CROSBY SH 207 (0453-04-024)

Items: 136

County: CROSBY
Length: N/A
Highway: SH 207
District: LUBBOCK
Control Number: 0453-04-024
DBE Goal: N/A
Project: F 2023(065)
Guaranty: N/A
Time: 492 WORKING DAYS
Engineer's Estimate: $18,805,429.35
Date: 09/07/2022 (3 years ago)
Contract Number: N/A
Type: REHABILIATION
Mail/Deliver Bids To: N/A
HEATH BOZEMAN
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (4)
E
Engineer's Estimate
$18,805,429.35
$23,557,970.65
Over/Under Est: 25.27% $4,752,541.30
$25,176,322.58
Over/Under Est: 33.88% $6,370,893.23
Amt Left: 6.87% $1,618,351.93
$27,359,902.95
Over/Under Est: 45.49% $8,554,473.60
Amt Left: 16.14% $3,801,932.30
Delta: -8.67% -$2,183,580.37
$27,982,885.06
Over/Under Est: 48.8% $9,177,455.71
Amt Left: 18.78% $4,424,914.41
Delta: -2.28% -$622,982.11
Subcontractor Percentage Amount
W. S. CONSTRUCTION COMPANY 11.26% $2,723,019.91
HJC FARMS, INC. 2.77% $669,872.57
BARRICADES UNLIMITED 2.22% $536,865.38
TRP CONSTRUCTION GROUP, LLC 1.82% $440,132.88
TEXOP CONSTRUCTION 0.95% $229,739.69
V-TECH ENVIROMENTAL SERVICES 0.59% $142,680.44
LIPHAM ASPHALT AND PAVING COMPANY, LLC 0.36% $87,059.25
MARCOM'S MOWING SERVICE, LLC 0.25% $60,457.81
LMN TRANSPORT 0.21% $50,784.56
LMSE TRUCKING, LLC 0.16% $38,693.00
H & F TRUCKING 0.16% $38,693.00
WITHERS CONSTRUCTION, LLC 0.14% $33,856.38
SURFACE PREPARATION TECHNOLOGIES, LLC 0.09% $21,764.81
Total: 20.98% $5,073,619.68

Bid Items & Bid Tabulations

136 Total 0 of 136
CROSBY  |  SH 207  |  LUBBOCK  |  0453-04-024  |  09/07/2022  |  $18,805,429.35  |  F 2023(065)  |  REHABILIATION  |  492 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
DUININCK, INC.
GILVIN-TERRILL, LTD.
J. LEE MILLIGAN, INC.
RK HALL, LLC
PREPARING ROW
STA 1.000 $5,000.000 $7,100.000 $30,000.000 $4,200.000 $56,626.840
PREP ROW (TREE)(GREATER THAN 24" DIA)
EA 10.000 $1,500.000 $2,200.000 $1,500.000 $2,520.000 $3,908.530
PREPARING ROW (TREE) (6" TO 24" DIA)
EA 20.000 $750.000 $1,100.000 $1,000.000 $1,550.000 $995.630
REMOVING CONC (RIPRAP)
SY 495.000 $25.000 $14.500 $25.000 $35.000 $136.710
REMOVING CONC (DRIVEWAYS)
SY 226.000 $20.000 $14.500 $25.000 $59.000 $62.040
EXCAVATION (ROADWAY)
CY 600.000 $30.000 $33.500 $25.000 $33.250 $9.390
SUBGRADE WIDENING (DENS CONT)
STA 615.000 $1,000.000 $438.500 $1,500.000 $595.000 $703.040
BACKFILL (TY B)
STA 615.000 $150.000 $125.000 $180.250 $145.000 $94.610
BLADING
STA 615.000 $150.000 $100.000 $35.000 $110.000 $354.890
PROOF ROLLING
HR 50.000 $150.000 $165.000 $250.000 $310.000 $154.980
FL BS (CMP IN PLC) (TY A GR 4) (3.5")
SY 121,425.000 $7.000 $9.700 $8.000 $9.750 $8.820
FL BS (CMP IN PLC) (TY A GR 4) (3.75")
SY 131,136.000 $7.000 $10.500 $9.000 $10.400 $9.520
REWORK BS MTL (TY B) (6") (DENS CONT)
