BURNET SH 71 (0700-01-049)
Items: 127
County: BURNET
Length: 0.0000 MILES
Highway: SH 71
District: AUSTIN
Control Number: 0700-01-049
DBE Goal: 6.0%
Project: STP 2025(431)HES
Guaranty: $100,000.00
Time: 185 WORKING DAYS
Engineer's Estimate: $6,847,444.59
Date: 02/06/2025 (1 year ago)
Contract Number: 2253012
Type: WIDEN ROAD - ADD SHOULDERS
Project ID: A00184596
Contract Type: Federal
Project Description: INSTALL CONTINUOUS TURN LANE, WIDEN PAVED SHOULDERS (TO >5 FT.)
Mail/Deliver Bids To: N/A
JOE MUCK
TYLER BRUDNICK
BURNET SH 71 (0700-01-049)
Project Name: N/A
Project: STP 2025(431)HES
Length: 0.0000 MILES
Project Type: CONSTRUCTION
Limits From: 0.75 MI W OF CR 401
Limits To: 0.75 MI E OF CR 401
Project Description: INSTALL CONTINUOUS TURN LANE, WIDEN PAVED SHOULDERS (TO >5 FT.)
BURNET SH 71 (0700-01-052)
Project Name: SH 71 - W & E OF CR 401
Project: F 2025(437)
Length: 0.0000 MILES
Project Type: INTERSECTION & OPERATIONAL IMPRV
Limits From: 0.135 MI W OF CR 401
Limits To: 0.135 MI E OF CR 401
Project Description: INSTALL TRAFFIC SIGNAL, RIGHT TURN LANES
Bidders (8)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$6,847,444.59 | |||
| $7,072,727.55 |
3.29%
$225,282.96
|
|||
| $7,134,113.80 |
4.19%
$286,669.21
|
0.87%
$61,386.25
|
||
| $7,454,914.35 |
8.87%
$607,469.76
|
5.4%
$382,186.80
|
-4.50%
-$320,800.55
|
|
| $7,631,214.05 |
11.45%
$783,769.46
|
7.9%
$558,486.50
|
-2.36%
-$176,299.70
|
|
| $7,724,046.84 |
12.8%
$876,602.25
|
9.21%
$651,319.29
|
-1.22%
-$92,832.79
|
|
| $8,355,246.24 |
22.02%
$1,507,801.65
|
18.13%
$1,282,518.69
|
-8.17%
-$631,199.40
|
|
| $8,664,286.86 |
26.53%
$1,816,842.27
|
22.5%
$1,591,559.31
|
-3.70%
-$309,040.62
|
|
| $9,723,815.50 |
42.01%
$2,876,370.91
|
37.48%
$2,651,087.95
|
-12.23%
-$1,059,528.64
|
E
Engineer's Estimate
$6,847,444.59
1
Awarded
$7,072,727.55
Over/Under Est:
3.29%
$225,282.96
$7,134,113.80
Over/Under Est:
4.19%
$286,669.21
Amt Left:
0.87%
$61,386.25
$7,454,914.35
Over/Under Est:
8.87%
$607,469.76
Amt Left:
5.4%
$382,186.80
Delta:
-4.50%
-$320,800.55
$7,631,214.05
Over/Under Est:
11.45%
$783,769.46
Amt Left:
7.9%
$558,486.50
Delta:
-2.36%
-$176,299.70
$7,724,046.84
Over/Under Est:
12.8%
$876,602.25
Amt Left:
9.21%
$651,319.29
Delta:
-1.22%
-$92,832.79
$8,355,246.24
Over/Under Est:
22.02%
$1,507,801.65
Amt Left:
18.13%
$1,282,518.69
Delta:
-8.17%
-$631,199.40
$8,664,286.86
Over/Under Est:
26.53%
$1,816,842.27
Amt Left:
22.5%
$1,591,559.31
Delta:
-3.70%
-$309,040.62
$9,723,815.50
Over/Under Est:
42.01%
$2,876,370.91
Amt Left:
37.48%
$2,651,087.95
Delta:
-12.23%
-$1,059,528.64
| Subcontractor | Percentage | Amount |
|---|---|---|
| SANTA FE CONCRETE SERVICES LLC | 6.31% | $450,976.99 |
| E-Z BEL CONSTRUCTION, LLC | 5.07% | $362,353.94 |
| LONE STAR EROSION CONTROL | 2.74% | $195,828.36 |
| TRP CONSTRUCTION GROUP, LLC | 2.22% | $158,663.85 |
| 4E TREE WORX LLC | 0.42% | $30,017.49 |
| GBC GENERAL BARRICADE COMPANY LLC | 0.36% | $25,729.27 |
| LAWLEY CONTRACTING, LLC | 0.00% | $0.00 |
| MG DRILLING FOUNDATION, LLC | 0.00% | $0.00 |
| Total: | 17.12% | $1,223,569.90 |
Bid Items & Bid Tabulations
127
Total
0 of 127