Bid Cobra

TxDOT Subcontracts for SANTA FE CONCRETE SERVICES LLC

Control Number County Highway Bid Date Low Bidder Pay Estimates % of Contract Amount % Complete Contract Amount
2399-01-085 BRAZOS FM 2818 06/05/2025 LARRY YOUNG PAVING, INC. 04/26 | 03/26 | 02/26 | 01/26 | 12/25 9.04% $161,808.71 78.00% $1,789,919.35
0913-09-132 WHARTON VARIOUS 06/05/2025 TI-ZACK CONCRETE, LLC 04/26 | 03/26 | 02/26 | 01/26 | 12/25 3.11% $66,251.50 66.00% $2,130,273.30
0700-01-049 BURNET SH 71 02/06/2025 HUNTER INDUSTRIES, LTD. 04/26 | 03/26 | 02/26 | 01/26 | 12/25 6.31% $450,976.99 85.00% $7,147,020.44
0006-03-121 NOLAN IH 20 11/07/2024 FNF CONSTRUCTION, INC. 05/26 | 04/26 | 03/26 | 02/26 | 01/26 0.83% $290,389.30 88.00% $34,986,662.64
0639-02-034 MADISON FM 39 06/30/2022 BIG CREEK CONSTRUCTION, LTD. 12/25 | 11/25 | 10/25 | 09/25 | 08/25 10.49% $1,580,820.20 104.00% $15,069,782.64