PREPARING ROW
|
STA
|
186.000
|
$1,000.000
|
$2,530.000
|
$2,116.600
|
$1,400.000
|
|
|
REMOVING CONC (PAV)
|
SY
|
546.000
|
$25.000
|
$10.000
|
$25.660
|
$55.000
|
|
|
REMOVING CONC (DRIVEWAYS)
|
SY
|
4,572.000
|
$15.000
|
$7.000
|
$23.090
|
$27.000
|
|
|
REMOVING CONC (CURB)
|
LF
|
5,382.000
|
$3.000
|
$3.000
|
$9.620
|
$5.000
|
|
|
REMOVING CONC (SIDEWALK OR RAMP)
|
SY
|
19,152.000
|
$10.000
|
$5.000
|
$23.090
|
$10.000
|
|
|
REMOVE CONC (MISC)
|
EA
|
1.000
|
$1,200.000
|
$500.000
|
$19,241.830
|
$100.000
|
|
|
REMOVE STAB BASE & ASPH PAV (13"-18")
|
SY
|
550.000
|
$3.500
|
$5.000
|
$20.520
|
$10.000
|
|
|
BLOCK SODDING(OPT1)
|
SY
|
6,355.000
|
$10.000
|
$5.440
|
$5.770
|
$6.000
|
|
|
FERTILIZER
|
AC
|
1.000
|
$700.000
|
$13,784.120
|
$1,421.330
|
$3,500.000
|
|
|
VEGETATIVE WATERING
|
MG
|
1,313.000
|
$8.640
|
$35.000
|
$25.660
|
$57.000
|
|
|
IRRIGATION SYSTEM (TY I)
|
LS
|
1.000
|
$952,000.000
|
$772,807.170
|
$891,538.120
|
$1,760,000.000
|
|
|
PLANT MATERIAL (4" CNTR)
|
EA
|
4,268.000
|
$6.000
|
$2.270
|
$2.570
|
$4.000
|
|
|
PLANT MATERIAL (1-GAL)
|
EA
|
10,774.000
|
$11.400
|
$5.240
|
$7.700
|
$11.000
|
|
|
PLANT MATERIAL (3-GAL)
|
EA
|
3,434.000
|
$16.000
|
$20.810
|
$19.240
|
$22.000
|
|
|
PLANT MATERIAL (5-GAL)
|
EA
|
758.000
|
$30.000
|
$21.410
|
$26.940
|
$25.000
|
|
|
MULCH
|
CY
|
720.000
|
$40.000
|
$56.220
|
$80.820
|
$95.000
|
|
|
PLANT SOIL MIX
|
CY
|
4,994.000
|
$45.000
|
$68.410
|
$51.310
|
$70.000
|
|
|
LANDSCAPE EDGE
|
LF
|
319.000
|
$15.000
|
$3.730
|
$8.980
|
$5.000
|
|
|
PLANT BED PREPARATION
|
SY
|
6,400.000
|
$5.000
|
$1.060
|
$17.960
|
$19.000
|
|
|
VEGETATION BARRIER
|
SY
|
102.000
|
$15.000
|
$2.020
|
$71.840
|
$34.000
|
|
|
PLANT MATERIAL (100 GAL) (TREE)
|
EA
|
155.000
|
$2,260.000
|
$975.320
|
$1,103.200
|
$1,500.000
|
|
|
PLANT MATERIAL (5 GAL) (SHRUB)
|
EA
|
20.000
|
$40.000
|
$21.410
|
$32.070
|
$25.000
|
|
|
PLANT MATERIAL (7-GAL)
|
EA
|
828.000
|
$60.000
|
$62.370
|
$47.460
|
$50.000
|
|
|
PLANT SOIL MIX (PLANTING SOIL)
|
CY
|
5,160.000
|
$40.000
|
$63.380
|
$51.310
|
$70.000
|
|
|
PLANT SOIL MIX (TURF SOIL)
|
CY
|
715.000
|
