.000
RIPRAP (MOW STRIP)(4 IN)
CY 608.000 $650.000 $715.000 $650.000 $663.210 $700.000 $335.000 $860.000 $810.000 $540.000
RIPRAP (STONE PROTECTION)(18 IN)
CY 300.000 $195.000 $245.000 $240.000 $156.450 $200.000 $291.000 $200.000 $210.000 $260.000
CONC BOX CULV (5 FT X 4 FT)
LF 58.000 $585.000 $670.000 $1,025.000 $692.710 $560.000 $827.000 $1,000.000 $1,125.000 $1,200.000
CONC BOX CULV (6 FT X 3 FT)
LF 71.000 $525.000 $716.000 $1,025.000 $750.440 $650.000 $852.000 $975.000 $1,110.000 $1,600.000
CONC BOX CULV (6 FT X 4 FT)
LF 132.000 $565.000 $753.000 $1,125.000 $785.070 $700.000 $938.000 $2,100.000 $1,150.000 $1,400.000
CONC BOX CULV (6 FT X 5 FT)
LF 31.000 $780.000 $934.000 $1,260.000 $923.610 $700.000 $1,033.000 $1,400.000 $1,390.000 $1,900.000
CONC BOX CULV (6 FT X 6 FT)
LF 96.000 $825.000 $825.000 $1,375.000 $946.710 $725.000 $1,204.000 $2,600.000 $1,500.000 $1,400.000
RC PIPE (CL III)(18 IN)
LF 1,636.000 $100.000 $125.000 $60.000 $55.420 $72.000 $110.000 $97.000 $72.000 $87.000
RC PIPE (CL III)(24 IN)
LF 1,570.000 $115.000 $150.000 $72.000 $69.270 $82.000 $134.000 $130.000 $85.000 $98.000
RC PIPE (CL III)(30 IN)
LF 1,090.000 $120.000 $175.000 $108.000 $90.050 $103.000 $352.000 $320.000 $110.000 $340.000
RC PIPE (CL III)(36 IN)
LF 335.000 $210.000 $265.000 $170.000 $144.310 $140.000 $473.000 $430.000 $150.000 $450.000
HEADWALL (CH - PW - 0) (DIA= 30 IN)
EA 8.000 $9,750.000 $6,500.000 $8,800.000 $13,854.220 $8,500.000 $14,456.000 $13,000.000 $11,000.000 $13,500.000
HEADWALL (CH - PW - 0) (DIA= 36 IN)
EA 4.000 $14,000.000 $8,500.000 $13,650.000 $15,586.000 $9,000.000 $14,768.000 $17,000.000 $13,000.000 $16,000.000
HEADWALL (CH - PW - S) (DIA= 30 IN)
EA 1.000 $15,000.000 $9,000.000 $10,000.000 $16,163.260 $10,500.000 $14,456.000 $13,000.000 $11,000.000 $12,000.000
WINGWALL (PW - 1) (HW=4 FT)
EA 3.000 $15,000.000 $18,000.000 $13,500.000 $17,317.780 $17,000.000 $14,456.000 $13,000.000 $8,200.000 $20,000.000
WINGWALL (PW - 1) (HW=5 FT)
EA 2.000 $22,000.000 $19,500.000 $17,600.000 $19,626.820 $18,000.000 $19,760.000 $19,000.000 $12,500.000 $25,000.000
WINGWALL (PW - 1) (HW=6 FT)
EA 5.000 $30,000.000 $22,500.000 $25,500.000 $21,935.850 $24,000.000 $17,160.000 $21,000.000 $16,000.000 $30,000.000
WINGWALL (PW - 1) (HW=7 FT)
EA 3.000 $35,500.000 $30,500.000 $32,800.000 $35,790.080 $28,000.000 $29,120.000 $27,000.000 $22,000.000 $32,000.000
WINGWALL (PW - 1) (HW=8 FT)
EA 1.000 $38,000.000 $36,250.000 $40,000.000 $40,408.150 $30,000.000 $26,000.000 $32,000.000 $23,500.000 $37,000.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 54.000 $1,600.000 $2,250.000 $1,120.000 $2,078.130 $2,200.000 $6,276.000 $1,300.000 $2,600.000 $3,200.000
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 48.000 $2,100.000 $2,750.000 $1,385.000 $2,309.040 $2,300.000 $6,604.000 $1,600.000 $3,200.000 $4,700.000
SET (TY II) (30 IN) (RCP) (4: 1) (C)
EA 2.000 $3,200.000 $6,000.000 $1,423.000 $3,117.200 $2,800.000 $8,695.000 $2,100.000 $4,500.000 $5,800.000