SY 12,379.000 $5.000 $4.200 $6.000 $5.150 $4.860
REWORK BS MTL (TY C) (6") (DENS CONT)
SY 212,949.000 $3.500 $2.550 $3.500 $1.050 $4.180
LIME (HYDRATED LIME (DRY))
TON 257.000 $250.000 $350.000 $300.000 $305.000 $240.910
LIME TRT (SUBGRADE)(8")
SY 13,692.000 $5.000 $4.900 $6.000 $6.750 $5.210
EMULS ASPH (EROSN CONT)(CSS-1H)
GAL 60,360.000 $6.000 $4.350 $5.000 $5.400 $5.260
FOG SEAL (CSS-1H)
GAL 73,665.000 $6.000 $4.050 $5.000 $5.250 $4.660
ASPH (AC-20-5TR)
GAL 88,638.000 $5.000 $5.950 $5.000 $5.750 $6.080
AGGR(TY-B GR-5 SAC-B)
CY 3,486.000 $125.000 $140.000 $130.000 $105.000 $220.340
FLEXIBLE PAVEMENT STRUCTURE REPAIR(6")
SY 3,919.000 $40.000 $81.500 $70.000 $105.000 $110.240
FLEXIBLE PAVEMENT STRUCTURE REPAIR(3")
SY 3,919.000 $20.000 $48.500 $65.000 $70.000 $103.730
PLANE ASPH CONC PAV(0" TO 3")
SY 668.000 $10.000 $11.000 $3.000 $15.000 $24.100
PLAN ASHP CONC PAV (2" TO 3")
SY 183,321.000 $3.750 $2.100 $3.000 $2.750 $3.580
CEM STABIL BKFL
CY 369.000 $200.000 $270.000 $250.000 $280.000 $275.000
CUT & RESTORE ASPH PAVING
SY 589.000 $100.000 $70.500 $65.000 $90.000 $234.870
TRENCH EXCAVATION PROTECTION
LF 462.000 $100.000 $22.000 $20.000 $22.250 $22.000
TEMPORARY SPL SHORING
SF 1,980.000 $30.000 $81.500 $40.000 $14.500 $48.080
CONC STR REPAIR (STANDARD)
SF 10.000 $250.000 $325.000 $300.000 $335.000 $330.000
RIPRAP (CONC)(4 IN)
CY 365.000 $600.000 $815.000 $800.000 $835.000 $825.000
RIPRAP (CONC)(5 IN)
CY 228.000 $600.000 $815.000 $800.000 $835.000 $825.000
RIPRAP (STONE TY F)(GROUT)(8 IN)
CY 65.000 $800.000 $870.000 $800.000 $200.000 $775.620
RIPRAP (MOW STRIP)(4 IN)
CY 180.000 $600.000 $855.000 $800.000 $875.000 $863.500
RAIL (TY T223)
LF 124.000 $200.000 $325.000 $300.000 $335.000 $330.000
GABIONS (GALV)
CY 29.000 $300.000 $545.000 $1,000.000 $490.000 $670.090
CONC BOX CULV (3 FT X 2 FT)
LF 50.000 $200.000 $415.000 $400.000 $425.000 $418.000
CONC BOX CULV (3 FT X 3 FT)
LF 286.000 $220.000 $435.000 $450.000 $445.000 $440.000
CONC BOX CULV (4 FT X 2 FT)
LF 92.000 $240.000 $490.000 $500.000 $500.000 $495.000
CONC BOX CULV (4 FT X 3 FT)
LF 196.000 $260.000 $560.000 $550.000 $570.000 $566.500
CONC BOX CULV (4 FT X 4 FT)
LF 48.000 $280.000 $630.000 $600.000 $645.000 $638.000
CONC BOX CULV (5 FT X 2 FT)
LF 44.000 $270.000 $665.000 $650.000 $680.000 $671.000
CONC BOX CULV (5 FT X 3 FT)
LF 40.000 $290.000 $700.000 $700.000 $715.000 $709.500
CONC BOX CULV (6 FT X 6 FT)
LF 96.000 $500.000 $1,200.000 $1,200.000 $1,200.000 $1,182.500
CONC BOX CULV (3 FT X 2 FT)(EXTEND)
LF 43.000 $500.000 $700.000 $650.000 $720.000 $709.500
CONC BOX CULV (3 FT X 3 FT)(EXTEND)
LF 27.000 $550.000 $805.000 $750.000 $820.000 $814.000
CONC BOX CULV (5 FT X 3 FT)(EXTEND)
LF 8.000 $600.000 $1,000.000 $1,000.000 $1,055.000 $1,045.000
