WINKLER SH 302 (0479-04-038)

Items: 97

County: WINKLER
Length: N/A
Highway: SH 302
District: ODESSA
Control Number: 0479-04-038
DBE Goal: N/A
Project: STP 2B20(250)
Guaranty: N/A
Time: 515 WORKING DAYS
Engineer's Estimate: $48,731,543.64
Date: 09/03/2020 (5 years ago)
Contract Number: N/A
Type: ROADWAY REHABILITATION
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (6)
E
Engineer's Estimate
$48,731,543.64
Over/Under Est: -10.77% -$5,246,438.74
$44,958,019.15
Over/Under Est: -7.74% -$3,773,524.49
Amt Left: 3.39% $1,472,914.25
Over/Under Est: -6.17% -$3,007,214.13
Amt Left: 5.15% $2,239,224.61
Delta: -1.70% -$766,310.36
Over/Under Est: -4.15% -$2,021,807.75
Amt Left: 7.42% $3,224,630.99
Delta: -2.16% -$985,406.38
Over/Under Est: -3.57% -$1,739,338.93
Amt Left: 8.07% $3,507,099.81
Delta: -0.60% -$282,468.82
$48,799,211.51
Over/Under Est: 0.14% $67,667.87
Amt Left: 12.22% $5,314,106.61
Delta: -3.85% -$1,807,006.80
Subcontractor Percentage Amount
SIBONEY CONTRACTING CO. 11.84% $5,491,953.60
HOOT JOHNSON CONSTRUCTION, INC. 7.10% $3,293,316.77
DTM TRUCKING, INC. 3.28% $1,521,419.58
PEYSON TRANSPORT, LLC 3.16% $1,465,757.89
WILD WEST TRUCKING, LLC 3.08% $1,428,650.09
WILD WEST TRUCKING, LLC 1.80% $834,925.38
BIG R TRUCKING TX LLC 1.08% $500,955.23
BARRICADES UNLIMITED 1.00% $463,847.43
TRP CONSTRUCTION GROUP, LLC 1.00% $463,847.43
FLASHER EQUIPMENT COMPANY 0.95% $440,655.06
WILLIS ELECTRIC CO., LP 0.39% $180,900.50
HJC FARMS, INC. 0.26% $120,600.33
FLAT LINE, INC. 0.21% $97,407.96
Total: 35.15% $16,304,237.25

Bid Items & Bid Tabulations

97 Total 0 of 97
WINKLER  |  SH 302  |  ODESSA  |  0479-04-038  |  09/03/2020  |  $48,731,543.64  |  STP 2B20(250)  |  ROADWAY REHAB  |  515 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
JOHNSON BROS. CORPORATION, A SOUTHLAND COMPANY
RK HALL, LLC
JONES BROS. DIRT & PAVING CONTRACTORS, INC.
KIEWIT INFRASTRUCTURE SOUTH CO.
ANGEL BROTHERS HOLDINGS CORP.
FNF CONSTRUCTION, INC.
PREPARING ROW
STA 668.000 $1,000.000 $5,500.000 $327.230 $250.000 $400.000 $1,200.000 $1,000.000
REMOVING STAB BASE & ASPH PAV (6" - 8")
SY 281,718.000 $7.500 $4.000 $2.800 $2.620 $2.390 $2.000 $3.250
EXCAVATION (ROADWAY)
CY 71,975.000 $8.500 $16.500 $8.680 $13.000 $12.430 $10.000 $9.400
EMBANKMENT (FINAL)(ORD COMP)(TY B)
CY 63.000 $75.000 $28.000 $114.380 $170.000 $48.670 $8.000 $8.000
EMBANKMENT (FINAL)(DENS CONT)(TY B)
CY 126,729.000 $10.000 $5.000 $8.750 $14.500 $12.850 $9.000 $15.000
BLADING
HR 50.000 $175.000 $140.000 $153.040 $350.000 $415.830 $60.000 $325.000
PROOF ROLLING
HR 33.000 $95.000 $90.000 $132.800 $150.000 $206.790 $60.000 $90.000
FL BS (CMP IN PLC)(TY A GR 4)(5")
SY 274,119.000 $7.500 $8.000 $7.500 $7.700 $6.280 $8.850 $7.500
REWORK BS MTL (TY D)(SURF)(ORD COMP)
SY 224,393.000 $0.850 $2.000 $0.990 $0.700 $0.710 $0.890 $1.400
PRIME COAT (MC-30)
GAL 99,661.000 $5.000 $5.000 $4.190 $4.150 $4.550 $3.600 $5.250
FOG SEAL (SS-1)
GAL 4,106.000 $4.000 $4.000 $6.800 $4.550 $3.740 $3.300 $3.750
FOG SEAL (CSS-1H)
GAL 49,830.000 $3.500 $4.000 $3.110 $3.900 $3.050 $3.300 $3.250
