Bid Cobra

KARNES FM 81 (1123-01-016)

Items: 73

County: KARNES
Length: N/A
Highway: FM 81
District: CORPUS CHRISTI
Control Number: 1123-01-016
DBE Goal: N/A
Project: F 2024(379)
Guaranty: N/A
Time: 123 WORKING DAYS
Engineer's Estimate: $7,558,774.95
Date: 11/01/2023 (2 years ago)
Contract Number: N/A
Type: REHABILITATE EXISTING ROADWAY
Mail/Deliver Bids To: N/A
NICK NOVOSAD
ROBERTO A JIMENEZ
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (3)
E
Engineer's Estimate
$7,558,774.95
$6,545,352.98
Over/Under Est: -13.41% -$1,013,421.97
Over/Under Est: -8.71% -$658,030.46
Amt Left: 5.43% $355,391.51
Over/Under Est: 5.47% $413,165.49
Amt Left: 21.8% $1,426,587.46
Delta: -15.52% -$1,071,195.95
Subcontractor Percentage Amount
ANTS CONTRACTORS LLC 8.10% $566,480.72
A K FUQUAY CONSTRUCTION 2.78% $194,421.78
HIGHWAY BARRICADES AND SERVICES, LLC 2.33% $162,950.63
MURRAY CONSTRUCTION 1.82% $127,283.32
RELMCO, INC. 0.87% $60,844.23
DUSTROL, INC. 0.84% $58,746.15
SOIL TECH ADVANCE INC. 0.58% $40,562.82
EGGEMEYER LAND CLEARING, LLC 0.22% $15,385.90
LISKA CONSTRUCTION COMPANY, INC. 0.18% $12,588.46
WEST TEXAS ROCK RESOURCES, LLC 0.16% $11,189.74
MPB, INC. 0.12% $8,392.31
Total: 18.00% $1,258,846.06

