Bid Cobra

TxDOT Subcontracts for DURWOOD GREENE CONSTRUCTION CO.

Control Number County Highway Bid Date Low Bidder Pay Estimates % of Contract Amount % Complete Contract Amount
2325-01-017 MONTGOMERY FM 2432 05/02/2025 VULCAN MATERIALS ASPHALT AND CONSTRUCTION, LLC 04/26 | 03/26 | 02/26 | 01/26 | 12/25 32.16% $1,367,265.29 99.00% $4,251,446.80
1004-01-064 BRAZORIA FM 524 04/03/2025 VULCAN MATERIALS ASPHALT AND CONSTRUCTION, LLC 04/26 | 03/26 | 02/26 | 01/26 | 12/25 0.59% $9,975.93 94.00% $1,690,835.76
0720-05-007 MONTGOMERY FS 149 03/05/2025 VULCAN MATERIALS ASPHALT AND CONSTRUCTION, LLC 03/26 | 02/26 | 01/26 | 12/25 | 11/25 16.94% $180,163.54 98.00% $1,063,539.21
1062-03-053 MONTGOMERY FM 1485 01/07/2025 VULCAN MATERIALS ASPHALT AND CONSTRUCTION, LLC 04/26 | 03/26 | 02/26 | 01/26 | 12/25 0.77% $59,222.41 91.00% $7,691,221.50
0338-11-056 MONTGOMERY SL 336 09/06/2024 JAMES CONSTRUCTION GROUP, LLC 04/26 | 03/26 | 02/26 | 01/26 | 12/25 5.39% $1,153,168.10 76.00% $21,394,584.37
0271-07-326 HARRIS IH 10 08/01/2024 WEBBER, LLC 04/26 | 03/26 | 02/26 | 01/26 | 12/25 0.28% $1,144,265.09 43.00% $408,666,104.46
1986-01-064 MONTGOMERY FM 1314 06/06/2024 R CONSTRUCTION CIVIL, LLC 04/26 | 03/26 | 02/26 | 01/26 | 12/25 1.83% $573,813.06 66.00% $31,355,904.72
0271-01-066 COLORADO IH 10 06/28/2023 WEBBER, LLC 04/26 | 03/26 | 02/26 | 01/26 | 12/25 16.01% $60,586,789.87 91.00% $378,430,917.35
0177-02-057 SAN JACINTO US 59 06/27/2023 WEBBER, LLC 05/26 | 04/26 | 03/26 | 02/26 | 01/26 5.85% $11,150,363.12 54.00% $190,604,497.81
0389-06-088 GALVESTON SH 146 05/05/2023 JAMES CONSTRUCTION GROUP, LLC 04/26 | 03/26 | 02/26 | 01/26 | 12/25 8.63% $17,177,919.98 27.00% $199,048,898.97
0111-03-059 FORT BEND FM 521 04/05/2023 GRANITE CONSTRUCTION COMPANY 05/26 | 04/26 | 03/26 | 02/26 | 01/26 3.27% $3,266,146.70 57.00% $99,882,161.95
0593-01-135 LIBERTY SH 105 01/06/2023 JAMES CONSTRUCTION GROUP, LLC 04/26 | 03/26 | 02/26 | 01/26 | 12/25 0.27% $34,735.66 100.00% $12,865,058.54
0089-10-026 WHARTON SH 60 10/07/2022 JAMES CONSTRUCTION GROUP, LLC 05/26 | 04/26 | 03/26 | 02/26 | 01/26 0.57% $10,780.34 93.00% $1,891,288.41
0338-04-066 MONTGOMERY SH 105 10/06/2022 JAMES CONSTRUCTION GROUP, LLC 04/26 | 03/26 | 02/26 | 01/26 | 12/25 5.97% $6,269,589.84 74.00% $105,018,255.25
0338-04-060 MONTGOMERY SH 105 08/04/2022 JAMES CONSTRUCTION GROUP, LLC 04/26 | 03/26 | 02/26 | 01/26 | 12/25 5.03% $2,678,106.60 65.00% $53,242,675.87
0188-04-035 BRAZORIA SH 36 08/03/2022 WEBBER, LLC 05/26 | 04/26 | 03/26 | 02/26 | 01/26 4.15% $5,266,463.14 92.00% $126,902,726.38
0213-04-050 POLK US 190 08/05/2021 VULCAN MATERIALS ASPHALT AND CONSTRUCTION, LLC 03/26 | 02/26 | 01/26 | 12/25 | 11/25 0.00% $0.00 113.00% $32,611,327.32
0523-09-009 MONTGOMERY FM 1488 08/05/2021 JAMES CONSTRUCTION GROUP, LLC 04/26 | 03/26 | 02/26 | 01/26 | 12/25 3.94% $1,938,734.74 70.00% $49,206,465.46
1259-01-044 MONTGOMERY FM 1097 08/04/2021 JAMES CONSTRUCTION GROUP, LLC 04/26 | 03/26 | 02/26 | 01/26 | 12/25 0.42% $91,568.05 103.00% $21,801,915.75