EASTLAND SH 6 (0257-04-029)

Items: 106

County: EASTLAND
Length: N/A
Highway: SH 6
District: BROWNWOOD
Control Number: 0257-04-029
DBE Goal: N/A
Project: F 2022(007)
Guaranty: N/A
Time: 230 WORKING DAYS
Engineer's Estimate: $11,744,639.75
Date: 09/02/2021 (4 years ago)
Contract Number: N/A
Type: HIGHWAY IMPROVEMENT
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Documents:
Bidders (6)
E
Engineer's Estimate
$11,744,639.75
$10,587,368.26
Over/Under Est: -9.85% -$1,157,271.49
Over/Under Est: -4.02% -$471,939.07
Amt Left: 6.47% $685,332.42
$11,420,827.83
Over/Under Est: -2.76% -$323,811.92
Amt Left: 7.87% $833,459.57
Delta: -1.31% -$148,127.15
$14,311,938.57
Over/Under Est: 21.86% $2,567,298.82
Amt Left: 35.18% $3,724,570.31
Delta: -25.31% -$2,891,110.74
$15,184,259.35
Over/Under Est: 29.29% $3,439,619.60
Amt Left: 43.42% $4,596,891.09
Delta: -6.10% -$872,320.78
$15,425,173.16
Over/Under Est: 31.34% $3,680,533.41
Amt Left: 45.69% $4,837,804.90
Delta: -1.59% -$240,913.81
Subcontractor Percentage Amount
4-WAY HAULERS, LLC 6.08% $643,711.99
CRUZ HERNANDEZ CONCRETE CONSTRUCTION 4.93% $521,957.26
TRP CONSTRUCTION GROUP, LLC 1.61% $170,456.63
COMEN ENTERPRISE LLC 1.51% $159,869.26
D. I. J. CONSTRUCTION, INC. 1.48% $156,693.05
WILKO INDUSTRIAL, L.L.C. 0.67% $70,935.37
ODUM SERVICES, LLC 0.55% $58,230.53
WOLFE CONSTRUCTION GROUP, INCORPORATED 0.54% $57,171.79
PINNACLE GRINDING AND GROOVING LLC 0.21% $22,233.47
TEXAS TRAFFIC AND BARRICADE, LLC 0.19% $20,116.00
PRECISION PAVEMENT MAINTENANCE, LLC 0.06% $6,352.42
DALLAS LITE AND BARRICADE, INC. 0.00% $0.00
Total: 17.83% $1,887,727.77

Bid Items & Bid Tabulations

106 Total 0 of 106
EASTLAND  |  SH 6  |  BROWNWOOD  |  0257-04-029  |  09/02/2021  |  $11,744,639.75  |  F 2022(007)  |  HWY IMPRV  |  230 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
BIG CREEK CONSTRUCTION, LTD.
JAY MILLS CONTRACTING, INCORPORATED
A. L. HELMCAMP, INC.
DELHUR INDUSTRIES, INC.
