COLORADO CR (0913-26-064)

Items: 57

County: COLORADO
Length: N/A
Highway: CR
District: YOAKUM
Control Number: 0913-26-064
DBE Goal: 600.0%
Project: BR 2020(608)
Guaranty: N/A
Time: 225 WORKING DAYS
Engineer's Estimate: $2,459,978.00
Date: 03/06/2024 (2 years ago)
Contract Number: N/A
Type: BRIDGE REPLACEMENT
Mail/Deliver Bids To: N/A
RYAN SIMPER
PAUL RODRIGUEZ
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (8)
E
Engineer's Estimate
$2,459,978.00
1
$2,752,206.71
Over/Under Est: 11.88% $292,228.71
$2,770,708.40
Over/Under Est: 12.63% $310,730.40
Amt Left: 0.67% $18,501.69
Over/Under Est: 17.79% $437,508.40
Amt Left: 5.28% $145,279.69
Delta: -4.58% -$126,778.00
Over/Under Est: 17.92% $440,870.90
Amt Left: 5.4% $148,642.19
Delta: -0.12% -$3,362.50
Over/Under Est: 24.08% $592,455.78
Amt Left: 10.91% $300,227.07
Delta: -5.23% -$151,584.88
$3,142,891.00
Over/Under Est: 27.76% $682,913.00
Amt Left: 14.2% $390,684.29
Delta: -2.96% -$90,457.22
Over/Under Est: 45.3% $1,114,449.50
Amt Left: 29.87% $822,220.79
Delta: -13.73% -$431,536.50
Over/Under Est: 59.07% $1,453,038.00
Amt Left: 42.18% $1,160,809.29
Delta: -9.47% -$338,588.50
Subcontractor Percentage Amount
JH CONTRACT FIELD SERVICES, LLC 8.76% $241,093.31
SYLVA CONSTRUCTION, LLC 3.78% $104,033.41
HEMPHILL WBE PILE DRIVING CO. 3.06% $84,217.53
A K FUQUAY CONSTRUCTION 0.66% $18,164.56
SUPERIOR TRAFFIC CONTROL, LLC 0.39% $10,733.61
HOUSTON SAWING & DRILLING 0.19% $5,229.19
Total: 16.84% $463,471.61

Bid Items & Bid Tabulations

57 Total 0 of 57
COLORADO  |  CR  |  YOAKUM  |  0913-26-064  |  03/06/2024  |  $2,459,978.00  |  BR 2020(608)  |  BRIDGE REPL  |  225 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
TREVWAY, INC.
C. E. BARKER, LTD.
E-Z BEL CONSTRUCTION, LLC
ARANDA BROTHERS CONSTRUCTION CO., INC.
A GREATER AUSTIN DEVELOPMENT COMPANY, LLC
EARTH BUILDERS, L.P.
AUSTIN ENGINEERING CO., INC.
TEXAS MATERIALS GROUP, INC.
PREPARING ROW
STA 10.400 $4,500.000 $4,500.000 $12,019.000 $9,000.000 $20,500.000 $10,135.000 $25,000.000 $11,000.000 $27,850.000
EXCAVATION (ROADWAY)
CY 476.000 $25.000 $10.000 $40.810 $28.000 $10.000 $25.750 $25.000 $100.000 $67.000
EXCAVATION (CHANNEL)
CY 1,044.000 $25.000 $13.090 $36.960 $28.000 $20.000 $28.850 $25.000 $70.000 $34.000
EMBANKMENT (FINAL)(ORD COMP)(TY C)
CY 1,416.000 $30.000 $15.000 $51.840 $36.000 $15.000 $27.800 $35.000 $95.000 $83.000
BLADING
HR 48.000 $120.000 $100.000 $85.800 $69.000 $75.000 $61.800 $125.000 $500.000 $100.000
BROADCAST SEED (PERM) (RURAL) (CLAY)
SY 2,636.000 $2.000 $1.500 $1.100 $1.000 $0.650 $1.050 $1.500 $1.000 $1.000
BROADCAST SEED (TEMP) (WARM)
SY 660.000 $2.000 $1.000 $1.100 $2.000 $0.550 $2.000 $2.000 $2.000 $2.000
BROADCAST SEED (TEMP) (COOL)
SY 660.000 $2.000 $1.000 $1.100 $2.000 $0.750 $2.000 $2.000 $2.000 $2.000
VEGETATIVE WATERING
MG 33.200 $75.000 $100.000 $38.610 $216.000 $65.000 $150.000 $100.000 $200.000 $60.000
FL BS (CMP IN PLC)(TY E GR 5)(FNL POS)
CY 710.000 $130.000 $180.000 $126.850 $125.000 $85.000 $131.850 $150.000 $170.000 $210.000