Bid Items & Bid Tabulations

73 Total 0 of 73
KARNES  |  FM 81  |  CORPUS CHRISTI  |  1123-01-016  |  11/01/2023  |  $7,558,774.95  |  F 2024(379)  |  REHAB EXIST ROADWAY  |  123 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
CK NEWBERRY, LLC
HUNTER INDUSTRIES, LTD.
TEXAS MATERIALS GROUP, INC.
PREPARING ROW
STA 269.000 $1,500.000 $250.000 $510.600 $730.000
EXCAVATION (ROADWAY)
CY 15,911.000 $11.000 $16.000 $23.600 $26.000
EMBANKMENT (FINAL)(ORD COMP)(TY D)
CY 5,431.000 $14.000 $10.000 $23.600 $24.000
DRILL SEEDING (PERM) (RURAL) (CLAY)
SY 52,999.000 $0.350 $0.330 $0.480 $0.480
DRILL SEED (TEMP)(WARM OR COOL)
SY 52,999.000 $0.200 $0.290 $0.400 $0.400
VEGETATIVE WATERING
MG 3,182.000 $30.000 $15.000 $17.500 $24.000
FL BS (CMP IN PLC)(TY A GR 5)(FNAL POS)
CY 34.000 $115.000 $400.000 $346.990 $228.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(8")
SY 3,166.000 $65.000 $80.000 $58.680 $83.000
PLANE ASPH CONC PAV(0" TO 2")
SY 948.000 $10.000 $8.000 $9.900 $6.000
FLOWABLE BACKFILL
CY 42.000 $400.000 $300.000 $480.000 $210.000
TEMPORARY SPL SHORING
SF 5,836.000 $45.000 $20.000 $65.000 $60.000
RIPRAP (CONC)(4 IN)
CY 97.000 $600.000 $500.000 $610.200 $565.000
RIPRAP (CONC)(5 IN)
CY 38.000 $550.000 $525.000 $756.000 $700.000
CMP (GAL STL 24 IN)
LF 20.000 $160.000 $85.000 $113.400 $105.000
CMP (GAL STL 42 IN)
LF 12.000 $175.000 $150.000 $172.800 $160.000
CMP (GAL STL 48 IN)
LF 35.000 $200.000 $375.000 $297.000 $275.000
CMP AR (GAL STL DES 4)
LF 22.000 $240.000 $150.000 $156.600 $145.000
CMP AR (GAL STL DES 5)
LF 18.000 $330.000 $180.000 $266.760 $247.000
CMP (GAL STL 72 IN)
LF 100.000 $350.000 $700.000 $410.400 $380.000
CONC BOX CULV (5 FT X 5 FT)(EXTEND)
LF 64.000 $1,200.000 $725.000 $961.200 $890.000
RC PIPE (CL III)(18 IN)
LF 9.000 $135.000 $100.000 $102.600 $95.000
RC PIPE (CL III)(24 IN)
LF 758.000 $150.000 $120.000 $105.840 $98.000
HEADWALL (CH - FW - 0) (DIA= 48 IN)
EA 4.000 $12,000.000 $10,000.000 $18,899.950 $17,500.000
HEADWALL (CH - PW - 0) (DIA= 72 IN)
EA 8.000 $20,000.000 $15,000.000 $23,219.930 $21,500.000
WINGWALL (PW - 2) (HW=6 FT)
EA 1.000 $25,000.000 $14,000.000 $17,852.350 $16,530.000
SET (TY I)(S= 5 FT)(HW= 5 FT)(3:1) (C)
EA 11.000 $10,000.000 $9,000.000 $7,451.980 $6,900.000
SET (TY II) (15 IN) (CMP) (6: 1) (P)
EA 2.000 $2,750.000 $1,000.000 $1,296.000 $1,200.000
SET (TY II) (18 IN) (CMP) (6: 1) (P)
EA 22.000 $1,800.000 $1,000.000 $1,566.000 $1,450.000
SET (TY II) (18 IN) (RCP) (4: 1) (C)
EA 1.000 $2,100.000 $1,500.000 $1,566.000 $1,450.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 12.000 $1,500.000 $1,500.000 $2,008.790 $1,860.000
SET (TY II) (24 IN) (CMP) (4: 1) (C)
EA 6.000 $2,400.000 $1,400.000 $1,997.990 $1,850.000
SET (TY II) (24 IN) (CMP) (6: 1) (P)
EA 46.000 $1,700.000 $1,600.000 $2,051.990 $1,500.000
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 46.000 $2,300.000 $2,200.000 $2,051.990 $1,900.000
SET (TY II) (42 IN) (CMP) (4: 1) (C)
EA 2.000 $2,400.000 $6,000.000 $5,281.180 $4,900.000
SET (TY II) (DES 4) (CMP) (4: 1) (C)
EA 4.000 $3,000.000 $3,500.000 $2,915.990 $2,700.000
SET (TY II) (DES 5) (CMP) (3: 1) (C)
EA 1.000 $4,500.000 $4,000.000 $3,860.990 $3,600.000
SET (TY II) (DES 5) (CMP) (4: 1) (C)
EA 1.000 $4,000.000 $6,000.000 $4,211.990 $3,900.000
CLEAN EXIST CULVERTS
EA 14.000 $1,000.000 $1,200.000 $1,393.200 $1,300.000
MOBILIZATION
LS 1.000 $646,882.810 $425,000.000 $632,796.100 $642,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 8.000 $10,000.000 $10,000.000 $4,749.600 $16,300.000
ROCK FILTER DAMS (INSTALL) (TY 3)
LF 420.000 $95.000 $75.000 $119.250 $120.000
ROCK FILTER DAMS (REMOVE)
LF 2,440.000 $15.000 $30.000 $15.400 $15.400
TEMP SEDMT CONT FENCE (INSTALL)
LF 13,879.000 $5.300 $4.250 $3.500 $3.500
TEMP SEDMT CONT FENCE (REMOVE)
LF 13,879.000 $2.000 $1.250 $0.500 $0.500
ROCK FILTER DAMS (INSTALL) (TY 2) (6:1)
LF 2,020.000 $60.000 $135.000 $53.500 $54.000
CONCRETE CURB (SPECIAL)
LF 371.000 $100.000 $35.000 $48.600 $45.000
INTERSECTIONS (ACP)
SY 250.000 $62.000 $150.000 $43.800 $146.000
DRIVEWAYS (ACP)
SY 1,108.000 $100.000 $75.000 $43.800 $72.000
DRIVEWAYS (SURF TREAT)
SY 2,033.000 $125.000 $50.000 $36.800 $72.000
TURNOUTS (ACP)
SY 269.000 $100.000 $75.000 $48.400 $200.000
RUMBLE STRIPS (SHOULDER)
LF 53,784.000 $0.500 $0.200 $0.180 $0.200
RUMBLE STRIPS (CENTERLINE)
LF 26,744.000 $2.000 $0.200 $0.230 $0.270
MAILBOX INSTALL-S (TWW-POST) TY 4
EA 22.000 $325.000 $350.000 $280.000 $280.000
IN SM RD SN SUP&AM TYS80(1)SA(P)
EA 90.000 $863.000 $800.000 $700.000 $700.000
IN SM RD SN SUP&AM TYS80(1)SA(T)
EA 1.000 $1,500.000 $1,000.000 $900.000 $900.000
INSTL OM ASSM (OM-2Y)(WC)GND(BI)
EA 25.000 $75.000 $175.000 $65.000 $65.000
WK ZN PAV MRK NON-REMOV (W)6"(SLD)
LF 56,254.000 $0.780 $0.400 $0.450 $0.400
WK ZN PAV MRK NON-REMOV (Y)6"(BRK)
LF 2,063.000 $0.550 $2.000 $0.450 $2.000
WK ZN PAV MRK NON-REMOV (Y)6"(SLD)
LF 100,184.000 $0.700 $0.400 $0.450 $0.400
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 2,348.000 $2.350 $1.600 $1.630 $1.800
RE PM W/RET REQ TY I (W)6"(SLD)(090MIL)
LF 53,730.000 $0.560 $0.750 $0.600 $0.720
RE PM W/RET REQ TY I (Y)6"(BRK)(090MIL)
LF 2,063.000 $0.500 $2.000 $0.600 $2.000
RE PM W/RET REQ TY I (Y)6"(SLD)(090MIL)
LF 43,972.000 $0.560 $0.750 $0.600 $0.720
REFL PAV MRKR TY II-A-A
EA 1,154.000 $5.000 $5.000 $4.500 $5.000
D-GR HMA TY-B PG64-22
TON 20,839.000 $100.000 $92.000 $90.900 $112.000
D-GR HMA TY-B PG64-22 (LEVEL-UP)
TON 96.000 $125.000 $240.000 $170.500 $296.000
D-GR HMA TY-D SAC-B PG70-22
TON 10,810.000 $105.000 $110.000 $103.200 $129.000
TACK COAT
GAL 16,137.000 $5.000 $5.000 $4.090 $3.800
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $17,500.000 $15,000.000 $10,000.000 $15,000.000
TMA (STATIONARY)
DAY 243.000 $169.000 $200.000 $300.000 $275.000
TMA (MOBILE OPERATION)
HR 288.000 $150.000 $25.000 $90.000 $85.000
LEAD LED CHEVRON
EA 2.000 $4,400.000 $100.000 $3,850.000 $3,900.000
LED CHEVRON
EA 15.000 $3,000.000 $4,500.000 $3,200.000 $3,200.000
Totals: $7,558,774.950 $6,545,352.980 $6,900,744.490 $7,971,940.440