SET (TY II) (30 IN) (RCP) (6: 1) (C)
EA 4.000 $3,500.000 $6,250.000 $2,300.000 $3,463.560 $3,000.000 $10,403.000 $2,100.000 $4,800.000 $11,000.000
REMOV STR (SET)
EA 57.000 $600.000 $750.000 $200.000 $692.710 $300.000 $867.000 $600.000 $500.000 $700.000
REMOV STR (WINGWALL)
EA 14.000 $2,000.000 $1,000.000 $1,200.000 $2,309.040 $2,000.000 $4,087.000 $2,800.000 $1,000.000 $860.000
REMOV STR (HEADWALL)
EA 2.000 $2,000.000 $1,425.000 $1,500.000 $1,731.780 $2,000.000 $4,087.000 $2,800.000 $1,000.000 $940.000
REMOV STR (PIPE)
LF 2,177.000 $35.000 $15.000 $11.000 $23.090 $25.000 $48.000 $38.000 $15.000 $19.000
REMOV STR (BOX CULVERT)
LF 58.000 $55.000 $100.000 $100.000 $115.450 $130.000 $281.000 $590.000 $550.000 $47.000
REMOV STR (RET WALL)
LF 7.000 $350.000 $150.000 $500.000 $232.310 $225.000 $100.000 $760.000 $70.000 $780.000
MOBILIZATION
LS 1.000 $1,444,900.000 $425,000.000 $1,025,000.000 $1,060,250.420 $1,500,000.000 $1,500,000.000 $250,000.000 $532,000.000 $800,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 12.000 $10,000.000 $14,000.000 $2,820.000 $13,552.870 $25,000.000 $57,429.000 $2,700.000 $10,000.000 $24,000.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $8,000.000 $23,750.000 $4,900.000 $5,151.230 $15,000.000 $9,743.000 $10,000.000 $10,000.000 $17,000.000
TMA (STATIONARY)
DAY 62.000 $275.000 $205.000 $355.000 $154.540 $185.000 $465.000 $300.000 $350.000 $555.220
TMA (MOBILE OPERATION)
HR 512.000 $125.000 $100.000 $106.000 $77.270 $60.000 $167.000 $150.000 $80.000 $44.420
ROCK FILTER DAMS (INSTALL) (TY 4)
LF 162.000 $65.000 $75.000 $56.060 $59.020 $65.000 $56.000 $74.000 $60.000 $66.630
ROCK FILTER DAMS (REMOVE)
LF 162.000 $12.000 $25.000 $15.550 $16.370 $23.000 $16.000 $26.000 $17.000 $27.760
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 1,569.000 $8.250 $6.000 $7.260 $7.640 $5.000 $7.000 $5.500 $15.000 $6.660
BIODEG EROSN CONT LOGS (REMOVE)
LF 1,569.000 $1.700 $2.000 $0.970 $1.020 $1.250 $1.000 $1.400 $2.000 $1.110
DRIVEWAYS (CONC)
SY 721.000 $120.000 $170.000 $167.000 $122.520 $100.000 $288.000 $128.000 $160.000 $140.000
DRIVEWAYS (ACP)
SY 2,412.000 $80.000 $95.000 $102.000 $48.400 $90.000 $70.000 $89.000 $140.000 $100.000
TURNOUTS (ACP)
SY 392.000 $85.000 $145.000 $39.000 $52.800 $65.000 $39.000 $92.000 $60.000 $260.000
MTL W-BEAM GD FEN (TIM POST)
LF 9,537.500 $27.000 $25.000 $22.670 $23.000 $25.000 $23.000 $30.000 $24.000 $28.870
SHORT RADIUS (28")
LF 325.000 $50.000 $50.000 $48.260 $48.000 $50.000 $48.000 $58.000 $50.000 $55.520
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 24.000 $1,500.000 $1,425.000 $1,220.300 $1,250.000 $1,450.000 $1,220.000 $1,700.000 $1,350.000 $3,886.570
MTL BM GD FEN (LONG SPAN SYSTEM)
EA 27.000 $1,180.000 $1,315.000 $1,318.560 $1,350.000 $1,500.000 $1,319.000 $1,500.000 $1,450.000 $4,997.010
REMOVE METAL BEAM GUARD FENCE
LF 1,975.000 $2.500 $3.000 $6.000 $2.500 $3.000 $6.000 $2.600 $5.000 $3.330
