| Control Number | County | Highway | Bid Date | Low Bidder | Pay Estimates | % of Contract | Amount | % Complete | Contract Amount |
|---|---|---|---|---|---|---|---|---|---|
| 0913-27-092 | VICTORIA | CLARK SCHOOL | 11/06/2025 | PRESIDIO CONTRACTING, LLC | 05/26 | 04/26 | 03/26 | 1.44% | $41,437.08 | 14.00% | $2,877,575.15 |
| 0913-21-056 | MATAGORDA | HAMMAN ST | 10/08/2025 | E-Z BEL CONSTRUCTION, LLC | 05/26 | 04/26 | 03/26 | 02/26 | 01/26 | 1.28% | $62,292.52 | 11.00% | $4,866,603.30 |
| 0913-21-054 | MATAGORDA | S GULF RD | 09/05/2025 | E-Z BEL CONSTRUCTION, LLC | 05/26 | 04/26 | 03/26 | 02/26 | 01/26 | 3.19% | $58,502.57 | 88.00% | $1,833,936.50 |
| 0913-28-095 | FAYETTE | KRUPPA RD | 04/03/2025 | TREVWAY, INC. | 05/26 | 04/26 | 03/26 | 02/26 | 01/26 | 5.00% | $101,807.90 | 38.00% | $2,036,157.99 |
| 0913-09-123 | WHARTON | COUNTY ROAD 404 | 03/04/2025 | TREVWAY, INC. | 05/26 | 04/26 | 03/26 | 02/26 | 01/26 | 3.85% | $119,354.10 | 42.00% | $3,100,106.40 |
| 0913-09-119 | WHARTON | CO | 08/02/2024 | TREVWAY, INC. | 05/26 | 04/26 | 03/26 | 02/26 | 01/26 | 4.13% | $89,080.32 | 98.00% | $2,156,908.46 |
| 0916-27-014 | REFUGIO | JW | 08/01/2024 | TEXAS STEEL INDUSTRIAL PLACING, CONCRETE DIVISION LLC | 10/25 | 09/25 | 08/25 | 07/25 | 06/25 | 4.58% | $31,221.01 | 94.00% | $681,681.50 |
| 0447-04-018 | REFUGIO | SH 202 | 05/03/2024 | E-Z BEL CONSTRUCTION, LLC | 05/26 | 04/26 | 03/26 | 02/26 | 01/26 | 0.99% | $76,496.80 | 104.00% | $7,726,949.43 |
| 0913-26-064 | COLORADO | CR | 03/06/2024 | TREVWAY, INC. | 12/25 | 11/25 | 10/25 | 09/25 | 08/25 | 3.78% | $104,033.41 | 96.00% | $2,752,206.71 |
| 0913-17-045 | DEWITT | CR | 06/27/2023 | CONSTAR CONSTRUCTION | 03/26 | 02/26 | 01/26 | 12/25 | 11/25 | 5.45% | $100,729.52 | 97.00% | $1,848,248.10 |
| 1132-01-035 | VICTORIA | FM 1686 | 06/01/2023 | E-Z BEL CONSTRUCTION, LLC | 07/25 | 06/25 | 05/25 | 04/25 | 03/25 | 2.68% | $69,972.68 | 96.00% | $2,610,920.91 |
| 0913-22-016 | GONZALES | CR | 04/04/2023 | E-Z BEL CONSTRUCTION, LLC | 05/25 | 04/25 | 03/25 | 02/25 | 01/25 | 2.71% | $34,649.75 | 102.00% | $1,278,588.55 |
| 0913-28-083 | FAYETTE | CR | 03/08/2023 | TREVWAY, INC. | 05/26 | 04/26 | 03/26 | 02/26 | 01/26 | 5.11% | $132,684.18 | 94.00% | $2,596,559.22 |
| 0913-28-070 | FAYETTE | CR | 08/04/2022 | FUQUA CONSTRUCTION CO., INC. | 05/26 | 04/26 | 03/26 | 02/26 | 01/26 | 2.84% | $30,953.07 | 87.00% | $1,089,896.94 |
| 0346-06-052 | LAVACA | SH 111 | 06/30/2022 | SB CONTRACTORS LLC | 12/25 | 11/25 | 10/25 | 09/25 | 08/25 | 2.67% | $100,792.67 | 102.00% | $3,775,006.39 |
| 0913-28-078 | FAYETTE | CR | 06/01/2022 | SB CONTRACTORS LLC | 11/25 | 10/25 | 09/25 | 08/25 | 07/25 | 3.89% | $108,890.02 | 99.00% | $2,799,229.26 |
| 0942-02-011 | GONZALES | FM 2067 | 05/04/2022 | HILL COUNTRY BRIDGE, INC. | 08/25 | 07/25 | 06/25 | 05/25 | 04/25 | 2.91% | $72,130.68 | 101.00% | $2,478,717.67 |
| 0913-18-036 | JACKSON | CR | 07/02/2021 | TREVWAY, INC. | 06/25 | 05/25 | 04/25 | 03/25 | 02/25 | 1.20% | $15,594.21 | 100.00% | $1,299,517.63 |
| 0913-28-075 | FAYETTE | CR | 07/02/2021 | TREVWAY, INC. | 11/24 | 10/24 | 09/24 | 08/24 | 07/24 | 2.77% | $22,325.94 | 96.00% | $805,990.58 |
| 0913-22-052 | GONZALES | CR | 04/08/2021 | SEFBO PIPELINE BRIDGE, INCORPORATED | 03/25 | 02/25 | 01/25 | 12/24 | 11/24 | 5.75% | $60,011.29 | 97.00% | $1,043,674.65 |
| 0913-09-102 | WHARTON | CR | 04/07/2021 | SB CONTRACTORS LLC | 09/24 | 08/24 | 07/24 | 06/24 | 05/24 | 1.79% | $22,269.10 | 99.00% | $1,244,083.83 |
| 1090-01-027 | JACKSON | FM 530 | 03/04/2021 | TREVWAY, INC. | 04/25 | 03/25 | 02/25 | 01/25 | 12/24 | 3.53% | $83,555.24 | 96.00% | $2,367,003.94 |
| 1302-02-013 | WHARTON | FM 647 | 02/04/2021 | SEFBO PIPELINE BRIDGE, INCORPORATED | 08/24 | 07/24 | 06/24 | 05/24 | 04/24 | 23.50% | $297,889.91 | 49.00% | $1,267,616.62 |
| 0269-03-036 | LAVACA | UA 77 | 11/04/2020 | HILL COUNTRY BRIDGE, INC. | 08/25 | 07/25 | 06/25 | 05/25 | 04/25 | 1.69% | $73,892.74 | 99.00% | $4,372,351.19 |