CONC BOX CULV (10 FT X 10 FT)(EXTEND)
LF 52.000 $1,200.000 $1,900.000 $2,000.000 $1,955.000 $1,936.000
RC PIPE (CL III)(48 IN)
LF 64.000 $300.000 $545.000 $500.000 $555.000 $550.000
RC PIPE (CL IV)(24 IN)
LF 88.000 $250.000 $180.000 $200.000 $185.000 $181.500
WINGWALL (FW - 0) (HW=5 FT)
EA 1.000 $12,000.000 $14,000.000 $15,000.000 $14,155.000 $14,025.000
WINGWALL (FW - 0) (HW=7 FT)
EA 1.000 $16,000.000 $16,500.000 $15,000.000 $16,650.000 $16,500.000
WINGWALL (FW - 0) (HW=8 FT)
EA 2.000 $18,000.000 $24,500.000 $25,000.000 $25,000.000 $24,750.000
WINGWALL (FW - 0) (HW=9 FT)
EA 3.000 $20,000.000 $19,000.000 $20,000.000 $19,500.000 $19,250.000
WINGWALL (FW - S) (HW=11 FT)
EA 2.000 $40,000.000 $160,000.000 $150,000.000 $161,000.000 $159,500.000
WINGWALL (PW - 1) (HW=5 FT)
EA 1.000 $25,000.000 $30,000.000 $30,000.000 $30,525.000 $30,250.000
SET (REPLACE PIPE RUNNER ASSEMBLY)
EA 2.000 $2,000.000 $43,500.000 $40,000.000 $44,400.000 $44,000.000
SET (TY I)(S=3 FT)(HW=3FT)(4:1)(C)
EA 2.000 $8,000.000 $8,200.000 $7,500.000 $8,325.000 $8,250.000
SET (TY I)(S=3 FT)(HW= 3 FT)(6:1)(C)
EA 8.000 $9,000.000 $16,000.000 $14,500.000 $16,100.000 $15,950.000
SET (TY I)(S=3 FT)(HW= 4 FT)(4:1)(C)
EA 4.000 $9,000.000 $16,000.000 $14,500.000 $16,100.000 $15,950.000
SET (TY I)(S=3 FT)(HW= 4 FT)(6:1)(C)
EA 14.000 $9,200.000 $17,500.000 $16,500.000 $18,000.000 $17,875.000
SET (TY I)(S= 4 FT)(HW= 3 FT)(6:1) (C)
EA 4.000 $10,000.000 $11,000.000 $10,000.000 $11,100.000 $11,000.000
SET (TY I)(S= 4 FT)(HW= 4 FT)(6:1) (C)
EA 4.000 $12,000.000 $13,500.000 $12,500.000 $14,000.000 $13,750.000
SET (TY I)(S= 5 FT)(HW= 3 FT)(6:1) (C)
EA 2.000 $16,000.000 $18,000.000 $20,000.000 $18,600.000 $18,425.000
SET (TY I)(S= 5 FT)(HW= 4 FT)(6:1) (C)
EA 4.000 $17,000.000 $27,000.000 $25,000.000 $27,750.000 $27,500.000
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 4.000 $2,500.000 $1,700.000 $1,600.000 $1,800.000 $1,760.000
SET (TY II) (48 IN) (RCP) (4: 1) (C)
EA 2.000 $4,500.000 $7,100.000 $6,500.000 $7,200.000 $7,150.000
CLEAN EXIST CULVERTS
EA 27.000 $2,500.000 $2,700.000 $2,000.000 $190.000 $7,998.420
REMOV STR (PIPE)
EA 13.000 $2,000.000 $325.000 $300.000 $335.000 $330.000
MOBILIZATION
LS 1.000 $1,710,000.000 $1,950,000.000 $2,500,000.000 $2,730,000.000 $2,613,402.060
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 35.000 $8,000.000 $25,000.000 $30,000.000 $35,250.000 $31,641.330
ROCK FILTER DAMS (INSTALL) (TY 3)
LF 299.000 $60.000 $76.000 $70.000 $90.000 $83.050
ROCK FILTER DAMS (REMOVE)
LF 299.000 $18.000 $22.000 $15.000 $10.000 $45.480
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 444.000 $50.000 $54.500 $30.000 $35.000 $86.680
CONSTRUCTION EXITS (REMOVE)
SY 444.000 $10.000 $16.500 $8.000 $7.000 $45.480
SANDBAGS FOR EROSION CONTROL