ASPH (RC-250)
GAL 601.000 $9.000 $28.090 $11.030 $22.000 $10.000 $22.450 $15.000 $36.000 $22.000
AGGR(TY-E GR-5 SAC-B)
CY 27.000 $250.000 $1,664.520 $772.160 $1,290.000 $135.000 $1,330.000 $400.000 $1,823.000 $1,500.000
AGGR(TY-PE GR-4 SAC-B)
CY 29.000 $250.000 $1,575.480 $496.390 $1,221.000 $125.000 $1,260.000 $400.000 $1,823.000 $1,400.000
ASPH (AC-15P OR AC-10-2TR OR CRS-2P)
GAL 1,016.000 $10.000 $23.050 $7.720 $18.000 $12.000 $18.400 $15.000 $24.000 $12.500
CEM STABIL BKFL
CY 200.000 $225.000 $193.000 $242.680 $403.000 $95.000 $322.550 $300.000 $271.000 $330.000
TRENCH EXCAVATION PROTECTION
LF 126.000 $50.000 $12.000 $24.270 $5.000 $1.000 $10.000 $25.000 $5.000 $50.000
SHEET PILING (PZ - 35)
SF 4,275.000 $60.000 $86.190 $72.390 $50.000 $65.000 $75.150 $75.000 $22.000 $87.000
DRILL SHAFT (24 IN)
LF 1,089.000 $250.000 $357.000 $338.880 $250.000 $355.000 $321.500 $350.000 $389.000 $313.000
CL C CONC (ABUT)
CY 66.800 $1,300.000 $906.550 $915.840 $2,000.000 $1,350.000 $1,330.000 $1,800.000 $3,700.000 $2,400.000
CL C CONC (CAP)
CY 23.100 $1,500.000 $1,600.000 $1,332.250 $2,500.000 $1,250.000 $2,180.000 $1,800.000 $3,700.000 $2,600.000
CL C CONC (COLUMN)
CY 7.700 $1,800.000 $1,781.850 $2,257.070 $3,000.000 $1,150.000 $2,485.000 $1,800.000 $3,700.000 $5,300.000
CL C CONC (RAIL FOUNDATION)
CY 1.400 $1,000.000 $1,500.000 $1,124.040 $3,600.000 $2,500.000 $2,030.000 $700.000 $3,700.000 $2,200.000
REINF CONC SLAB (SLAB BEAM)
SF 6,714.000 $25.000 $21.000 $27.970 $36.000 $16.750 $32.100 $30.000 $48.000 $59.000
PRESTR CONC SLAB BEAM (5SB15)
LF 1,312.400 $275.000 $266.000 $262.730 $268.000 $295.000 $252.700 $290.000 $390.000 $280.000
RIPRAP (STONE PROTECTION)(18 IN)
CY 1,169.000 $175.000 $206.230 $261.430 $237.000 $250.000 $234.000 $220.000 $112.000 $220.000
RAIL (TY T223)
LF 542.000 $140.000 $155.000 $74.930 $310.000 $150.000 $190.000 $150.000 $334.000 $215.000
ARMOR JOINT (SEALED)
LF 154.000 $125.000 $99.000 $86.040 $140.000 $200.000 $135.000 $200.000 $212.000 $120.000
RC PIPE (CL III)(18 IN)
LF 332.000 $120.000 $97.130 $63.350 $100.000 $95.000 $113.000 $90.000 $120.000 $76.000
RC PIPE (CL III)(24 IN)
LF 172.000 $130.000 $123.270 $73.060 $105.000 $140.000 $122.000 $110.000 $135.000 $385.000
RC PIPE (CL III)(30 IN)
LF 116.000 $160.000 $189.150 $89.440 $110.000 $170.000 $155.000 $180.000 $175.000 $230.000
SET (TY II) (18 IN) (RCP) (3: 1) (C)
EA 2.000 $2,000.000 $3,331.000 $1,329.210 $3,500.000 $1,600.000 $1,675.000 $1,500.000 $2,000.000 $2,400.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 2.000 $2,100.000 $4,779.000 $1,814.570 $4,500.000 $1,850.000 $2,865.000 $1,900.000 $2,500.000 $1,400.000
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 1.000 $2,700.000 $7,222.000 $2,134.460 $4,700.000 $2,000.000 $4,025.000 $3,200.000 $4,500.000 $1,900.000
SET (TY II) (30 IN) (RCP) (6: 1) (P)
EA 1.000 $3,700.000 $11,609.000 $2,702.550 $4,800.000 $2,300.000 $5,040.000 $5,500.000 $4,500.000 $3,500.000
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