ASPH (AC-20-5TR)
GAL 184,733.000 $3.000 $4.000 $3.190 $3.170 $3.380 $3.500 $3.000
AGGR(TY-PB GR-4 SAC-A)
CY 4,227.000 $100.000 $130.000 $142.250 $100.000 $100.270 $50.000 $110.000
STONE-MTRX-ASPH SMAR-F SAC-A
TON 40,374.000 $120.000 $104.500 $115.580 $112.000 $120.520 $110.000 $108.000
CEM STABIL BKFL
CY 932.000 $175.000 $60.000 $216.000 $409.580 $235.470 $250.000 $206.000
TEMPORARY SPL SHORING
SF 1,028.000 $25.000 $65.000 $21.600 $101.050 $23.550 $30.000 $39.000
DRILL SHAFT (RDWY ILL POLE) (30 IN)
LF 80.000 $225.000 $450.000 $324.000 $322.500 $353.200 $330.000 $393.000
CL B CONC (MISC)
CY 56.100 $550.000 $800.000 $540.000 $1,179.280 $588.670 $630.000 $701.000
RIPRAP (CONC)(5 IN)
CY 120.000 $500.000 $400.000 $540.000 $790.130 $588.670 $630.000 $675.000
GABION MATTRESSES (GALV)(12 IN)
SY 79.000 $45.000 $75.000 $509.700 $40.000 $47.840 $160.000 $150.000
CONC BOX CULV (5 FT X 3 FT)
LF 184.000 $325.000 $300.000 $442.800 $655.750 $482.710 $257.000 $440.000
CONC BOX CULV (6 FT X 3 FT)
LF 68.000 $375.000 $315.000 $567.000 $712.730 $618.110 $339.000 $690.000
CONC BOX CULV (9 FT X 5 FT)
LF 515.000 $750.000 $900.000 $993.600 $1,469.530 $1,083.160 $545.000 $860.000
RC PIPE (CL III)(18 IN)
LF 3,615.000 $80.000 $50.000 $64.800 $105.350 $70.640 $55.000 $90.000
RC PIPE (CL IV)(24 IN)
LF 83.000 $100.000 $85.000 $129.600 $178.450 $141.280 $98.000 $168.000
RC PIPE (CL IV)(30 IN)
LF 86.000 $125.000 $125.000 $151.200 $223.600 $164.830 $114.000 $186.000
RC PIPE (CL IV)(36 IN)
LF 72.000 $150.000 $125.000 $302.400 $302.080 $329.660 $185.000 $246.000
RC PIPE (CL IV)(42 IN)
LF 92.000 $185.000 $200.000 $216.000 $388.080 $235.470 $150.000 $266.000
SET (TY I)(S= 5 FT)(HW= 4 FT)(4:1) (C)
EA 6.000 $10,000.000 $9,000.000 $5,400.000 $8,688.150 $5,886.720 $14,200.000 $6,800.000
SET (TY I)(S= 6 FT)(HW= 4 FT)(4:1) (C)
EA 2.000 $11,750.000 $8,000.000 $12,960.000 $26,740.630 $14,128.130 $16,800.000 $20,000.000
SET (TY I)(S= 9 FT)(HW= 6 FT)(4:1) (C)
EA 14.000 $15,000.000 $11,000.000 $7,020.000 $10,106.080 $7,652.740 $15,200.000 $8,300.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 160.000 $1,250.000 $800.000 $1,188.000 $1,216.900 $1,295.080 $1,500.000 $1,700.000
SET (TY II) (24 IN) (RCP) (4: 1) (C)
EA 2.000 $2,000.000 $1,500.000 $1,188.000 $1,196.480 $1,295.080 $2,300.000 $2,100.000
SET (TY II) (30 IN) (RCP) (4: 1) (C)
EA 2.000 $2,500.000 $2,000.000 $2,160.000 $1,888.780 $2,354.690 $2,800.000 $3,000.000
SET (TY II) (36 IN) (RCP) (6: 1) (C)
EA 2.000 $3,750.000 $4,000.000 $4,158.000 $2,857.350 $4,532.770 $5,400.000 $4,000.000
SET (TY II) (42 IN) (RCP) (4: 1) (C)
EA 2.000 $5,000.000 $4,000.000 $4,860.000 $4,255.930 $5,298.050 $7,600.000 $5,400.000
REMOV STR (SET)
EA 2.000 $500.000 $400.000 $540.000 $411.730 $588.670 $900.000 $2,450.000
REMOV STR (PIPE)
EA 1.000 $500.000 $500.000 $270.000 $1,082.530 $294.340 $900.000 $2,200.000
MOBILIZATION
LS 1.000 $4,485,138.600 $4,031,000.000 $974,223.570 $2,000,000.000 $4,144,219.510 $4,690,000.000 $4,555,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 27.000 $12,500.000 $7,500.000 $10,000.000 $20,000.000 $25,000.000 $6,400.000 $21,811.740
