Control Number County Highway Bid Date Low Bidder Pay Estimates % of Contract Amount % Complete Contract Amount
0176-04-056 POLK US 59 05/05/2022 JAMES CONSTRUCTION GROUP, LLC 05/26 | 04/26 | 03/26 | 02/26 | 01/26 0.23% $411,008.32 82.00% $178,699,269.14
0200-16-020 JEFFERSON US 69 09/02/2021 WILLIAMS BROTHERS CONSTRUCTION CO., INC. 05/26 | 04/26 | 03/26 | 02/26 | 01/26 0.15% $122,374.05 76.00% $81,582,703.12
0028-03-107 LIBERTY US 90 08/05/2021 JAMES CONSTRUCTION GROUP, LLC 04/26 | 03/26 | 02/26 | 01/26 | 12/25 0.05% $22,937.50 100.00% $45,874,999.14
0195-01-119 COOKE IH 35 02/05/2021 AUSTIN BRIDGE & ROAD SERVICES, LP 05/26 | 04/26 | 03/26 | 02/26 | 01/26 0.62% $1,305,897.38 96.00% $210,628,609.25
0005-14-067 MIDLAND IH 20 02/04/2021 JAMES CONSTRUCTION GROUP, L.L.C. 05/26 | 04/26 | 03/26 | 02/26 | 01/26 0.08% $39,629.79 104.00% $49,537,239.68
0028-14-091 ORANGE IH 10 06/05/2020 WILLIAMS BROTHERS CONSTRUCTION CO., INC. 05/26 | 04/26 | 03/26 | 02/26 | 01/26 0.61% $340,602.19 102.00% $55,836,425.37
1258-04-065 HARRIS FM 1093 09/06/2019 HARPER BROTHERS CONSTRUCTION LLC 08/25 | 07/25 | 06/25 | 05/25 | 04/25 0.74% $89,117.78 99.00% $12,042,943.12
0500-04-105 GALVESTON IH 45 08/07/2019 WILLIAMS BROTHERS CONSTRUCTION CO., INC. 04/26 | 03/26 | 02/26 | 01/26 | 12/25 0.50% $856,117.58 86.00% $171,223,516.80
0739-02-162 JEFFERSON IH 10 07/11/2018 JOHNSON BROS. CORPORATION, A SOUTHLAND COMPANY 04/26 | 03/26 | 02/26 | 01/26 | 12/25 0.41% $559,905.74 86.00% $136,562,374.44
0500-04-106 GALVESTON IH 45 06/05/2018 WILLIAMS BROTHERS CONSTRUCTION CO., INC. 04/26 | 03/26 | 02/26 | 01/26 | 12/25 0.60% $1,494,530.03 81.00% $249,088,339.11