| Control Number | County | Highway | Bid Date | Low Bidder | Pay Estimates | % of Contract | Amount | % Complete | Contract Amount |
|---|---|---|---|---|---|---|---|---|---|
| 3256-01-118 | HARRIS | SL 8 | 04/05/2023 | MAIN LANE INDUSTRIES LTD. | 04/26 | 03/26 | 02/26 | 01/26 | 12/25 | 0.05% | $25,657.77 | 100.00% | $51,315,542.12 |
| 0598-02-111 | BRAZORIA | SH 288 | 08/04/2022 | JAMES CONSTRUCTION GROUP, LLC | 04/26 | 03/26 | 02/26 | 01/26 | 12/25 | 1.27% | $666,962.05 | 106.00% | $52,516,696.65 |
| 0028-03-107 | LIBERTY | US 90 | 08/05/2021 | JAMES CONSTRUCTION GROUP, LLC | 04/26 | 03/26 | 02/26 | 01/26 | 12/25 | 0.21% | $96,337.50 | 100.00% | $45,874,999.14 |
| 2093-01-010 | FORT BEND | FM 2218 | 06/04/2020 | JAMES CONSTRUCTION GROUP, L.L.C. | 04/26 | 03/26 | 02/26 | 01/26 | 12/25 | 0.12% | $57,708.22 | 102.00% | $48,090,185.42 |
| 1258-04-065 | HARRIS | FM 1093 | 09/06/2019 | HARPER BROTHERS CONSTRUCTION LLC | 08/25 | 07/25 | 06/25 | 05/25 | 04/25 | 0.63% | $75,870.54 | 99.00% | $12,042,943.12 |
| 3510-05-043 | HARRIS | SH 99 | 08/07/2019 | HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC. | 09/25 | 08/25 | 07/25 | 06/25 | 05/25 | 0.14% | $15,694.68 | 102.00% | $11,210,484.61 |
| 0177-03-096 | LIBERTY | US 59 | 09/07/2018 | JAMES CONSTRUCTION GROUP, L.L.C. | 02/25 | 01/25 | 12/24 | 11/24 | 10/24 | 0.20% | $212,247.92 | 102.00% | $106,123,961.38 |
| 0912-71-003 | HARRIS | CS | 04/04/2017 | J.D. ABRAMS, L.P. | 08/25 | 07/25 | 06/25 | 05/25 | 04/25 | 0.00% | $0.00 | 99.00% | $14,729,937.61 |