Control Number County Highway Bid Date Low Bidder Pay Estimates % of Contract Amount % Complete Contract Amount
6491-37-001 NAVARRO IH0045 01/07/2026 ROY JORGENSEN ASSOCIATES, INC. 05/26 | 04/26 | 03/26 0.00% $0.00 22.00% $1,224,500.00
2264-01-012 ELLIS FM 2377 08/08/2025 KNIFE RIVER CORPORATION - SOUTH 05/26 | 04/26 | 03/26 | 02/26 | 01/26 0.03% $1,960.65 66.00% $6,535,504.83
0712-03-013 ELLIS FM 916 06/05/2024 KNIFE RIVER CORPORATION - SOUTH 05/26 | 04/26 | 03/26 | 02/26 | 01/26 0.02% $1,791.92 101.00% $8,959,575.54
6450-13-001 BELL IH0035 08/03/2023 ROY JORGENSEN ASSOCIATES, INC. 05/26 | 04/26 | 03/26 | 02/26 | 01/26 0.19% $73,803.12 73.00% $38,843,747.36