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 960.000 $20.000 $24.000 $14.900 $16.000 $47.000 $44.000 $29.950
CONSTRUCTION EXITS (REMOVE)
SY 960.000 $10.000 $8.000 $4.460 $5.000 $20.000 $13.000 $7.360
BIODEG EROSN CONT LOGS (INSTL) (18")
LF 250.000 $7.500 $6.000 $5.110 $32.000 $17.000 $8.000 $9.270
BIODEG EROSN CONT LOGS (REMOVE)
LF 250.000 $1.500 $1.000 $1.570 $15.000 $10.000 $2.000 $1.790
CONSTRUCTING DETOURS
SY 77,492.000 $60.000 $9.000 $39.770 $45.000 $28.910 $44.250 $44.370
PTB (FRN&INSTL)(SGL SLP)(TY 1) OR (STL)
LF 20,540.000 $50.000 $48.000 $55.040 $66.650 $40.000 $5.000 $62.890
PTB (MOVE)(SGL SLP)(TY 1) OR (STL)
LF 106,260.000 $8.000 $6.000 $2.990 $10.750 $6.000 $5.000 $2.450
PTB (REMOVE)(SGL SLP)(TY 1) OR (STL)
LF 20,540.000 $12.000 $7.000 $6.970 $10.750 $5.000 $5.000 $3.350
DRIVEWAYS (CONC)
SY 597.000 $80.000 $90.000 $154.080 $145.000 $140.480 $110.000 $140.480
DRIVEWAYS (ACP)
SY 17,081.000 $45.000 $30.000 $43.100 $63.000 $50.180 $48.000 $75.380
RUMBLE STRIPS (SHOULDER)
LF 133,054.000 $0.160 $0.150 $0.130 $0.130 $0.140 $0.110 $0.150
RUMBLE STRIPS (CENTERLINE)
LF 52,163.000 $0.200 $0.150 $0.210 $0.200 $0.140 $0.110 $0.150
CRASH CUSH ATTEN (MOVE & RESET)
EA 123.000 $1,500.000 $1,500.000 $1,314.500 $1,881.250 $1,282.720 $1,500.000 $1,000.000
CRASH CUSH ATTEN (REMOVE)
EA 27.000 $800.000 $800.000 $767.490 $1,343.750 $1,282.720 $1,000.000 $700.000
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
EA 27.000 $7,500.000 $7,500.000 $8,054.200 $8,600.000 $8,000.000 $11,000.000 $10,000.000
IN RD IL (TY SA) 50T-8 (400W EQ) LED
EA 10.000 $3,650.000 $4,500.000 $5,616.000 $5,590.000 $6,122.190 $5,700.000 $5,300.000
CONDT (PVC) (SCH 40) (2")
LF 559.000 $10.000 $10.000 $10.800 $10.750 $11.770 $11.000 $11.000
CONDT (PVC) (SCH 40) (2") (BORE)
LF 563.000 $27.000 $25.000 $32.400 $32.250 $35.320 $33.000 $31.000
ELEC CONDR (NO.8) INSULATED
LF 2,153.000 $1.000 $1.500 $2.160 $2.150 $2.350 $2.210 $2.500
ELEC CONDR (NO.6) INSULATED
LF 1,806.000 $1.500 $1.650 $2.700 $2.690 $2.940 $2.750 $2.600
GROUND BOX TY A (122311)W/APRON
EA 12.000 $920.000 $1,000.000 $1,350.000 $1,343.750 $1,471.680 $1,300.000 $1,300.000
ELC SRV TY A 240/480 060(NS)SS(E)SP(O)
EA 2.000 $6,115.000 $7,500.000 $7,830.000 $7,793.750 $8,535.740 $8,000.000 $7,400.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 72.000 $550.000 $550.000 $807.840 $804.100 $880.650 $900.000 $760.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 4.000 $700.000 $700.000 $995.760 $991.150 $1,085.510 $1,000.000 $940.000
IN SM RD SN SUP&AM TYS80(1)SA(T)
EA 5.000 $800.000 $655.000 $1,045.440 $1,040.600 $1,139.670 $1,300.000 $990.000
IN SM RD SN SUP&AM TYS80(1)SA(U)
EA 1.000 $850.000 $1,000.000 $1,220.400 $1,214.750 $1,330.400 $1,400.000 $1,200.000
IN SM RD SN SUP&AM TYS80(2)SA(P)
EA 6.000 $1,600.000 $1,195.000 $1,447.200 $1,440.500 $1,577.640 $1,900.000 $1,400.000
RELOCATE SM RD SN SUP&AM(SIGN ONLY)
