VICTORIA FM 1686 (1132-01-035)

Items: 62

County: VICTORIA
Length: N/A
Highway: FM 1686
District: YOAKUM
Control Number: 1132-01-035
DBE Goal: N/A
Project: BR 2023(899)
Guaranty: N/A
Time: 0 X
Engineer's Estimate: $3,135,749.00
Date: 06/01/2023 (3 years ago)
Contract Number: N/A
Type: BRIDGE REPLACEMENT
Mail/Deliver Bids To: N/A
CLAYTON HARRIS
JAMES JANAK
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (3)
E
Engineer's Estimate
$3,135,749.00
$3,399,017.10
Over/Under Est: 8.4% $263,268.10
Over/Under Est: 32.33% $1,013,687.28
Amt Left: 22.08% $750,419.18
Over/Under Est: 42.53% $1,333,767.00
Amt Left: 31.49% $1,070,498.90
Delta: -7.71% -$320,079.72
Subcontractor Percentage Amount
ZENITH SITE SERVICES 9.01% $235,243.97
WEBER-BALKE FOUNDATION COMPANY, INC 8.66% $226,105.75
LONE STAR PAVING COMPANY 4.10% $107,047.76
SYLVA CONSTRUCTION, LLC 2.68% $69,972.68
J. R. (JOE) RAMON & SONS, INC. 2.50% $65,273.02
DIIBS SPECIALISTS, LLC 1.74% $45,430.02
AARON CONCRETE CONTRACTORS, LLC 1.56% $40,730.37
TORO BRAVO CONSTRUCTION, LLC 0.74% $19,320.81
TEXAS EROSION CONTROL SERVICES 0.67% $17,493.17
HIGHWAY BARRICADES AND SERVICES, LLC 0.42% $10,965.87
SOUTH TEXAS TRAFFIC ALLIANCE INC. 0.27% $7,049.49
AREA WIDE PROTECTIVE, INC. 0.21% $5,482.93
PRIMATE CONSTRUCTION, LP 0.19% $4,960.75
Total: 32.75% $855,076.59