ALTUS CONSTRUCTION LLC
RK HALL, LLC
PREPARING ROW
STA 392.000 $1,200.000 $500.000 $450.000 $950.000 $660.000 $709.270 $158.420
EXCAVATION (ROADWAY)
CY 20,815.000 $20.000 $12.000 $10.000 $9.000 $11.000 $17.500 $10.750
EMBANKMENT (FINAL)(DENS CONT)(TY C)
CY 5,669.000 $18.000 $12.000 $5.000 $10.000 $3.300 $36.210 $16.440
BLADING
STA 473.180 $100.000 $250.000 $140.000 $45.000 $198.000 $394.500 $159.840
DRILL SEEDING (PERM) (RURAL) (SANDY)
SY 234,649.000 $0.150 $0.120 $0.140 $0.110 $0.143 $0.110 $0.110
DRILL SEEDING (TEMP) (WARM)
SY 117,325.000 $0.200 $0.100 $0.130 $0.080 $0.110 $0.090 $0.080
DRILL SEEDING (TEMP) (COOL)
SY 117,325.000 $0.200 $0.110 $0.130 $0.090 $0.110 $0.100 $0.090
VEGETATIVE WATERING
MG 5,269.000 $13.000 $5.000 $9.800 $5.000 $43.600 $1.150 $43.130
PROOF ROLLING
HR 32.000 $120.000 $110.000 $85.000 $85.000 $110.000 $114.510 $120.170
FL BS (CMP IN PLC)(TYD GR1-2)(FNAL POS)
CY 23,645.000 $37.000 $50.000 $35.000 $40.000 $48.023 $43.930 $40.800
FL BS (CMP IN PLC)(TY D GR 4)(FNAL POS)
CY 2,774.000 $155.000 $50.000 $96.500 $45.000 $54.073 $43.930 $66.120
REWRK BS MTL (TY C)(18")(DENS CONT)
SY 8,593.000 $10.000 $8.000 $3.750 $1.500 $2.400 $12.090 $4.610
RWRK BS MTL (TY C)(0"-15")(DENS CONT)
SY 8,499.000 $8.000 $6.000 $2.250 $1.500 $2.400 $6.950 $7.410
PRIME COAT (RC-250)
GAL 12,481.000 $3.500 $3.700 $4.100 $4.300 $5.280 $8.500 $4.570
FOG SEAL (CSS-1H)
GAL 52,257.000 $4.000 $1.000 $3.400 $3.300 $3.289 $8.060 $7.750
ASPH (AC-20-5TR)
GAL 54,871.000 $4.000 $3.400 $3.450 $3.300 $4.543 $5.280 $3.440
ASPH (CRS-2P)
GAL 65,324.000 $4.000 $3.300 $3.350 $2.800 $4.433 $4.970 $3.620
AGGR(TY-B GR-5 SAC-B)
CY 454.000 $120.000 $110.000 $90.000 $150.000 $111.800 $202.160 $201.500
AGGR(TY-PB GR-3 SAC-B)
CY 2,178.000 $105.000 $120.000 $119.000 $150.000 $133.800 $250.700 $234.530
TEMPORARY SPL SHORING
SF 3,297.000 $20.000 $30.000 $25.300 $55.000 $60.500 $22.900 $57.750
RIPRAP (CONC)(5 IN)
CY 44.700 $580.000 $600.000 $583.000 $580.000 $605.000 $424.500 $577.500
RIPRAP (MOW STRIP)(4 IN)
CY 191.000 $395.000 $500.000 $583.000 $610.000 $632.500 $381.350 $603.750
CMP (GAL STL 24 IN)
LF 436.000 $80.000 $80.000 $66.000 $110.000 $110.000 $71.590 $105.000
CMP (GAL STL 30 IN)
LF 8.000 $90.000 $150.000 $83.000 $230.000 $242.000 $305.070 $231.000
CMP (GAL STL 36 IN)
LF 8.000 $100.000 $170.000 $99.000 $260.000 $275.000 $315.890 $262.500
CMP AR (GAL STL DES 3)
LF 292.000 $75.000 $100.000 $73.000 $110.000 $110.000 $106.020 $105.000
CONC BOX CULV (3 FT X 2 FT)(EXTEND)
LF 25.000 $850.000 $500.000 $473.000 $620.000 $643.500 $766.760 $614.250
CONC BOX CULV (3 FT X 3 FT)(EXTEND)
LF 23.000 $700.000 $600.000 $500.500 $410.000 $737.000 $774.720 $703.500
CONC BOX CULV (4 FT X 3 FT)(EXTEND)
LF 19.000 $750.000 $625.000 $577.500 $810.000 $847.000 $813.280 $808.500
CONC BOX CULV (4 FT X 4 FT)(EXTEND)
