MONTGOMERY FS 149 (0720-05-007)

Items: 54

County: MONTGOMERY
Length: 1.3600 MILES
Highway: FS 149
District: HOUSTON
Control Number: 0720-05-007
DBE Goal: 0.0%
Project: F 2025(587)
Guaranty: $32,000.00
Time: 33 WORKING DAYS
Engineer's Estimate: $1,594,146.85
Date: 03/05/2025 (1 year ago)
Contract Number: 3253224
Type: SURFACING/ROADWAY RESTORATION
Project ID: A00130696
Contract Type: Federal
Project Description: BASE REPAIR, 3 INCH MILL, AND 3 INCH OVERLAY
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
MATTHEW CONNELLY
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (6)
E
Engineer's Estimate
$1,594,146.85
Over/Under Est: -33.28% -$530,607.64
Over/Under Est: -31.61% -$503,866.50
Amt Left: 2.51% $26,741.14
Over/Under Est: -24.04% -$383,291.55
Amt Left: 13.85% $147,316.09
Delta: -11.06% -$120,574.95
Over/Under Est: -18.69% -$297,888.20
Amt Left: 21.88% $232,719.44
Delta: -7.05% -$85,403.35
Over/Under Est: -7.27% -$115,931.75
Amt Left: 38.99% $414,675.89
Delta: -14.04% -$181,956.45
Over/Under Est: 88.65% $1,413,214.93
Amt Left: 182.77% $1,943,822.57
Delta: -103.45% -$1,529,146.68
Subcontractor Percentage Amount
DURWOOD GREENE CONSTRUCTION CO. 16.94% $180,163.54
TRP CONSTRUCTION GROUP, LLC 8.45% $89,869.06
DUSTROL, INC. 4.18% $44,455.94
PROFESSIONAL TRAFFIC CONTROL LLC 0.68% $7,232.07
SUPERIOR TRAFFIC CONTROL, LLC 0.24% $2,552.49
Total: 30.49% $324,273.10

Bid Items & Bid Tabulations

54 Total 0 of 54
MONTGOMERY  |  FS 149  |  HOUSTON  |  0720-05-007  |  03/05/2025  |  $1,594,146.85  |  F 2025(587)  |  SURF/ROADWAY RESTOR  |  33 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
VULCAN MATERIALS ASPHALT AND CONSTRUCTION, LLC
DURWOOD GREENE CONSTRUCTION CO.
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.
FORDE CONSTRUCTION COMPANY, INC.
ENVIRONMENTAL ALLIES, INC.
TEXAS MATERIALS GROUP, INC.
BACKFILL (TY A)
STA 73.000 $300.000 $264.000 $235.000 $527.000 $375.000 $750.000 $444.120
SP MIXES SP-D SAC-A PG70-22
TON 2,670.000 $175.000 $136.750 $165.000 $157.500 $137.000 $155.000 $377.410
FLEXIBLE PAVEMENT STRUCTURE REPAIR(10")
SY 2,670.000 $130.000 $73.000 $65.000 $85.000 $120.000 $105.000 $217.700
PLANE ASPH CONC PAV(2")
SY 28,969.000 $5.000 $2.250 $2.500 $3.500 $5.000 $6.000 $16.630
MOBILIZATION
LS 1.000 $134,078.120 $106,000.000 $90,000.000 $100,000.000 $125,000.000 $125,000.000 $215,709.330
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 3.000 $7,000.000 $15,630.000 $7,000.000 $10,000.000 $1,500.000 $1,500.000 $1,753.310
