TxDOT Subcontracts for MCL CONTRACTING, LLC
| Control Number | County | Highway | Bid Date | Low Bidder | Pay Estimates | % of Contract | Amount | % Complete | Contract Amount |
|---|---|---|---|---|---|---|---|---|---|
| 0516-02-029 | GOLIAD | SH 239 | 02/04/2021 | HUNTER INDUSTRIES, LTD. | 01/25 | 11/24 | 10/24 | 09/24 | 08/24 | 0.00% | $0.00 | 100.00% | $7,455,639.89 |
| 0216-01-057 | COMAL | SL 337 | 07/09/2020 | HUNTER INDUSTRIES, LTD. | 12/24 | 11/24 | 10/24 | 09/24 | 08/24 | 0.70% | $99,992.48 | 100.00% | $14,284,639.49 |
| 0353-03-100 | TARRANT | SH 114 | 07/08/2020 | ZACHRY CONSTRUCTION CORPORATION | 04/26 | 03/26 | 02/26 | 01/26 | 12/25 | 4.85% | $1,734,925.32 | 100.00% | $35,771,656.09 |
| 0231-04-060 | BELL | IH 14 | 06/04/2020 | JAMES CONSTRUCTION GROUP, L.L.C. | 11/24 | 10/24 | 09/24 | 08/24 | 07/24 | 0.08% | $31,572.90 | 100.00% | $39,466,124.00 |
| 0171-04-050 | TARRANT | SH 199 | 06/04/2020 | SEMA CONSTRUCTION, INC. | 05/26 | 04/26 | 03/26 | 02/26 | 01/26 | 0.20% | $246,250.97 | 94.00% | $123,125,487.11 |
| 0176-01-081 | NACOGDOCHES | US 59 | 07/09/2019 | LONGVIEW BRIDGE AND ROAD, LTD. | 05/26 | 04/26 | 03/26 | 02/26 | 01/26 | 4.61% | $4,036,279.97 | 94.00% | $87,554,880.10 |
| 0027-01-044 | COLORADO | US 90 | 05/07/2019 | HARPER BROTHERS CONSTRUCTION LLC | 05/26 | 04/26 | 03/26 | 02/26 | 01/26 | 0.57% | $67,802.15 | 97.00% | $11,895,114.28 |
| 0080-11-001 | HOOD | US 377 | 08/07/2018 | ZACHRY CONSTRUCTION CORPORATION | 04/26 | 03/26 | 02/26 | 01/26 | 12/25 | 0.03% | $26,980.50 | 102.00% | $89,934,997.26 |
| 0718-02-045 | TARRANT | FM 156 | 08/07/2018 | WEBBER, LLC | 04/26 | 03/26 | 02/26 | 01/26 | 12/25 | 0.02% | $12,871.70 | 98.00% | $64,358,489.53 |
| 0253-04-138 | BEXAR | US 281 | 07/10/2018 | ZACHRY CONSTRUCTION CORPORATION | 07/25 | 06/25 | 05/25 | 04/25 | 03/25 | 0.12% | $230,740.89 | 100.00% | $192,284,071.77 |