LF 24.000 $600.000 $700.000 $665.500 $900.000 $940.500 $873.220 $897.750
CONC BOX CULV (5 FT X 3 FT)(EXTEND)
LF 27.000 $500.000 $725.000 $654.500 $910.000 $954.800 $998.970 $911.400
CONC BOX CULV (5 FT X 4 FT)(EXTEND)
LF 33.000 $610.000 $800.000 $731.500 $1,000.000 $1,050.500 $970.640 $1,002.750
CONC BOX CULV (6 FT X 4 FT)(EXTEND)
LF 30.000 $650.000 $950.000 $825.000 $1,100.000 $1,155.000 $560.490 $1,102.500
CONC BOX CULVERT (2 FT X 2 FT) (EXTEND)
LF 101.000 $630.000 $450.000 $368.500 $500.000 $517.000 $566.490 $493.500
RC PIPE (CL III)(24 IN)
LF 28.000 $180.000 $120.000 $85.000 $160.000 $165.000 $115.880 $157.500
SET (TY I)(S=2 FT)(HW=3FT)(3:1)(C)
EA 8.000 $4,500.000 $6,500.000 $3,080.000 $4,700.000 $4,950.000 $3,839.490 $4,725.000
SET (TY I)(S=3 FT)(HW=3FT)(3:1)(C)
EA 1.000 $6,500.000 $7,000.000 $3,500.000 $5,000.000 $5,225.000 $5,759.240 $4,882.500
SET (TY I)(S=3 FT)(HW=3FT)(4:1)(C)
EA 1.000 $7,200.000 $7,500.000 $2,750.000 $6,200.000 $6,435.000 $5,759.240 $6,142.500
SET (TY I)(S=3 FT)(HW= 4 FT)(3:1)(C)
EA 2.000 $8,000.000 $9,000.000 $4,400.000 $5,900.000 $6,121.500 $5,058.320 $5,843.250
SET (TY I)(S= 4 FT)(HW= 4 FT)(3:1) (C)
EA 1.000 $6,000.000 $10,000.000 $11,000.000 $15,000.000 $14,960.000 $7,587.480 $14,280.000
SET (TY I)(S= 4 FT)(HW= 5 FT)(3:1) (C)
EA 2.000 $8,400.000 $14,000.000 $15,400.000 $19,000.000 $20,130.000 $10,224.200 $19,215.000
SET (TY I)(S= 5 FT)(HW= 4 FT)(3:1) (C)
EA 2.000 $7,000.000 $12,000.000 $12,100.000 $15,000.000 $15,510.000 $10,907.840 $14,805.000
SET (TY I)(S= 5 FT)(HW= 5 FT)(3:1) (C)
EA 16.000 $7,500.000 $6,000.000 $14,300.000 $8,000.000 $8,250.000 $12,648.090 $7,875.000
SET (TY I)(S= 6 FT)(HW= 5 FT)(3:1) (C)
EA 2.000 $8,000.000 $14,000.000 $17,600.000 $20,000.000 $20,680.000 $12,295.080 $19,740.000
SET (TY I)(S= 6 FT)(HW= 6 FT)(3:1) (C)
EA 6.000 $9,000.000 $8,000.000 $16,060.000 $9,000.000 $9,350.000 $17,566.920 $8,925.000
SET (TY II) (24 IN) (CMP) (6: 1) (P)
EA 30.000 $1,200.000 $1,500.000 $1,300.000 $1,500.000 $1,540.000 $1,734.300 $1,470.000
SET (TY II) (24 IN) (RCP) (4: 1) (C)
EA 2.000 $1,300.000 $1,400.000 $1,050.000 $1,300.000 $1,320.000 $1,800.720 $1,260.000
SET (TY II) (30 IN) (RCP) (6: 1) (P)
EA 2.000 $1,750.000 $2,500.000 $2,000.000 $3,200.000 $3,300.000 $3,183.470 $3,150.000
SET (TY II) (36 IN) (CMP) (6: 1) (P)
EA 2.000 $3,400.000 $4,500.000 $3,275.000 $3,900.000 $4,125.000 $5,156.620 $3,937.500
SET (TY II) (DES 3) (CMP) (6: 1) (P)
EA 34.000 $1,750.000 $2,000.000 $1,850.000 $3,200.000 $3,300.000 $1,762.060 $3,150.000
CLEAN EXIST CULVERTS
EA 16.000 $2,100.000 $1,000.000 $1,050.000 $1,600.000 $1,650.000 $2,048.370 $1,312.500
REMOV STR (PIPE)
EA 13.000 $500.000 $500.000 $265.000 $260.000 $275.000 $430.750 $262.500
MOBILIZATION
LS 1.000 $750,000.000 $800,000.000 $925,000.000 $860,000.000 $1,312,355.000 $1,500,122.870 $1,532,872.520