Bid Items & Bid Tabulations

62 Total 0 of 62
VICTORIA  |  FM 1686  |  YOAKUM  |  1132-01-035  |  06/01/2023  |  $3,135,749.00  |  BR 2023(899)  |  BRIDGE REPL  |  0 X
Item Code
Description
Unit
Quantity
Engineer's Estimate
E-Z BEL CONSTRUCTION, LLC
R CONSTRUCTION CIVIL, LLC
CROSS PLUS CONSTRUCTION, LLC
PREPARING ROW
STA 11.900 $3,600.000 $1,200.000 $3,519.000 $3,300.000
EXCAVATION (ROADWAY)
CY 1,527.000 $30.000 $22.000 $18.000 $44.000
EXCAVATION (CHANNEL)
CY 852.000 $20.000 $22.000 $21.000 $44.000
EMBANKMENT (FINAL)(DENS CONT)(TY C)
CY 338.000 $30.000 $15.000 $29.000 $55.000
BLADING
HR 24.000 $100.000 $60.000 $138.000 $11.000
BROADCAST SEED (PERM) (RURAL) (CLAY)
SY 2,750.000 $2.000 $1.400 $2.000 $6.000
BROADCAST SEED (TEMP) (WARM)
SY 687.000 $1.000 $2.550 $3.000 $6.000
BROADCAST SEED (TEMP) (COOL)
SY 687.000 $1.000 $2.550 $3.000 $6.000
VEGETATIVE WATERING
MG 23.200 $75.000 $72.000 $54.000 $110.000
FL BS (CMP IN PLC)(TYE GR1-2)(FNAL POS)
CY 1,528.000 $125.000 $91.000 $155.000 $110.000
CEMENT
TON 40.000 $250.000 $350.000 $344.000 $550.000
CEMENT TREAT (SUBGRADE) (8")
SY 2,539.000 $7.000 $4.000 $7.000 $22.000
ASPH (RC-250)
GAL 1,047.000 $15.000 $9.400 $15.000 $11.000
AGGR(TY-E GR-5 SAC-B)
CY 37.000 $200.000 $536.000 $934.000 $165.000
AGGR(TY-PE GR-3 SAC-B)
CY 40.000 $200.000 $542.000 $233.000 $165.000
ASPH (AC-15P OR AC-10-2TR OR CRS-2P)
GAL 1,781.000 $15.000 $8.200 $12.000 $22.000
CEM STABIL BKFL
CY 217.000 $175.000 $250.000 $195.000 $275.000
CUT AND RESTORE PAV (FLEX BASE)
SY 160.000 $45.000 $124.000 $21.000 $110.000
TEMPORARY SPL SHORING
SF 974.000 $25.000 $25.000 $27.000 $55.000
DRILL SHAFT (36 IN)
LF 716.000 $330.000 $320.000 $493.000 $330.000
CL C CONC (ABUT)
CY 52.200 $1,400.000 $1,060.000 $2,291.000 $1,650.000
CL C CONC (CAP)
CY 44.400 $1,600.000 $639.000 $1,909.000 $4,400.000
CL C CONC (COLUMN)
CY 24.100 $1,600.000 $1,000.000 $2,673.000 $3,300.000
REINF CONC SLAB
SF 7,770.000 $25.000 $29.000 $22.000 $28.000
APPROACH SLAB
CY 99.400 $700.000 $705.000 $1,883.000 $1,650.000
PRESTR CONC GIRDER (TX28)
LF 917.120 $175.000 $230.000 $204.000 $275.000
RIPRAP (CONC)(5 IN)
CY 55.400 $600.000 $400.000 $459.000 $220.000
RIPRAP (STONE PROTECTION)(18 IN)
CY 556.000 $200.000 $335.000 $250.000 $220.000
RAIL (TY SSTR)
LF 72.000 $115.000 $269.000 $374.000 $275.000
RAIL (TY SSTR) (W/DRAIN SLOTS)
LF 410.000 $105.000 $108.000 $122.000 $275.000
SEALED EXPANSION JOINT (4 IN) (SEJ - M)
LF 94.000 $200.000 $333.000 $217.000 $110.000
CONC BOX CULV (10 FT X 8 FT)
LF 126.000 $1,000.000 $1,900.000 $2,500.000 $1,650.000
WINGWALL (FW - 0) (HW=8 FT)
EA 2.000 $24,000.000 $40,000.000 $35,000.000 $27,500.000
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
EA 1.000 $25,000.000 $18,000.000 $45,000.000 $55,000.000
REMOV STR (BRIDGE 100 - 499 FT LENGTH)
EA 1.000 $55,000.000 $50,000.000 $82,075.000 $110,000.000
REMOV STR (SMALL)
EA 2.000 $800.000 $10,000.000 $594.000 $1,100.000
MOBILIZATION
LS 1.000 $201,000.000 $256,000.000 $300,000.000 $220,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 9.000 $3,000.000 $4,000.000 $6,500.000 $5,500.000
ROCK FILTER DAMS (INSTALL) (TY 1)
LF 80.000 $40.000 $61.000 $75.000 $55.000
ROCK FILTER DAMS (REMOVE)
LF 80.000 $10.000 $22.000 $27.000 $6.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 1,300.000 $4.000 $7.000 $8.000 $17.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 1,300.000 $1.000 $1.000 $2.000 $1.000
PORT CTB (FUR & INST)(F-SHAPE)(TY 1)
LF 540.000 $55.000 $65.000 $85.000 $220.000
PORT CTB (REMOVE)(F-SHAPE)(TY 1)
LF 540.000 $15.000 $34.000 $6.000 $165.000
DRIVEWAYS (SURF TREAT)
SY 143.000 $55.000 $125.000 $25.000 $55.000
MTL W-BEAM GD FEN (TIM POST)
LF 375.000 $30.000 $29.000 $46.000 $44.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 7.000 $2,200.000 $2,355.000 $3,900.000 $3,850.000
GUARDRAIL END TREATMENT (INSTALL)
EA 7.000 $3,000.000 $3,245.000 $4,714.000 $3,850.000
CRASH CUSH ATTEN (REMOVE)
EA 4.000 $650.000 $1,035.000 $1,044.000 $1,100.000
CRASH CUSH ATTEN (INSTL)(L)(N)(TL3)
EA 1.000 $22,000.000 $27,025.000 $38,064.000 $44,000.000
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
EA 4.000 $9,000.000 $8,375.000 $12,227.000 $44,000.000
RELOCATE SM RD SN SUP&AM TY TWT
EA 2.000 $500.000 $950.000 $765.000 $550.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
EA 8.000 $27.000 $35.000 $20.000 $17.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 11.000 $35.000 $35.000 $44.000 $17.000
REF PROF PAV MRK TY I(W)6"(SLD)(100MIL)
LF 2,756.000 $1.000 $3.300 $5.000 $11.000
REF PROF PAV MRK TY I(Y)6"(BRK)(100MIL)
LF 324.000 $1.000 $3.750 $5.000 $11.000
REFL PAV MRKR TY II-A-A
EA 34.000 $5.000 $20.000 $15.000 $11.000
NO. OF WORKING DAYS
$/D 4,755.000 $175.000 $169.000 $175.000 $175.000
D-GR HMA TY-D SAC-B PG70-22
TON 594.000 $160.000 $140.000 $270.000 $165.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 3.000 $7,500.000 $12,500.000 $19,945.000 $16,500.000
TMA (STATIONARY)
DAY 4.000 $350.000 $350.000 $228.000 $16,500.000
TMA (MOBILE OPERATION)
DAY 4.000 $250.000 $225.000 $622.000 $2,750.000
Totals: $3,135,749.000 $3,399,017.100 $4,149,436.280 $4,469,516.000