$1.000
|
$63.380
|
$60.290
|
$70.000
|
|
|
PLANT MATERIAL (200 GAL) (TREE)
|
EA
|
136.000
|
$2,800.000
|
$2,136.220
|
$2,389.840
|
$3,400.000
|
|
|
HMCL ACP TY-D AC-1.5
|
TON
|
30.800
|
$160.000
|
$140.000
|
$186.000
|
$1,200.000
|
|
|
D-GR HMA(SQ) TY-D SAC-A PG70-22
|
TON
|
32.000
|
$120.000
|
$140.000
|
$237.320
|
$1,200.000
|
|
|
PLANE ASPH CONC PAV (2")
|
SY
|
397.600
|
$0.500
|
$10.000
|
$20.520
|
$150.000
|
|
|
CONC PVMT (CONT REINF)(FAST TRK)(10")
|
SY
|
555.000
|
$95.000
|
$150.000
|
$141.110
|
$450.000
|
|
|
DRILL SHAFT (TRF SIG POLE) (36 IN)
|
LF
|
226.400
|
$340.000
|
$275.000
|
$352.770
|
$300.000
|
|
|
DRILL SHAFT (TRF SIG POLE) (48 IN)
|
LF
|
498.900
|
$400.000
|
$365.000
|
$468.220
|
$400.000
|
|
|
CL C CONC (FOOTING)
|
CY
|
24.400
|
$675.000
|
$500.000
|
$288.630
|
$1,500.000
|
|
|
ADJUSTING MANHOLES & INLETS
|
EA
|
19.000
|
$1,300.000
|
$400.000
|
$769.670
|
$1,500.000
|
|
|
ADJUSTING MANHOLES (WATER METER)
|
EA
|
32.000
|
$275.000
|
$250.000
|
$455.390
|
$400.000
|
|
|
ADJUSTING MANHOLES (ELECTRIC BOX)
|
EA
|
93.000
|
$250.000
|
$350.000
|
$833.810
|
$450.000
|
|
|
ADJUSTING MANHOLES (IRRIGATION BOX)
|
EA
|
7.000
|
$250.000
|
$350.000
|
$513.120
|
$400.000
|
|
|
ADJUSTING MANHOLES (TELEPHONE BOX)
|
EA
|
30.000
|
$675.000
|
$400.000
|
$962.090
|
$500.000
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$1,173,030.060
|
$1,060,000.000
|
$125,000.000
|
$1,500,000.000
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
18.000
|
$7,000.000
|
$10,000.000
|
$19,883.220
|
$36,500.000
|
|
|
SANDBAGS FOR EROSION CONTROL
|
EA
|
104.000
|
$6.000
|
$12.000
|
$115.450
|
$50.000
|
|
|
TEMP SEDMT CONT FENCE (INSTALL)
|
LF
|
17,180.000
|
$4.000
|
$2.250
|
$1.990
|
$3.000
|
|
|
TEMP SEDMT CONT FENCE (REMOVE)
|
LF
|
17,180.000
|
$1.000
|
$1.000
|
$1.350
|
$0.500
|
|
|
BIODEG EROSN CONT LOGS (INSTL) (8")
|
LF
|
624.000
|
$4.000
|
$5.000
|
$8.340
|
$8.000
|
|
|
BIODEG EROSN CONT LOGS (REMOVE)
|
LF
|
624.000
|
$2.000
|
$2.000
|
$3.850
|
$0.500
|
|
|
CONC CURB (TY II)
|
LF
|
6,020.000
|
$6.000
|
$3.000
|
$8.340
|
$30.000
|
|
|
CONCRETE CURB (SPECIAL)
|
LF
|
1,905.000
|
