| Control Number | County | Highway | Bid Date | Low Bidder | Pay Estimates | % of Contract | Amount | % Complete | Contract Amount |
|---|---|---|---|---|---|---|---|---|---|
| 2305-01-014 | BOSQUE | FM 2114 | 06/02/2023 | BIG CREEK CONSTRUCTION, LTD. | 12/25 | 11/25 | 10/25 | 09/25 | 08/25 | 0.03% | $4,044.37 | 88.00% | $13,481,238.33 |
| 0257-03-033 | EASTLAND | SH 6 | 01/06/2022 | BIG CREEK CONSTRUCTION, LTD. | 08/25 | 07/25 | 06/25 | 05/25 | 04/25 | 0.06% | $6,586.43 | 107.00% | $10,977,389.53 |
| 0257-04-029 | EASTLAND | SH 6 | 09/02/2021 | BIG CREEK CONSTRUCTION, LTD. | 10/24 | 09/24 | 08/24 | 07/24 | 06/24 | 0.06% | $6,352.42 | 100.00% | $10,587,368.26 |
| 0258-02-059 | ERATH | SH 6 | 10/02/2020 | BIG CREEK CONSTRUCTION, LTD. | 07/25 | 06/25 | 05/25 | 04/25 | 03/25 | 0.00% | $0.00 | 102.00% | $35,379,498.13 |