BRAZOS FM 2818 (2399-01-085)
Items: 52
County: BRAZOS
Length: 0.0000 MILES
Highway: FM 2818
District: BRYAN
Control Number: 2399-01-085
DBE Goal: 4.0%
Project: F 2025(793)
Guaranty: $40,000.00
Time: 173 WORKING DAYS
Engineer's Estimate: $2,013,591.48
Date: 06/05/2025 (1 year ago)
Contract Number: 6253222
Type: CONSTRUCT PEDESTRIAN INFRASTRUCTURE
Project ID: A00187707
Contract Type: Federal
Project Description: CONSTRUCT A SHARED USE PATH
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
JAMES ROBBINS
JOSEPH GREIVE
BRAZOS FM 2818 (2399-01-085)
Project Name: N/A
Project: F 2025(793)
Length: 0.0000 MILES
Project Type: CONSTRUCTION
Limits From: 0.5 MI E OF FM 2154
Limits To: 0.1 MI E OF WELSH AVE
Project Description: CONSTRUCT A SHARED USE PATH
BRAZOS FM 2818 (2399-01-087)
Project Name: FM 2818 F: BS 6R T: WELSH - SUP TASA
Project: STP 2025(827)TAPS
Length: 0.0000 MILES
Project Type: PEDESTRIAN, SIDEWALKS & CURB RAMPS
Limits From: 0.1 MI E OF WELSH AVE.
Limits To: BS 6R
Project Description: CONSTRUCT 10 FT WIDE SHARED USE PATH INCLUDING A PEDESTRIAN BRIDGE, ADA RAMPS, PEDESTRIAN BUTTONS, CROSSWALKS, AND UPGRADED DRAINAGE
Bidders (10)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$2,013,591.48 | |||
| $1,789,919.35 |
-11.11%
-$223,672.13
|
|||
| $1,892,754.91 |
-6%
-$120,836.57
|
5.75%
$102,835.56
|
||
| $1,965,065.60 |
-2.41%
-$48,525.88
|
9.79%
$175,146.25
|
-3.82%
-$72,310.69
|
|
| $1,974,590.03 |
-1.94%
-$39,001.45
|
10.32%
$184,670.68
|
-0.48%
-$9,524.43
|
|
| $1,977,474.50 |
-1.79%
-$36,116.98
|
10.48%
$187,555.15
|
-0.15%
-$2,884.47
|
|
| $1,979,260.10 |
-1.7%
-$34,331.38
|
10.58%
$189,340.75
|
-0.09%
-$1,785.60
|
|
| $2,023,517.20 |
0.49%
$9,925.72
|
13.05%
$233,597.85
|
-2.24%
-$44,257.10
|
|
| $2,048,057.60 |
1.71%
$34,466.12
|
14.42%
$258,138.25
|
-1.21%
-$24,540.40
|
|
| $2,049,715.00 |
1.79%
$36,123.52
|
14.51%
$259,795.65
|
-0.08%
-$1,657.40
|
|
| $2,069,684.70 |
2.79%
$56,093.22
|
15.63%
$279,765.35
|
-0.97%
-$19,969.70
|
E
Engineer's Estimate
$2,013,591.48
1
Awarded
$1,789,919.35
Over/Under Est:
-11.11%
-$223,672.13
$1,892,754.91
Over/Under Est:
-6%
-$120,836.57
Amt Left:
5.75%
$102,835.56
$1,965,065.60
Over/Under Est:
-2.41%
-$48,525.88
Amt Left:
9.79%
$175,146.25
Delta:
-3.82%
-$72,310.69
$1,974,590.03
Over/Under Est:
-1.94%
-$39,001.45
Amt Left:
10.32%
$184,670.68
Delta:
-0.48%
-$9,524.43
$1,977,474.50
Over/Under Est:
-1.79%
-$36,116.98
Amt Left:
10.48%
$187,555.15
Delta:
-0.15%
-$2,884.47
$1,979,260.10
Over/Under Est:
-1.7%
-$34,331.38
Amt Left:
10.58%
$189,340.75
Delta:
-0.09%
-$1,785.60
$2,023,517.20
Over/Under Est:
0.49%
$9,925.72
Amt Left:
13.05%
$233,597.85
Delta:
-2.24%
-$44,257.10
$2,048,057.60
Over/Under Est:
1.71%
$34,466.12
Amt Left:
14.42%
$258,138.25
Delta:
-1.21%
-$24,540.40
$2,049,715.00
Over/Under Est:
1.79%
$36,123.52
Amt Left:
14.51%
$259,795.65
Delta:
-0.08%
-$1,657.40
$2,069,684.70
Over/Under Est:
2.79%
$56,093.22
Amt Left:
15.63%
$279,765.35
Delta:
-0.97%
-$19,969.70
| Subcontractor | Percentage | Amount |
|---|---|---|
| SANTA FE CONCRETE SERVICES LLC | 9.04% | $161,808.71 |
| TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. | 4.96% | $88,780.00 |
| CEN TEX HYDROSEED, INC. | 1.99% | $35,619.40 |
| TRAFFIC SIGNS & LINES, LLC | 1.19% | $21,300.04 |
| COASTAL FOUNDATION DRILLING CO., INC. | 0.56% | $10,023.55 |
| CEN-TREE SOLUTIONS LLC | 0.18% | $3,221.85 |
| Total: | 17.92% | $320,753.55 |
Bid Items & Bid Tabulations
52
Total
0 of 52
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
| Description | Amount |
|---|---|
| SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) | $45,000.00 |
| EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) | $10,000.00 |
| LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (PART) | $2,000.00 |
| Total: | $57,000.00 |