GUARDRAIL END TREATMENT (INSTALL)
EA 21.000 $3,200.000 $3,600.000 $3,361.960 $3,100.000 $3,500.000 $3,362.000 $4,300.000 $3,250.000 $3,886.570
GUARDRAIL END TREATMENT (REMOVE)
EA 14.000 $240.000 $190.000 $404.370 $250.000 $300.000 $404.000 $230.000 $275.000 $444.180
MAILBOX INSTALL-S (TWW-POST) TY 4
EA 18.000 $310.000 $325.000 $275.000 $275.000 $300.000 $275.000 $305.000 $300.000 $333.130
MAILBOX INSTALL-D (TWW-POST) TY 4
EA 3.000 $330.000 $385.000 $300.000 $300.000 $325.000 $300.000 $333.000 $325.000 $388.660
MAILBOX INSTALL-M (TWW-POST) TY 4
EA 5.000 $700.000 $715.000 $600.000 $600.000 $625.000 $600.000 $667.000 $650.000 $721.790
RELOCATE RD IL ASM (SHOE-BASE)
EA 2.000 $3,000.000 $1,525.000 $1,400.000 $1,549.390 $1,450.000 $2,939.000 $1,722.000 $1,625.000 $1,720.520
CONDT (PVC) (SCH 40) (2")
LF 234.000 $12.500 $19.000 $18.000 $19.920 $18.000 $15.000 $22.000 $21.000 $22.120
ELEC CONDR (NO.8) BARE
LF 244.000 $2.000 $5.000 $4.000 $4.430 $4.000 $3.000 $5.000 $5.000 $4.920
ELEC CONDR (NO.8) INSULATED
LF 488.000 $2.100 $6.000 $5.000 $5.530 $5.000 $3.000 $6.000 $6.000 $6.140
GROUND BOX TY A (122311)W/APRON
EA 2.000 $1,300.000 $2,725.000 $2,500.000 $2,766.770 $3,000.000 $1,396.000 $3,100.000 $2,900.000 $3,072.360
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 47.000 $710.000 $925.000 $615.000 $615.000 $615.000 $615.000 $684.000 $660.000 $777.310
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 4.000 $880.000 $1,095.000 $755.000 $755.000 $755.000 $755.000 $840.000 $810.000 $1,665.670
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
EA 2.000 $875.000 $1,250.000 $805.000 $805.000 $805.000 $805.000 $900.000 $870.000 $1,110.450
IN SM RD SN SUP&AM TY10BWG(1)SB(P)
EA 6.000 $825.000 $925.000 $658.000 $658.000 $658.000 $658.000 $730.000 $810.000 $1,110.450
IN SM RD SN SUP&AM TY10BWG(1)SB(T)
EA 2.000 $1,000.000 $1,075.000 $795.000 $795.000 $795.000 $795.000 $880.000 $855.000 $1,110.450
IN SM RD SN SUP&AM TYS80(1)SA(U-BM)
EA 1.000 $1,250.000 $1,350.000 $1,040.000 $1,040.000 $1,040.000 $1,040.000 $1,100.000 $1,120.000 $1,110.450
IN SM RD SN SUP&AM TYS80(1)SB(U-BM)
EA 1.000 $2,040.000 $1,350.000 $1,050.000 $1,050.000 $1,050.000 $1,050.000 $1,150.000 $1,130.000 $1,110.450
REMOVE SM RD SN SUP&AM
EA 40.000 $110.000 $135.000 $100.000 $100.000 $150.000 $35.000 $111.000 $110.000 $277.610
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
EA 155.000 $45.000 $45.000 $45.510 $35.000 $40.000 $35.000 $38.000 $42.000 $27.760
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
LF 58,559.000 $0.350 $0.250 $0.140 $0.150 $0.140 $0.250 $0.280 $0.150 $0.280
WK ZN PAV MRK NON-REMOV (W)6"(BRK)
LF 14,550.000 $0.400 $0.250 $0.180 $0.190 $0.180 $0.250 $0.290 $0.200 $0.330
WK ZN PAV MRK NON-REMOV (W)6"(SLD)
LF 58,057.000 $0.400 $0.250 $0.180 $0.190 $0.180 $0.250 $0.280 $0.200 $0.330
WK ZN PAV MRK NON-REMOV (W)8"(DOT)
LF 54.000 $0.750 $0.250 $0.220 $0.230 $0.220 $1.000 $1.170 $0.250 $1.110
WK ZN PAV MRK NON-REMOV (W)8"(SLD)