EA 800.000 $8.000 $5.450 $15.000 $25.000 $62.280
TEMP SEDMT CONT FENCE (INSTALL)
LF 10,000.000 $3.000 $3.250 $4.500 $8.750 $7.640
TEMP SEDMT CONT FENCE (REMOVE)
LF 5,000.000 $1.000 $1.100 $1.250 $4.000 $3.050
BIODEG EROSN CONT LOGS (INSTL) (18")
LF 12,360.000 $7.000 $6.800 $8.750 $8.300 $7.880
BIODEG EROSN CONT LOGS (REMOVE)
LF 6,180.000 $2.000 $2.200 $2.000 $3.350 $1.650
PORT CTB (DES SOURCE)(F-SHAPE)(TY 1)
LF 390.000 $15.000 $35.500 $10.000 $22.250 $22.000
PORT CTB (MOVE)(F-SHAPE)(TY 1)
LF 4,110.000 $10.000 $20.500 $15.000 $17.000 $16.500
PORT CTB (STKPL)(F-SHAPE)(TY 1)
LF 1,080.000 $15.000 $25.000 $10.000 $22.250 $22.000
INTERSECTIONS (ACP)
SY 1,612.000 $50.000 $125.000 $99.040 $108.000 $144.520
DRIVEWAYS (CONC)
SY 685.000 $90.000 $135.000 $150.000 $155.000 $188.840
DRIVEWAYS (ACP)
SY 3,202.000 $60.000 $100.000 $85.000 $73.000 $106.550
TURNOUTS (ACP)
SY 127.000 $50.000 $115.000 $100.000 $1,465.000 $275.350
RUMBLE STRIPS (SHOULDER) ASPHALT
LF 122,906.000 $0.200 $0.090 $0.250 $0.250 $0.090
RUMBLE STRIPS (CENTERLINE) ASPHALT
LF 61,453.000 $0.200 $0.150 $0.300 $0.300 $0.090
MTL W-BEAM GD FEN (STEEL POST)
LF 2,275.000 $40.000 $38.500 $32.000 $39.400 $39.050
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 4.000 $3,000.000 $4,200.000 $2,600.000 $4,275.000 $4,235.000
REMOVE METAL BEAM GUARD FENCE
LF 1,400.000 $4.000 $3.250 $3.000 $3.350 $3.300
REMOVE TERMINAL ANCHOR SECTION
EA 6.000 $350.000 $325.000 $300.000 $335.000 $330.000
GUARDRAIL END TREATMENT (INSTALL)
EA 18.000 $4,000.000 $3,900.000 $3,175.000 $3,940.000 $3,905.000
GUARDRAIL END TREATMENT (REMOVE)
EA 8.000 $900.000 $325.000 $300.000 $335.000 $330.000
CRASH CUSH ATTEN (MOVE & RESET)
EA 56.000 $1,800.000 $2,700.000 $3,250.000 $2,800.000 $2,750.000
CRASH CUSH ATTEN (REMOVE)
EA 13.000 $1,500.000 $1,600.000 $1,750.000 $1,665.000 $1,650.000
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
EA 13.000 $7,000.000 $8,200.000 $9,975.000 $8,325.000 $8,250.000
WIRE FENCE (TY C)
LF 300.000 $10.000 $38.000 $35.000 $40.000 $16.760
MAILBOX INSTALL-S (TWW-POST) TY 4
EA 8.000 $350.000 $315.000 $325.000 $420.000 $319.000
MAILBOX INSTALL-D (TWW-POST) TY 4
EA 1.000 $400.000 $350.000 $350.000 $475.000 $352.000
MAILBOX INSTALL-M (TWW-POST) TY 4
EA 1.000 $600.000 $760.000 $725.000 $890.000 $770.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 14.000 $800.000 $795.000 $785.000 $1,110.000 $803.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P-BM)
EA 12.000 $1,200.000 $840.000 $889.000 $1,200.000 $847.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 26.000 $900.000 $940.000 $931.000 $1,260.000 $951.500
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
EA 1.000 $1,200.000 $980.000 $846.000 $1,400.000 $990.000
IN SM RD SN SUP&AM TYS80(1)SA(U-1EXT)