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 80.000 $150.000 $81.000 $300.000 $100.000 $130.000 $115.000 $399.030
TMA (STATIONARY)
DAY 27.000 $380.000 $271.000 $300.000 $125.000 $170.000 $275.000 $580.410
TMA (MOBILE OPERATION)
HR 112.000 $100.000 $32.000 $70.000 $15.000 $25.000 $150.000 $164.600
INTERSECTIONS (ACP)
SY 703.000 $55.000 $26.000 $25.000 $30.500 $53.000 $65.000 $83.770
DRIVEWAYS (ACP)
SY 1,564.000 $95.000 $63.000 $27.000 $45.300 $82.000 $65.000 $36.440
TURNOUTS (ACP)
SY 165.000 $124.000 $62.000 $140.000 $35.000 $48.000 $105.000 $139.600
MILL RUMBLE STRIPS (ASPH) (CENTERLINE)
LF 35,829.000 $1.400 $0.080 $0.280 $0.100 $0.150 $1.000 $0.250
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 4.000 $864.000 $743.940 $720.000 $715.000 $680.000 $800.000 $1,729.130
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 3.000 $955.000 $753.040 $750.000 $735.000 $742.000 $815.000 $1,777.490
IN SM RD SN SUP&AM TYS80(1)SA(U)
EA 1.000 $1,100.000 $1,086.600 $1,100.000 $1,105.000 $1,140.000 $1,250.000 $2,672.280
REMOVE SM RD SN SUP&AM
EA 8.000 $46.000 $130.000 $150.000 $135.000 $110.000 $145.000 $326.480
WK ZN PAV MRK NON-REMOV (W)6"(BRK)
LF 1,149.000 $0.650 $0.340 $0.380 $0.350 $0.350 $0.750 $0.850
WK ZN PAV MRK NON-REMOV (W)6"(SLD)
LF 42,486.000 $0.700 $0.340 $0.380 $0.350 $0.350 $0.550 $0.850
WK ZN PAV MRK NON-REMOV (W)8"(SLD)
LF 2,673.000 $1.000 $0.760 $1.000 $0.350 $0.800 $0.800 $1.330
WK ZN PAV MRK NON-REMOV (W)12"(SLD)
LF 300.000 $3.700 $2.750 $3.000 $1.880 $2.850 $2.500 $4.550
WK ZN PAV MRK NON-REMOV (W)24"(SLD)
LF 225.000 $4.000 $5.500 $6.000 $3.800 $5.700 $4.500 $918.980
WK ZN PAV MRK NON-REMOV (W)(ARROW)
EA 21.000 $100.000 $85.000 $110.000 $100.000 $129.000 $115.000 $241.840
WK ZN PAV MRK NON-REMOV (W)(DBL ARW)
EA 3.000 $146.000 $125.000 $170.000 $135.000 $129.000 $150.000 $326.480
WK ZN PAV MRK NON-REMOV (W)(RR XING)
EA 3.000 $330.000 $255.000 $275.000 $200.000 $263.000 $275.000 $483.670
WK ZN PAV MRK NON-REMOV(W)(WORD)
EA 21.000 $130.000 $125.000 $140.000 $105.000 $129.000 $175.000 $253.930
WK ZN PAV MRK NON-REMOV (Y)6"(BRK)
LF 3,414.000 $0.660 $0.340 $0.380 $0.350 $0.350 $0.600 $0.850
WK ZN PAV MRK NON-REMOV (Y)6"(SLD)
LF 34,302.000 $0.620 $0.340 $0.380 $0.350 $0.350 $0.650 $0.850
WK ZN PAV MRK REMOV (REFL) TY II-A-A
EA 867.000 $7.000 $6.000 $4.200 $3.880 $6.200 $6.000 $9.380
WK ZN PAV MRK REMOV (REFL) TY II-C-R
EA 207.000 $6.000 $6.000 $4.200 $3.880 $6.200 $5.000 $9.380
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 891.000 $1.500 $1.750 $1.100 $1.250 $1.800 $1.850 $3.020
REFL PAV MRK TY I (W)12"(SLD)(100MIL)