LF 2,749.000 $0.480 $0.250 $0.220 $0.230 $0.220 $1.000 $0.610 $0.250 $0.390
WK ZN PAV MRK NON-REMOV (W)24"(SLD)
LF 12.000 $4.550 $6.500 $6.000 $6.320 $6.000 $6.000 $5.830 $6.500 $3.330
WK ZN PAV MRK NON-REMOV (W)(ARROW)
EA 40.000 $82.330 $38.000 $35.000 $36.860 $35.000 $35.000 $58.300 $38.000 $72.180
WK ZN PAV MRK NON-REMOV(W)(WORD)
EA 16.000 $95.920 $45.000 $40.000 $42.120 $40.000 $40.000 $58.300 $43.000 $72.180
WK ZN PAV MRK NON-REMOV (Y)4"(BRK)
LF 14,630.000 $0.150 $0.250 $0.140 $0.150 $0.140 $0.250 $0.290 $0.200 $0.280
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 58,559.000 $0.350 $0.250 $0.140 $0.150 $0.140 $0.250 $0.290 $0.200 $0.280
WK ZN PAV MRK NON-REMOV (Y)6"(BRK)
LF 12,720.000 $0.500 $0.250 $0.180 $0.190 $0.180 $1.000 $0.290 $0.200 $0.330
WK ZN PAV MRK NON-REMOV (Y)6"(SLD)
LF 58,334.000 $0.400 $0.250 $0.180 $0.190 $0.180 $0.250 $0.290 $0.250 $0.330
WK ZN PAV MRK REMOV (TRAF BTN) TY W
EA 180.000 $2.800 $3.000 $2.500 $2.630 $2.500 $3.000 $4.660 $2.750 $6.110
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 374.000 $2.000 $1.250 $1.000 $6.730 $2.500 $1.000 $1.510 $3.500 $5.550
REFL PAV MRK TY I (W)8"(SLD)(090MIL)
LF 2,749.000 $0.940 $1.000 $0.700 $0.740 $0.700 $1.000 $1.030 $1.000 $1.110
REFL PAV MRK TY I (W)24"(SLD)(090MIL)
LF 12.000 $8.980 $16.000 $15.000 $15.800 $15.000 $15.000 $16.320 $16.000 $13.330
REFL PAV MRK TY I (W)(ARROW)(090MIL)
EA 40.000 $168.130 $205.000 $185.000 $194.810 $185.000 $185.000 $174.910 $200.000 $186.280
REFL PAV MRK TY I (W)(WORD)(090MIL)
EA 16.000 $192.380 $220.000 $200.000 $210.610 $200.000 $200.000 $174.910 $215.000 $208.490
RE PROFILE PM TY I(W)6"(SLD)(090MIL)
LF 58,057.000 $1.100 $0.750 $0.720 $0.760 $0.720 $0.750 $0.850 $0.750 $0.940
RE PROFILE PM TY I(Y)6"(SLD)(090MIL)
LF 58,334.000 $1.100 $0.750 $0.720 $0.760 $0.720 $0.750 $0.850 $0.750 $0.940
RE PROFILE PM TY I(Y)6"(BRK)(090MIL)
LF 12,720.000 $1.200 $1.000 $0.720 $0.760 $0.720 $0.750 $0.860 $0.750 $0.940
REFL PAV MRK TY I (W)6"(BRK)(090MIL)
LF 14,550.000 $0.520 $0.750 $0.510 $0.540 $0.510 $0.500 $0.640 $0.550 $0.720
PRFB RUMBLE STRIP (BLK)(1')(EDGELINE)
LF 11,614.000 $5.500 $4.000 $3.100 $3.260 $3.100 $3.000 $2.330 $3.350 $6.390
REFL PAV MRKR TY I-C
EA 874.000 $6.000 $5.000 $4.000 $4.210 $4.000 $4.000 $4.520 $5.000 $6.390
REFL PAV MRKR TY II-A-A
EA 1,654.000 $4.500 $5.000 $4.000 $4.210 $4.000 $4.000 $4.410 $5.000 $6.390
ELIM EXT PM & MRKS (4")
LF 9,744.000 $0.600 $1.000 $0.440 $0.460 $0.440 $0.500 $0.820 $0.500 $0.440
ELIM EXT PM & MRKS (ARROW)
EA 2.000 $70.000 $105.000 $95.000 $100.040 $95.000 $95.000 $69.960 $100.000 $111.040
BONDING COURSE
GAL 41,389.000 $4.000 $3.250 $4.500 $3.520 $4.000 $4.000 $4.830 $3.150 $3.340
SUBSURFACE UTIL LOCATE (NON-PAVED AREA)
EA 10.000 $1,805.000 $2,000.000 $975.000 $4,000.000 $750.000 $3,619.000 $580.000 $4,000.000 $1,800.000
Totals: $19,572,839.890 $14,639,581.450 $14,682,822.165 $15,140,468.230 $15,440,401.840 $15,578,367.000 $15,679,939.425 $15,689,948.000 $16,484,000.585