TxDOT Subcontracts for DTM TRUCKING, INC.
| Control Number | County | Highway | Bid Date | Low Bidder | Pay Estimates | % of Contract | Amount | % Complete | Contract Amount |
|---|---|---|---|---|---|---|---|---|---|
| 0479-04-055 | WINKLER | SH 302 | 10/09/2025 | RAGLE CONSTRUCTION, INC. | No reports | 0.01% | $1,407.41 | 0.00% | $14,074,052.74 |
| 0005-14-094 | MIDLAND | IH 20 | 03/06/2024 | SUNDT CONSTRUCTION, INC. | 05/26 | 04/26 | 03/26 | 02/26 | 01/26 | 2.71% | $4,420,595.59 | 58.00% | $163,121,608.34 |
| 0005-13-064 | ECTOR | IH 20 | 11/02/2023 | SUNDT CONSTRUCTION, INC. | 05/26 | 04/26 | 03/26 | 02/26 | 01/26 | 3.20% | $7,620,480.21 | 60.00% | $238,140,006.54 |
| 0479-04-038 | WINKLER | SH 302 | 09/03/2020 | JOHNSON BROS. CORPORATION, A SOUTHLAND COMPANY | 04/26 | 03/26 | 02/26 | 01/26 | 12/25 | 3.28% | $1,521,419.58 | 98.00% | $46,384,743.22 |
| 0068-09-012 | LYNN | SL 76 | 05/08/2020 | ALLEN BUTLER CONSTRUCTION, INC. | 12/24 | 11/24 | 10/24 | 09/24 | 08/24 | 2.72% | $652,327.74 | 97.00% | $23,982,637.33 |
| 0052-01-042 | PARMER | US 70 | 12/03/2019 | JOHNSON BROS. CORPORATION, A SOUTHLAND COMPANY | 03/25 | 02/25 | 01/25 | 12/24 | 11/24 | 8.67% | $876,302.48 | 95.00% | $10,107,295.03 |
| 0076-01-029 | PECOS | US 67 | 04/03/2019 | JOHNSON BROS. CORPORATION, A SOUTHLAND COMPANY | 09/24 | 08/24 | 07/24 | 06/24 | 05/24 | 3.30% | $1,614,906.36 | 25.00% | $48,936,556.30 |
| 0168-01-030 | PARMER | US 60 | 03/06/2019 | JOHNSON BROS. CORPORATION, A SOUTHLAND COMPANY | 10/25 | 09/25 | 08/25 | 07/25 | 06/25 | 2.14% | $545,276.41 | 97.00% | $25,480,205.97 |