EA 1.000 $1,500.000 $1,100.000 $1,428.000 $1,800.000 $1,100.000
REMOVE SM RD SN SUP&AM
EA 51.000 $100.000 $110.000 $100.000 $125.000 $110.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 33.000 $90.000 $49.000 $39.000 $50.000 $49.500
INSTL DEL ASSM (D-SW)SZ 1(WFLX)GND(BI)
EA 50.000 $90.000 $81.500 $76.000 $166.500 $82.500
INSTL DEL ASSM (D-SW)SZ 1(WFLX)SRF(BI)
EA 8.000 $90.000 $165.000 $96.000 $185.000 $165.000
INSTL OM ASSM (OM-2Z)(WFLX)GND(BI)
EA 54.000 $60.000 $81.500 $82.000 $166.500 $82.500
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
LF 289,156.000 $0.250 $0.160 $0.150 $0.170 $0.170
WK ZN PAV MRK NON-REMOV (W)24"(SLD)
LF 930.000 $5.000 $2.200 $2.000 $2.250 $2.200
WK ZN PAV MRK NON-REMOV(W)18"(YLD TRI)
EA 192.000 $25.000 $22.000 $20.000 $22.200 $22.000
WK ZN PAV MRK NON-REMOV (Y)4"(BRK)
LF 34,530.000 $0.250 $0.160 $0.150 $0.170 $0.170
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 301,090.000 $0.250 $0.160 $0.150 $0.170 $0.170
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 27,230.000 $2.000 $1.300 $1.000 $1.750 $4.870
RE PM W/RET REQ TY I (W)6"(SLD)(100MIL)
LF 130,706.000 $0.500 $0.760 $0.700 $0.780 $0.770
RE PM W/RET REQ TY I (Y)6"(BRK)(100MIL)
LF 13,760.000 $0.500 $0.760 $0.700 $0.780 $0.770
RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL)
LF 49,080.000 $0.500 $0.760 $0.700 $0.780 $0.770
PREFAB PAV MRK TY C (W) (24") (SLD)
LF 201.000 $25.000 $18.500 $17.000 $19.000 $18.700
REFL PAV MRKR TY II-A-A
EA 1,295.000 $3.000 $3.800 $3.500 $3.900 $3.850
ELIM EXT PAV MRK & MRKS (4")
LF 292,294.000 $0.700 $0.710 $0.650 $0.750 $0.720
ELIM EXT PAV MRK & MRKS (24")
LF 930.000 $5.000 $5.450 $5.000 $5.550 $5.500
ELIM EXT PAV MRK & MRKS (18")(YLD TRI)
EA 192.000 $20.000 $11.000 $10.000 $11.100 $11.000
FULL - WIDTH MOWING
CYC 6.000 $5,000.000 $5,400.000 $2,250.000 $6,545.000 $18,600.770
LITTER REMOVAL
CYC 6.000 $2,000.000 $2,700.000 $845.000 $3,300.000 $12,777.140
STONE-MTRX-ASPH SMA-D SAC-B PG76-28
TON 25,940.000 $135.000 $200.000 $220.000 $206.000 $197.580
TACK COAT
GAL 54.000 $10.000 $6.550 $10.000 $10.000 $244.220
CEMENT
TON 894.000 $320.000 $245.000 $225.000 $280.000 $489.260
FOAMED ASPHALT TREAT (8") (DC)
SY 226,641.000 $4.500 $4.800 $4.250 $9.100 $6.790
ASPHALT BINDER (PG 64-22)
GAL 535,862.000 $3.000 $4.150 $4.500 $4.800 $4.980
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 2,100.000 $100.000 $27.000 $35.000 $92.000 $80.300
TMA (STATIONARY)
DAY 1,968.000 $150.000 $165.000 $155.000 $550.000 $252.990
TMA (MOBILE OPERATION)
DAY 108.000 $250.000 $870.000 $950.000 $925.000 $846.530
TEMP SPEED MONITOR SYS
EA 2.000 $15,000.000 $16,500.000 $12,500.000 $20,000.000 $12,389.430
Totals: $18,805,429.350 $23,557,970.650 $25,176,322.580 $27,359,902.950 $27,982,885.060