$20.000
|
$3.000
|
$16.030
|
$35.000
|
|
|
DRIVEWAYS (CONC)
|
SY
|
1,689.000
|
$75.000
|
$100.000
|
$63.500
|
$108.000
|
|
|
DRIVEWAYS (CONC) (HES)
|
SY
|
2,956.000
|
$95.000
|
$110.000
|
$80.240
|
$126.000
|
|
|
CURB RAMPS (TY 1)
|
EA
|
42.000
|
$1,400.000
|
$1,500.000
|
$1,603.500
|
$1,500.000
|
|
|
CURB RAMPS (TY 2)
|
EA
|
79.000
|
$1,600.000
|
$1,500.000
|
$1,731.750
|
$1,500.000
|
|
|
CURB RAMPS (TY 5)
|
EA
|
1.000
|
$2,000.000
|
$2,500.000
|
$2,116.600
|
$3,000.000
|
|
|
CONC SIDEWALKS (5") (TYPE 1)
|
SY
|
14,439.000
|
$65.000
|
$110.000
|
$66.960
|
$99.000
|
|
|
CONC SIDEWALKS (5") (TYPE 2)
|
SY
|
188.000
|
$85.000
|
$130.000
|
$69.270
|
$135.000
|
|
|
CONC SIDEWALKS (6") (TYPE 1)
|
SY
|
34.000
|
$75.000
|
$140.000
|
$67.990
|
$200.000
|
|
|
CONDT (PVC) (SCH 40) (1")
|
LF
|
5,000.000
|
$27.000
|
$4.160
|
$5.340
|
$5.000
|
|
|
CONDT (PVC) (SCH 40) (1 1/4")
|
LF
|
3,205.000
|
$8.000
|
$4.310
|
$5.530
|
$5.000
|
|
|
CONDT (PVC) (SCH 80) (2")
|
LF
|
59,477.000
|
$8.000
|
$5.780
|
$7.410
|
$7.000
|
|
|
CONDT (PVC) (SCH 80) (2") (BORE)
|
LF
|
340.000
|
$15.000
|
$11.730
|
$15.050
|
$13.000
|
|
|
CONDT (PVC) (SCH 80) (3")
|
LF
|
530.000
|
$15.000
|
$5.780
|
$7.410
|
$7.000
|
|
|
CONDT (PVC) (SCH 80) (3") (BORE)
|
LF
|
945.000
|
$25.000
|
$12.550
|
$16.100
|
$13.000
|
|
|
CONDT (PVC) (SCH 80) (4")
|
LF
|
650.000
|
$23.000
|
$6.720
|
$8.620
|
$8.000
|
|
|
CONDT (PVC) (SCH 80) (4") (BORE)
|
LF
|
3,135.000
|
$37.000
|
$13.490
|
$17.300
|
$15.000
|
|
|
ELEC CONDR (NO.10) INSULATED
|
LF
|
15,000.000
|
$2.800
|
$0.650
|
$0.830
|
$0.700
|
|
|
ELEC CONDR (NO.8) INSULATED
|
LF
|
60,696.000
|
$1.250
|
$0.790
|
$1.010
|
$0.800
|
|
|
ELEC CONDR (NO.6) BARE
|
LF
|
6,935.000
|
$1.500
|
$0.930
|
$1.190
|
$1.000
|
|
|
ELEC CONDR (NO.6) INSULATED
|
LF
|
53,883.000
|
$1.500
|
$1.010
|
$1.300
|
$1.100
|
|
|
ELEC CONDR (NO.4) INSULATED
|
LF
|
1,280.000
|
$2.000
|
$1.300
|
$1.670
|
$1.500
|
|
|
TRAY CABLE (4 CONDR) (12 AWG)
|
LF
|
6,995.000
|
$2.250
|
$1.400
|
$1.800
|
$1.600
|
|
|
GROUND BOX TY A (122311)W/APRON
|
EA
|
102.000
|
$975.000
|
$751.160
|
$963.580
|
$800.000
|
|
|
