Control Number County Highway Bid Date Low Bidder Pay Estimates % of Contract Amount % Complete Contract Amount
0914-00-512 TRAVIS VA 02/01/2024 TEXAS MATERIALS GROUP, INC. 04/26 | 03/26 | 02/26 | 01/26 | 12/25 1.10% $100,285.86 71.00% $9,116,896.65
0136-04-048 DELTA SH 19 12/05/2023 GARRET SHIELDS INFRASTRUCTURE 05/26 | 04/26 | 03/26 | 02/26 | 01/26 0.00% $0.00 19.00% $4,447,953.00
6442-78-001 TRAVIS IH0035 11/01/2023 TEXAS MATERIALS GROUP, INC. 02/26 | 01/26 | 12/25 | 11/25 | 10/25 0.67% $50,120.37 46.00% $7,480,651.97
0009-04-074 ROCKWALL SH 66 08/03/2023 FNH CONSTRUCTION, LLC 10/25 | 09/25 | 08/25 | 07/25 | 06/25 3.66% $149,969.49 83.00% $4,097,527.00