| Control Number | County | Highway | Bid Date | Low Bidder | Pay Estimates | % of Contract | Amount | % Complete | Contract Amount |
|---|---|---|---|---|---|---|---|---|---|
| 2033-02-012 | NOLAN | FM 1170 | 05/04/2023 | J. H. STRAIN & SONS, INC. | 02/26 | 01/26 | 12/25 | 11/25 | 10/25 | 2.01% | $250,448.44 | 97.00% | $12,460,121.62 |
| 0453-04-024 | CROSBY | SH 207 | 09/07/2022 | DUININCK, INC. | 04/26 | 03/26 | 02/26 | 01/26 | 12/25 | 0.36% | $87,059.25 | 69.00% | $24,183,125.31 |
| 0032-07-029 | STONEWALL | US 83 | 01/07/2022 | DELHUR INDUSTRIES, INC. | 01/25 | 12/24 | 11/24 | 10/24 | 09/24 | 0.88% | $169,836.15 | 91.00% | $19,299,562.06 |
| 1337-02-012 | LIPSCOMB | SH 23 | 10/07/2021 | J. LEE MILLIGAN, INC. | 12/24 | 11/24 | 10/24 | 09/24 | 08/24 | 3.03% | $224,651.59 | 100.00% | $7,414,243.89 |