GROUND BOX TY D (162922)W/APRON
|
EA
|
49.000
|
$925.000
|
$1,127.350
|
$1,446.150
|
$1,200.000
|
|
|
RELOCATE ELECTRICAL SERVICES
|
EA
|
24.000
|
$2,500.000
|
$2,210.900
|
$2,836.120
|
$2,400.000
|
|
|
ELC SRV TY D 120/240 060(NS)SS(E)PS(U)
|
EA
|
10.000
|
$7,000.000
|
$4,284.290
|
$5,495.840
|
$5,000.000
|
|
|
RELOCATE SM RD SN SUP&AM TY S80
|
EA
|
67.000
|
$300.000
|
$550.000
|
$641.390
|
$600.000
|
|
|
INSTALL HWY TRF SIG (ISOLATED)
|
EA
|
10.000
|
$32,000.000
|
$48,973.930
|
$62,823.200
|
$55,000.000
|
|
|
REMOVING TRAFFIC SIGNALS
|
EA
|
10.000
|
$4,000.000
|
$2,117.000
|
$2,715.660
|
$2,500.000
|
|
|
VEH SIG SEC (12")LED(GRN)
|
EA
|
120.000
|
$225.000
|
$154.580
|
$198.290
|
$170.000
|
|
|
VEH SIG SEC (12")LED(GRN ARW)
|
EA
|
46.000
|
$200.000
|
$154.580
|
$198.290
|
$170.000
|
|
|
VEH SIG SEC (12")LED(YEL)
|
EA
|
120.000
|
$210.000
|
$154.580
|
$198.290
|
$170.000
|
|
|
VEH SIG SEC (12")LED(YEL ARW)
|
EA
|
45.000
|
$200.000
|
$154.580
|
$198.290
|
$170.000
|
|
|
VEH SIG SEC (12")LED(RED)
|
EA
|
120.000
|
$210.000
|
$154.580
|
$198.290
|
$170.000
|
|
|
VEH SIG SEC (12")LED(RED ARW)
|
EA
|
44.000
|
$195.000
|
$154.580
|
$198.290
|
$170.000
|
|
|
VEH SIG SEC (12")LED(GRN U-TURN ARW)
|
EA
|
2.000
|
$350.000
|
$195.180
|
$250.370
|
$220.000
|
|
|
VEH SIG SEC (12")LED(YEL U-TURN ARW)
|
EA
|
2.000
|
$350.000
|
$195.180
|
$250.370
|
$220.000
|
|
|
VEH SIG SEC (12")LED(RED U-TURN ARW)
|
EA
|
2.000
|
$350.000
|
$195.180
|
$250.370
|
$220.000
|
|
|
PED SIG SEC (LED)(COUNTDOWN)
|
EA
|
82.000
|
$450.000
|
$347.420
|
$445.670
|
$400.000
|
|
|
BACK PLATE (12")(3 SEC)
|
EA
|
162.000
|
$100.000
|
$78.820
|
$101.110
|
$100.000
|
|
|
BACK PLATE (12")(4 SEC)
|
EA
|
1.000
|
$110.000
|
$102.020
|
$130.870
|
$110.000
|
|
|
BACK PLATE (12")(5 SEC)ALUM
|
EA
|
1.000
|
$120.000
|
$118.260
|
$151.700
|
$120.000
|
|
|
TRF SIG CBL (TY A)(14 AWG)(3 CONDR)
|
LF
|
12,930.000
|
$1.250
|
$0.770
|
$0.990
|
$0.800
|
|
|
TRF SIG CBL (TY A)(14 AWG)(5 CONDR)
|
LF
|
12,770.000
|
$1.410
|
$0.920
|
$1.180
|
$1.000
|
|
|
TRF SIG CBL (TY A)(14 AWG)(7 CONDR)
|
LF
|
19,475.000
|
$1.650
|
$1.310
|
$1.680
|
$1.400
|
|
|