LF 100.000 $5.500 $3.750 $5.000 $3.990 $3.900 $5.000 $9.650
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 75.000 $9.000 $8.000 $10.000 $7.250 $8.250 $9.000 $17.530
RE PROFILE PM TY I(W)6"(SLD)(090MIL)
LF 14,162.000 $1.750 $0.980 $1.000 $0.900 $1.000 $1.750 $2.180
RE PROFILE PM TY I(Y)6"(SLD)(090MIL)
LF 1,575.000 $2.000 $0.980 $1.000 $0.900 $1.000 $2.000 $2.180
RE PROFILE PM TY I(Y)6"(BRK)(090MIL)
LF 394.000 $1.100 $0.980 $3.500 $3.000 $1.000 $5.000 $7.260
ALL-WTHER PM TY I (W)6"(BRK)(100MIL)
LF 383.000 $1.000 $2.750 $4.500 $4.000 $2.850 $6.000 $9.670
ALL-WTHER PM TY I (Y)6"(SLD)(100MIL)
LF 9,859.000 $1.000 $0.860 $1.250 $1.050 $0.900 $1.500 $2.540
ALL-WTHER PM TY I (Y)6"(BRK)(100MIL)
LF 744.000 $1.500 $2.750 $4.500 $4.000 $2.850 $5.750 $9.670
PREFAB PM TY C (W)(ARROW)
EA 7.000 $284.000 $308.530 $255.000 $235.000 $318.000 $300.000 $568.310
PREFAB PM TY C (W)(DBL ARROW)
EA 1.000 $388.000 $436.660 $300.000 $265.000 $450.000 $500.000 $640.870
PREFAB PM TY C (W)(WORD)
EA 7.000 $344.000 $376.960 $270.000 $245.000 $389.000 $375.000 $592.500
PREFAB PM TY C (W)(RR XING)
EA 1.000 $700.000 $684.480 $950.000 $750.000 $706.000 $1,000.000 $1,813.770
REFL PAV MRKR TY I-C
EA 69.000 $1.000 $6.000 $7.000 $6.360 $6.200 $7.150 $15.380
REFL PAV MRKR TY II-A-A
EA 289.000 $9.000 $6.000 $7.000 $6.360 $6.200 $8.000 $15.380
PAV SURF PREP FOR MRK (6")
LF 27,117.000 $0.100 $0.030 $0.200 $0.150 $0.030 $0.750 $0.360
PAV SURF PREP FOR MRK (8")
LF 891.000 $1.000 $0.040 $0.300 $0.250 $0.040 $1.000 $0.600
PAV SURF PREP FOR MRK (12")
LF 100.000 $1.500 $0.060 $0.650 $0.600 $0.060 $1.000 $1.450
PAV SURF PREP FOR MRK (24")
LF 75.000 $0.700 $0.120 $1.500 $1.250 $0.120 $2.000 $3.020
PAV SURF PREP FOR MRK (ARROW)
EA 7.000 $13.000 $5.000 $55.000 $50.000 $5.150 $60.000 $120.920
PAV SURF PREP FOR MRK (DBL ARROW)
EA 1.000 $49.000 $5.000 $65.000 $60.000 $5.150 $100.000 $145.110
PAV SURF PREP FOR MRK (WORD)
EA 7.000 $12.000 $5.000 $55.000 $50.000 $5.150 $75.000 $120.920
PAV SURF PREP FOR MRK (RR XING)
EA 1.000 $90.000 $5.000 $110.000 $100.000 $5.150 $200.000 $241.830
UNDERSEAL COURSE
GAL 5,340.000 $6.000 $5.400 $7.000 $16.300 $3.500 $6.000 $7.710
Totals: $1,594,146.850 $1,063,539.210 $1,090,280.350 $1,210,855.300 $1,296,258.650 $1,478,215.100 $3,007,361.780
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
RAILROAD FORCE ACCOUNT WORK (PART) $5,000.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $1,050.00
LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (PART) $6,777.00
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $5,000.00
Total: $17,827.00