GILLESPIE US 87 (0071-06-063)
Items: 53
County: GILLESPIE
Length: 0.0000 MILES
Highway: US 87
District: AUSTIN
Control Number: 0071-06-063
DBE Goal: 0.0%
Project: C 71-6-63
Guaranty: $100,000.00
Time: 172 WORKING DAYS
Engineer's Estimate: $9,134,181.38
Date: 07/02/2025 (11 months ago)
Contract Number: 7253208
Type: SURFACING/ROADWAY RESTORATION
Project ID: A00178488
Project Description: FULL DEPTH RECLAMATION, OVERLAY & SEAL COAT
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
JOE MUCK
TYLER BRUDNICK
GILLESPIE US 87 (0071-06-063)
Project Name: N/A
Project: C 71-6-63
Length: 0.0000 MILES
Project Type: CONSTRUCTION
Limits From: RM 648
Limits To: US 290
Project Description: FULL DEPTH RECLAMATION, OVERLAY & SEAL COAT
GILLESPIE US 87 (0071-06-064)
Project Name: US 87 - OLD MASON RD TO US 290
Project: C 71-6-64
Length: 0.0000 MILES
Project Type: RESTORATION
Limits From: OLD MASON ROAD
Limits To: US 290
Project Description: FULL DEPTH RECLAMATION, OVERLAY & SEAL COAT
GILLESPIE US 87 (0071-06-061)
Project Name: US 87 FROM RM 648 TO BARONS CREEK
Project: C 71-6-61
Length: 0.0000 MILES
Project Type: RESTORATION
Limits From: RM 648
Limits To: BARONS CREEK
Project Description: FULL DEPTH RECLAMATION, OVERLAY & SEAL COAT
Bidders (7)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$9,134,181.38 | |||
| $9,157,488.33 |
0.26%
$23,306.95
|
|||
| $9,159,903.39 |
0.28%
$25,722.01
|
0.03%
$2,415.06
|
||
| $9,191,852.42 |
0.63%
$57,671.04
|
0.38%
$34,364.09
|
-0.35%
-$31,949.03
|
|
| $9,354,352.56 |
2.41%
$220,171.18
|
2.15%
$196,864.23
|
-1.77%
-$162,500.14
|
|
| $9,549,213.60 |
4.54%
$415,032.22
|
4.28%
$391,725.27
|
-2.08%
-$194,861.04
|
|
| $9,999,849.90 |
9.48%
$865,668.52
|
9.2%
$842,361.57
|
-4.72%
-$450,636.30
|
|
| $10,584,876.34 |
15.88%
$1,450,694.96
|
15.59%
$1,427,388.01
|
-5.85%
-$585,026.44
|
E
Engineer's Estimate
$9,134,181.38
1
Awarded
$9,157,488.33
Over/Under Est:
0.26%
$23,306.95
$9,159,903.39
Over/Under Est:
0.28%
$25,722.01
Amt Left:
0.03%
$2,415.06
$9,191,852.42
Over/Under Est:
0.63%
$57,671.04
Amt Left:
0.38%
$34,364.09
Delta:
-0.35%
-$31,949.03
$9,354,352.56
Over/Under Est:
2.41%
$220,171.18
Amt Left:
2.15%
$196,864.23
Delta:
-1.77%
-$162,500.14
$9,549,213.60
Over/Under Est:
4.54%
$415,032.22
Amt Left:
4.28%
$391,725.27
Delta:
-2.08%
-$194,861.04
$9,999,849.90
Over/Under Est:
9.48%
$865,668.52
Amt Left:
9.2%
$842,361.57
Delta:
-4.72%
-$450,636.30
$10,584,876.34
Over/Under Est:
15.88%
$1,450,694.96
Amt Left:
15.59%
$1,427,388.01
Delta:
-5.85%
-$585,026.44
| Subcontractor | Percentage | Amount |
|---|---|---|
| D. I. J. CONSTRUCTION, INC. | 12.11% | $1,108,971.84 |
| PERFORMANCE EQUIPMENT SERVICE | 4.63% | $423,991.71 |
| SOUTHWEST ROAD & SAFETY CONTRACTORS, LTD. | 2.02% | $184,981.26 |
| 4E TREE WORX LLC | 1.15% | $105,311.12 |
| BUYERS BARRICADES AUSTIN, LLC | 0.30% | $27,472.46 |
| A K FUQUAY CONSTRUCTION | 0.05% | $4,578.74 |
| Total: | 20.26% | $1,855,307.13 |
Bid Items & Bid Tabulations
53
Total
0 of 53
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
| Description | Amount |
|---|---|
| LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) | $10,000.00 |
| SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) | $10,000.00 |
| EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) | $10,000.00 |
| Total: | $30,000.00 |