TRF SIG CBL (TY C)(14 AWG)(2 CONDR)
|
LF
|
103,576.000
|
$1.200
|
$1.070
|
$1.370
|
$1.100
|
|
|
INS TRF SIG PL AM (S)1 ARM(20')LUM
|
EA
|
1.000
|
$5,900.000
|
$7,145.600
|
$9,166.000
|
$7,500.000
|
|
|
INS TRF SIG PL AM(S)1 ARM(28')LUM
|
EA
|
4.000
|
$7,500.000
|
$7,578.280
|
$9,721.300
|
$8,000.000
|
|
|
INS TRF SIG PL AM(S)1 ARM(32')LUM
|
EA
|
5.000
|
$7,650.000
|
$8,429.720
|
$10,813.500
|
$9,000.000
|
|
|
INS TRF SIG PL AM(S)1 ARM(36')LUM
|
EA
|
4.000
|
$7,900.000
|
$8,769.600
|
$11,249.500
|
$9,500.000
|
|
|
INS TRF SIG PL AM(S)1 ARM(40')LUM
|
EA
|
2.000
|
$9,000.000
|
$9,155.880
|
$11,745.000
|
$10,000.000
|
|
|
INS TRF SIG PL AM(S)1 ARM(50')LUM
|
EA
|
1.000
|
$8,800.000
|
$22,925.080
|
$29,408.000
|
$25,000.000
|
|
|
INS TRF SIG PL AM(S)1 ARM(55')LUM
|
EA
|
1.000
|
$21,000.000
|
$23,387.920
|
$30,002.000
|
$25,000.000
|
|
|
INS TRF SIG PL AM(S)1 ARM(60')LUM
|
EA
|
14.000
|
$22,200.000
|
$23,639.640
|
$30,324.660
|
$25,000.000
|
|
|
INS TRF SIG PL AM(S)1 ARM(65')LUM
|
EA
|
7.000
|
$21,500.000
|
$23,766.080
|
$30,486.860
|
$25,000.000
|
|
|
PED POLE ASSEMBLY
|
EA
|
16.000
|
$1,800.000
|
$1,598.950
|
$2,051.100
|
$1,700.000
|
|
|
PEDESTRIAN PUSH BUTTON POLE
|
EA
|
37.000
|
$2,240.000
|
$1,494.550
|
$1,917.200
|
$1,600.000
|
|
|
PED DETECT PUSH BUTTON (APS)
|
EA
|
83.000
|
$775.000
|
$737.200
|
$945.670
|
$800.000
|
|
|
VEH LP DETECT (SAWCUT)
|
LF
|
24,599.000
|
$13.000
|
$8.950
|
$11.480
|
$10.000
|
|
|
INSTALL OF ELECTRICAL SERVICE
|
EA
|
4.000
|
$500.000
|
$5,244.300
|
$6,727.330
|
$5,500.000
|
|
|
REMOVAL OF PEDESTRIAN PUSH BUTTONS
|
EA
|
1.000
|
$100.000
|
$21.180
|
$27.170
|
$25.000
|
|
|
REMOVE PED POLE ASSM
|
EA
|
4.000
|
$350.000
|
$338.720
|
$434.500
|
$400.000
|
|
|
LANDSCAPE AMENITY (TY 4)
|
EA
|
26.000
|
$1,741.670
|
$2,000.000
|
$2,976.000
|
$100.000
|
|
|
LANDSCAPE AMENITY (TY 5)
|
EA
|
309.000
|
$4,000.000
|
$3,324.540
|
$4,264.680
|
$3,500.000
|
|
|
LANDSCAPE AMENITY (TY 10)
|
EA
|
72.000
|
$25.000
|
$2,500.000
|
$6,157.390
|
$2,600.000
|
|
|
LANDSCAPE AMENITY (TY 11)
|
EA
|
5.000
|
$15.000
|
$3,600.000
|
$4,938.750
|
$2,500.000
|
|
|
LANDSCAPE AMENITY (TY 12)
