Control Number County Highway Bid Date Low Bidder Pay Estimates % of Contract Amount % Complete Contract Amount
0015-01-246 MCLENNAN IH 35 10/02/2024 JAMES CONSTRUCTION GROUP, LLC 05/26 | 04/26 | 03/26 | 02/26 | 01/26 4.08% $9,605,527.27 28.00% $235,429,589.99
0171-05-101 TARRANT SH 199 06/05/2024 FNH CONSTRUCTION, LLC 05/26 | 04/26 | 03/26 | 02/26 | 01/26 37.96% $1,073,493.62 55.00% $2,827,960.00
0918-24-267 COLLIN CS 02/02/2024 FNH CONSTRUCTION, LLC 04/26 | 03/26 | 02/26 | 01/26 | 12/25 26.10% $1,271,678.85 80.00% $4,872,332.75
0442-03-042 ELLIS IH 35E 02/01/2024 FLATIRON CONSTRUCTORS, INC. 04/26 | 03/26 | 02/26 | 01/26 | 12/25 0.00% $0.00 55.00% $137,568,648.40
1139-01-048 ELLIS FM 813 08/02/2023 FNH CONSTRUCTION, LLC 10/25 | 09/25 | 08/25 | 07/25 | 06/25 28.80% $307,731.89 86.00% $1,068,513.50
1311-01-060 DENTON FM 1171 06/28/2023 SEMA CONSTRUCTION, INC. 12/24 | 11/24 | 10/24 | 09/24 | 08/24 20.30% $171,707.64 100.00% $845,850.43
0197-03-078 KAUFMAN US 175 06/27/2023 GRANITE CONSTRUCTION COMPANY 05/26 | 04/26 | 03/26 | 02/26 | 01/26 0.91% $521,977.24 94.00% $57,360,135.83
0009-03-048 DALLAS SH 66 05/05/2023 XIT PAVING AND CONSTRUCTION INC. 05/26 | 04/26 | 03/26 | 02/26 | 01/26 0.34% $14,540.93 90.00% $4,276,745.58
0918-47-342 DALLAS CS 05/05/2023 FNH CONSTRUCTION, LLC 04/26 | 03/26 | 02/26 | 01/26 | 12/25 38.32% $1,058,537.31 89.00% $2,762,362.50
0008-03-094 PARKER IH 20 05/04/2023 SEMA CONSTRUCTION, INC. 05/26 | 04/26 | 03/26 | 02/26 | 01/26 7.99% $4,644,000.33 99.00% $58,122,657.49
2658-01-013 HUNT FM 2642 01/05/2023 HARPER BROTHERS CONSTRUCTION LLC 04/26 | 02/26 | 01/26 | 12/25 | 11/25 1.00% $307,628.19 95.00% $30,762,819.11
0116-03-066 BURLESON SH 21 05/05/2022 CORNERSTONE PAVING AND CONSTRUCTION, L.L.C. 10/24 | 09/24 | 08/24 | 07/24 | 06/24 3.61% $106,180.30 98.00% $2,941,282.43
0155-02-029 GOLIAD US 183 11/04/2021 HUNTER INDUSTRIES, LTD. 11/25 | 10/25 | 09/25 | 08/25 | 07/25 0.56% $146,152.01 98.00% $26,098,572.88
0258-09-142 MCLENNAN SH 6 08/05/2021 WEBBER, LLC 05/25 | 04/25 | 03/25 | 02/25 | 01/25 3.09% $1,777,247.98 103.00% $57,516,115.75
0249-08-042 PALO PINTO US 281 07/08/2020 JAY MILLS CONTRACTING, INCORPORATED 04/25 | 03/25 | 02/25 | 01/25 | 12/24 0.29% $67,096.01 95.00% $23,136,556.03
0135-10-057 DENTON US 377 06/04/2020 RAGLE CONSTRUCTION, INC. 10/24 | 09/24 | 08/24 | 07/24 | 06/24 0.33% $68,035.23 100.00% $20,616,736.66