EA 1.000 $275.000 $400.000 $216.000 $215.000 $235.470 $330.000 $210.000
REMOVE SM RD SN SUP&AM
EA 61.000 $100.000 $95.000 $135.150 $80.000 $107.740 $120.000 $100.000
INSTL DEL ASSM (D-SW)SZ 1(FLX)GND(BI)
EA 13.000 $95.000 $65.000 $91.800 $91.380 $100.070 $99.450 $87.000
INSTL OM ASSM (OM-2Z)(FLX)GND
EA 12.000 $95.000 $86.000 $93.960 $93.530 $102.430 $130.000 $89.000
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
LF 186,848.000 $0.150 $0.250 $0.140 $0.140 $0.150 $0.110 $0.150
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 174,784.000 $0.200 $0.250 $0.140 $0.140 $0.150 $0.120 $0.150
WK ZN PAV MRK REMOV (W)4"(SLD)
LF 82,155.000 $0.800 $0.750 $0.540 $0.540 $0.590 $1.110 $0.700
WK ZN PAV MRK REMOV (Y)4"(SLD)
LF 93,593.000 $0.800 $0.750 $0.540 $0.540 $0.590 $1.110 $0.700
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 13,450.000 $1.250 $1.000 $3.110 $1.500 $2.350 $1.000 $2.000
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 13,420.000 $1.250 $0.850 $3.110 $1.500 $2.350 $1.000 $2.000
REFL PAV MRK TY I (W)8"(LNDP)(100MIL)
LF 1,290.000 $0.800 $0.750 $0.820 $0.820 $0.890 $0.880 $1.250
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 30,283.000 $1.000 $0.850 $0.820 $0.820 $0.890 $0.880 $0.750
RE PM W/RET REQ TY I (W)4"(BRK)(100MIL)
LF 12,084.000 $0.400 $0.400 $0.410 $0.410 $0.450 $0.440 $0.400
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 133,054.000 $0.400 $0.300 $0.410 $0.410 $0.450 $0.440 $0.400
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 239,836.000 $0.400 $0.350 $0.410 $0.410 $0.450 $0.440 $0.400
PREFAB PAV MRK TY C (W) (24") (SLD)
LF 122.000 $13.000 $13.000 $17.280 $17.200 $18.840 $16.000 $13.000
PREFAB PAV MRK TY C (W) (ARROW)
EA 44.000 $225.000 $210.000 $286.200 $284.880 $312.000 $200.000 $215.000
PREFAB PAV MRK TY C (W) (LNDP ARROW)
EA 24.000 $450.000 $495.000 $648.000 $645.000 $706.410 $500.000 $490.000
PREFAB PAV MRK TY C (W) (WORD)
EA 44.000 $260.000 $266.000 $351.000 $349.380 $382.640 $270.000 $260.000
REFL PAV MRKR TY I-C
EA 1,777.000 $3.250 $3.000 $3.240 $3.230 $3.530 $3.200 $3.100
REFL PAV MRKR TY II-A-A
EA 2,645.000 $3.250 $3.000 $3.240 $3.230 $3.530 $3.200 $3.000
ELIM EXT PAV MRK & MRKS (4")
LF 91,220.000 $1.000 $0.400 $0.590 $0.590 $0.650 $0.200 $0.600
SP MIXES SP-B SAC-B PG70-22
TON 257,579.000 $75.000 $68.000 $89.000 $74.000 $82.610 $84.000 $80.000
TACK COAT
GAL 116,673.000 $3.250 $3.000 $3.440 $3.910 $2.900 $2.750 $4.000
BONDING COURSE
GAL 58,337.000 $3.500 $3.000 $4.620 $4.140 $4.290 $3.350 $3.900
PORTABLE CHANGEABLE MESSAGE SIGN
EA 4.000 $10,000.000 $9,000.000 $17,093.450 $16,500.000 $19,913.460 $13,500.000 $25,000.000
TMSP RADAR SPEED CONTROL MONITOR
EA 2.000 $10,000.000 $12,500.000 $9,313.750 $9,900.000 $11,773.320 $22,500.000 $15,000.000
TMA (STATIONARY)
DAY 515.000 $200.000 $200.000 $254.940 $55.000 $349.510 $335.000 $190.000
TMA (MOBILE OPERATION)
HR 80.000 $75.000 $50.000 $362.330 $93.500 $87.130 $84.000 $95.000
Totals: $48,731,543.640 $43,485,104.900 $44,958,019.150 $45,724,329.518 $46,709,735.897 $46,992,204.710 $48,799,211.510