|
EA
|
26.000
|
$500.000
|
$1,275.000
|
$1,539.350
|
$1,000.000
|
|
|
LANDSCAPE AMENITY (TY 13)
|
EA
|
21.000
|
$3,141.640
|
$3,000.000
|
$13,469.000
|
$5,000.000
|
|
|
LANDSCAPE AMENITY (TY 14)
|
EA
|
7.000
|
$394.640
|
$12,102.550
|
$26,938.500
|
$5,000.000
|
|
|
LANDSCAPE AMENITY (TY 15)
|
EA
|
2.000
|
$80,000.000
|
$87,000.000
|
$103,905.000
|
$50,000.000
|
|
|
LANDSCAPE AMENITY (TY 18)
|
EA
|
24.000
|
$5,000.000
|
$5,830.000
|
$6,221.500
|
$15,000.000
|
|
|
LANDSCAPE AMENITY (TY 19)
|
EA
|
26.000
|
$375.000
|
$6,000.000
|
$10,518.000
|
$100.000
|
|
|
LANDSCAPE AMENITY (TY 20)
|
EA
|
2.000
|
$5,000.000
|
$3,000.000
|
$1,988.000
|
$2,500.000
|
|
|
LANDSCAPE AMENITY (TRASH/RECYCLE BIN)
|
EA
|
26.000
|
$900.000
|
$2,000.000
|
$2,976.000
|
$100.000
|
|
|
TREE PROTECTION
|
EA
|
195.000
|
$303.400
|
$400.000
|
$198.830
|
$330.000
|
|
|
LOOSE AGGR FOR GROUNDCOVER (TYPE I)
|
CY
|
5.000
|
$16.500
|
$1,355.170
|
$115.450
|
$1,500.000
|
|
|
DECORATIVE LANDSCAPE PAVING (TYPE 1)
|
SY
|
897.000
|
$225.000
|
$250.000
|
$207.810
|
$180.000
|
|
|
DECORATIVE LANDSCAPE PAVING (TYPE 2)
|
SY
|
1,631.000
|
$225.000
|
$220.000
|
$207.810
|
$180.000
|
|
|
DECORATIVE LANDSCAPE PAVING (TYPE 3)
|
SY
|
359.400
|
$180.000
|
$350.000
|
$230.900
|
$450.000
|
|
|
DECORATIVE LANDSCAPE PAVING (TYPE 4)
|
SY
|
291.900
|
$180.000
|
$350.000
|
$230.900
|
$450.000
|
|
|
ADJUST FIRE HYDRANT
|
EA
|
17.000
|
$850.000
|
$750.000
|
$3,444.000
|
$1,500.000
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
EA
|
4.000
|
$9,900.000
|
$15,000.000
|
$10,903.700
|
$20,000.000
|
|
MULTIPOLYMER PAV MRK (W)(12")(SLD)
|
LF
|
6,551.000
|
$6.000
|
$3.500
|
$9.940
|
$8.000
|
|
MULTIPOLYMER PAV MRK (W)(24")(SLD)
|
LF
|
1,570.000
|
$9.000
|
$8.000
|
$17.960
|
$14.000
|
|
|
TMA (STATIONARY)
|
EA
|
3.000
|
$4,125.000
|
$18,000.000
|
$4,490.000
|
$50,000.000
|
|
|
TMA (MOBILE OPERATION)
|
HR
|
500.000
|
$24.000
|
$30.000
|
$211.660
|
$80.000
|
|
|
NATURAL GAS PIPELINE
|
EA
|
10.000
|
$500.000
|
$750.000
|
$8,787.000
|
$500.000
|
|
Totals: |
$12,182,874.520
|
$12,691,072.790
|
$13,845,428.110
|
$15,988,219.700
|