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 14.000 $25,000.000 $2,500.000 $4,800.000 $8,500.000 $10,144.000 $28,628.300 $20,200.420
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 600.000 $35.000 $25.000 $33.000 $36.000 $29.700 $28.850 $37.060
ROCK FILTER DAMS (REMOVE)
LF 600.000 $10.000 $5.000 $11.000 $11.000 $8.800 $8.590 $23.210
TEMP SEDMT CONT FENCE (INSTALL)
LF 1,000.000 $3.500 $4.000 $3.850 $3.000 $6.955 $3.320 $5.600
TEMP SEDMT CONT FENCE (REMOVE)
LF 1,000.000 $0.750 $1.000 $1.100 $1.000 $0.825 $1.150 $2.170
BIODEG EROSN CONT LOGS (INSTL) (18")
LF 2,120.000 $5.000 $5.000 $6.600 $5.000 $5.225 $5.290 $5.020
BIODEG EROSN CONT LOGS (REMOVE)
LF 2,120.000 $1.000 $1.000 $1.100 $0.650 $1.375 $0.690 $1.410
ONE-WAY TRAF CONT (FLAGGER CONT)
HR 808.000 $70.000 $80.000 $98.000 $1.000 $60.000 $89.480 $109.450
ONE-WAY TRAF CONT (PILOT CAR)
HR 1,448.000 $80.000 $120.000 $98.000 $1.000 $120.000 $129.160 $124.280
ONE-WAY TRAF CONT (PORT TRAF SIG)
MO 3.000 $3,800.000 $5,300.000 $6,650.000 $7,000.000 $5,500.000 $5,725.660 $5,967.290
PORT CTB (DES SOURCE)(SGL SLP)(TY 1)
LF 2,940.000 $20.000 $7.000 $7.300 $20.000 $52.119 $9.480 $24.890
PORT CTB (MOVE)(SGL SLP)(TY 1)
LF 2,940.000 $5.000 $5.000 $3.500 $14.000 $5.625 $12.200 $6.200
PORT CTB (REMOVE)(SGL SLP)(TY 1)
LF 2,940.000 $6.000 $7.000 $7.300 $15.000 $9.681 $9.190 $24.890
DRIVEWAYS (ACP)
SY 2,267.110 $40.000 $20.000 $43.250 $21.000 $78.635 $46.780 $50.430
DRIVEWAYS (SURF TREAT)
SY 6,271.740 $20.000 $5.000 $20.500 $21.000 $33.309 $18.060 $53.130
TURNOUTS (ACP)
SY 33.000 $40.000 $75.000 $43.250 $130.000 $316.500 $91.610 $528.680
RUMBLE STRIPS (SHOULDER)
LF 94,637.000 $0.200 $0.180 $0.100 $0.160 $0.102 $0.100 $0.170
RUMBLE STRIPS (CENTERLINE)
LF 47,318.000 $0.200 $0.180 $0.100 $0.160 $0.102 $0.100 $0.170
MTL W-BEAM GD FEN (STEEL POST)
LF 1,925.000 $28.000 $35.000 $35.750 $31.000 $34.925 $20.960 $30.450
GUARDRAIL END TREATMENT (INSTALL)
EA 12.000 $2,600.000 $3,500.000 $3,025.000 $2,900.000 $3,630.000 $2,337.830 $2,929.500
CRASH CUSH ATTEN (MOVE & RESET)
EA 2.000 $1,200.000 $2,000.000 $2,000.000 $730.000 $825.000 $1,878.020 $2,341.100
CRASH CUSH ATTEN (REMOVE)
EA 2.000 $1,270.000 $1,200.000 $1,350.000 $730.000 $550.000 $764.860 $2,341.100
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
EA 2.000 $10,000.000 $14,000.000 $9,600.000 $8,000.000 $8,135.000 $3,679.690 $10,358.860
MAILBOX INSTALL-S (WC-POST) TY 3
EA 3.000 $175.000 $300.000 $275.000 $260.000 $181.500 $188.950 $262.500
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 2.000 $800.000 $600.000 $737.000 $790.000 $902.000 $939.010 $787.500
IN SM RD SN SUP&AM TYTWT(1)WS(P)
EA 24.000 $455.000 $500.000 $484.000 $580.000 $599.500 $624.100 $577.500
REMOVE SM RD SN SUP&AM
EA 13.000 $101.000 $100.000 $22.000 $79.000 $55.000 $91.110 $107.130