EA 3.000 $35,000.000 $25,000.000 $27,577.000 $25,667.000 $100,000.000 $55,000.000 $40,000.000 $30,000.000 $40,000.000
REMOV STR (SMALL)
EA 5.000 $900.000 $1,822.000 $1,544.310 $3,464.000 $750.000 $925.000 $5,000.000 $2,100.000 $3,000.000
REMOV STR (SMALL FENCE)
LF 530.000 $5.000 $3.000 $7.720 $5.000 $5.000 $15.000 $5.000 $3.000 $5.000
MOBILIZATION
LS 1.000 $224,000.000 $240,000.000 $250,000.000 $250,000.000 $200,000.000 $305,000.000 $300,000.000 $350,000.000 $380,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 15.000 $4,500.000 $1,000.000 $4,681.470 $2,000.000 $4,000.000 $3,375.000 $2,000.000 $1,210.000 $10,000.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 1,406.000 $5.000 $3.000 $1.820 $4.000 $3.000 $4.650 $5.000 $5.500 $4.500
TEMP SEDMT CONT FENCE (REMOVE)
LF 1,406.000 $2.000 $1.000 $1.050 $1.000 $1.000 $1.000 $1.000 $1.250 $1.000
DRIVEWAYS (SURF TREAT)
SY 71.000 $60.000 $47.000 $54.380 $76.000 $10.000 $79.000 $65.000 $340.000 $120.000
MTL W-BEAM GD FEN (TIM POST)
LF 100.000 $30.000 $110.000 $33.090 $31.000 $35.000 $25.750 $30.000 $40.000 $27.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 9.000 $2,300.000 $2,568.500 $1,985.540 $3,432.000 $1,900.000 $2,485.000 $2,300.000 $2,500.000 $2,600.000
MTL BEAM GD FEN TRANS (TL2)
EA 1.000 $1,500.000 $3,900.000 $1,654.620 $1,550.000 $1,650.000 $1,210.000 $1,400.000 $1,885.000 $1,600.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 2.000 $1,600.000 $2,551.000 $1,654.620 $1,260.000 $1,650.000 $1,285.000 $1,500.000 $765.000 $1,500.000
GUARDRAIL END TREATMENT (INSTALL)
EA 8.000 $3,500.000 $3,271.000 $4,191.700 $3,260.000 $4,000.000 $3,040.000 $3,200.000 $3,964.000 $2,900.000
CRASH CUSH ATTEN (INSTL)(L)(N)(TL2)
EA 1.000 $18,000.000 $41,000.000 $36,418.190 $26,000.000 $35,000.000 $35,680.000 $36,000.000 $32,000.000 $25,000.000
CRASH CUSH ATTEN (INSTL)(L)(N)(TL3)
EA 1.000 $25,000.000 $34,000.000 $18,807.510 $32,800.000 $30,000.000 $32,675.000 $30,000.000 $40,000.000 $31,000.000
WIRE FENCE (TY A)
LF 530.000 $20.000 $21.000 $19.860 $16.000 $30.000 $22.700 $23.000 $20.000 $16.000
WIRE FENCE (TY C)
LF 530.000 $20.000 $26.000 $30.890 $12.000 $30.000 $22.700 $23.000 $20.000 $32.000
WIRE FENCE (WATER GAP)
LF 30.000 $75.000 $322.470 $71.700 $74.000 $120.000 $30.900 $160.000 $125.000 $175.000
MAILBOX INSTALL-S (WC-POST) TY 3
EA 1.000 $280.000 $800.000 $361.810 $225.000 $250.000 $1,000.000 $310.000 $255.000 $360.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
EA 12.000 $40.000 $25.000 $24.270 $22.000 $30.000 $20.000 $25.000 $30.000 $25.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 17.000 $40.000 $25.000 $27.580 $24.000 $30.000 $25.000 $30.000 $54.000 $35.000
AMPHIBIAN/REPTILE EXCLUSION FENCE INST
LF 1,500.000 $6.000 $7.000 $4.800 $17.000 $5.000 $11.500 $4.000 $8.500 $4.500
AMPHIBIAN/REPTILE EXCLUSION FENCE REM
LF 1,500.000 $2.000 $1.000 $1.100 $8.000 $1.200 $2.800 $1.000 $3.000 $1.000
Totals: $2,459,978.000 $2,752,206.715 $2,770,708.426 $2,897,486.400 $2,900,848.900 $3,052,433.780 $3,142,891.000 $3,574,427.500 $3,913,016.000