INSTL OM ASSM (OM-2Y)(WC)GND
EA 40.000 $70.000 $100.000 $93.500 $79.000 $63.800 $115.090 $78.750
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 24.000 $60.000 $50.000 $25.300 $31.000 $31.900 $28.340 $30.450
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
LF 191,195.000 $0.150 $0.250 $0.310 $0.250 $0.275 $0.290 $0.250
WK ZN PAV MRK NON-REMOV (W)24"(SLD)
LF 96.000 $15.000 $10.000 $11.000 $6.300 $6.600 $6.870 $6.300
WK ZN PAV MRK NON-REMOV (Y)4"(BRK)
LF 103,424.000 $0.200 $0.220 $0.090 $0.210 $0.275 $0.290 $0.210
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 8,890.000 $0.500 $0.440 $0.530 $0.420 $0.275 $0.290 $0.420
WK ZN PAV MRK REMOV (REFL) TY II-A-A
LF 2,870.000 $0.800 $1.000 $4.950 $0.790 $3.630 $3.780 $0.790
WK ZN PAV MRK REMOV (Y)4"(SLD)
LF 20,800.000 $1.050 $1.000 $0.660 $0.950 $0.880 $0.920 $0.950
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 56,784.000 $0.500 $1.000 $1.300 $0.500 $1.925 $1.260 $2.930
REFL PAV MRK TY I (W)4"(DOT)(100MIL)
LF 1,356.000 $1.500 $1.500 $0.720 $1.310 $1.100 $1.150 $1.310
REFL PAV MRK TY I(W)(LNDP ARW)(100MIL)
EA 8.000 $350.000 $350.000 $605.000 $315.000 $275.000 $286.280 $315.000
RE PM W/RET REQ TY I (W)4"(BRK)(100MIL)
LF 7,350.000 $0.250 $0.400 $0.500 $0.380 $0.484 $0.500 $0.380
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 94,840.000 $0.250 $0.400 $0.480 $0.380 $0.440 $0.460 $0.380
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
LF 1,892.000 $0.250 $0.400 $0.500 $0.380 $0.484 $0.500 $0.380
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 81,149.000 $0.250 $0.400 $0.480 $0.380 $0.440 $0.460 $0.380
REFL PAV MRKR TY I-C
EA 368.000 $3.500 $6.000 $5.500 $5.250 $3.630 $3.780 $5.250
REFL PAV MRKR TY II-A-A
EA 1,186.000 $3.000 $4.000 $5.500 $3.680 $3.630 $3.780 $3.680
ELIM EXT PAV MRK & MRKS (4")
LF 5,128.000 $0.550 $0.700 $1.900 $0.530 $0.825 $0.860 $0.530
SP MIXES SP-C SAC-B PG76-22
TON 29,003.000 $90.000 $82.000 $90.500 $90.330 $96.052 $105.950 $92.810
CEMENT
TON 1,433.000 $150.000 $200.000 $178.000 $185.000 $190.784 $226.450 $206.070
ASPHALT BINDER (PG 64-22)
TON 3,219.000 $425.000 $500.000 $500.000 $500.000 $613.800 $596.220 $545.660
FOAMED ASPHALT TREAT (10")(DC)
SY 137,794.000 $3.000 $2.200 $3.400 $3.800 $6.276 $6.320 $9.000
FOAMED ASPHALT TREAT (12")(DC)
SY 123,499.000 $4.500 $2.400 $3.750 $4.800 $7.003 $5.770 $10.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 4.000 $5,975.000 $10,000.000 $11,000.000 $10,000.000 $9,240.000 $4,007.960 $24,033.170
TMA (STATIONARY)
DAY 346.000 $200.000 $150.000 $210.000 $125.000 $264.000 $171.770 $383.310
TMA (MOBILE OPERATION)
HR 440.000 $20.000 $50.000 $22.000 $30.000 $55.000 $57.260 $49.550
Totals: $11,744,639.750 $10,587,368.260 $11,272,700.688 $11,420,827.830 $14,311,938.652 $15,184,259.360 $15,425,173.175