REMOVING CONC (MEDIANS)
|
SY
|
90.000
|
$6.000
|
$43.000
|
$35.000
|
$19.350
|
$24.560
|
$37.000
|
$10.260
|
$45.000
|
|
|
REMOVING CONC (SIDEWALKS)
|
SY
|
15.000
|
$8.750
|
$43.000
|
$35.000
|
$19.350
|
$147.330
|
$36.750
|
$12.930
|
$75.000
|
|
|
REMOVING CONCRETE(MOW STRIP)
|
LF
|
2,915.000
|
$10.000
|
$10.000
|
$8.500
|
$8.865
|
$8.730
|
$8.700
|
$8.410
|
$8.500
|
|
|
EMBANKMENT (FINAL)(ORD COMP)(TY B)
|
CY
|
6.800
|
$25.000
|
$150.000
|
$96.360
|
$88.400
|
$262.030
|
$89.250
|
$6.220
|
$100.000
|
|
|
BACKFILL (TY A)
|
STA
|
324.750
|
$225.000
|
$90.000
|
$95.550
|
$187.469
|
$280.000
|
$189.310
|
$227.300
|
$204.000
|
|
|
BACKFILL (TY B)
|
STA
|
501.000
|
$150.000
|
$90.000
|
$95.550
|
$118.500
|
$230.000
|
$357.710
|
$187.750
|
$264.000
|
|
|
BLADING
|
HR
|
58.000
|
$100.000
|
$80.000
|
$91.200
|
$111.505
|
$145.990
|
$150.000
|
$164.810
|
$126.000
|
|
|
COMPOST MANUF TOPSOIL (4")
|
SY
|
9,414.000
|
$1.500
|
$1.500
|
$2.200
|
$0.873
|
$0.800
|
$1.000
|
$0.770
|
$12.000
|
|
|
BLOCK SODDING
|
SY
|
9,414.000
|
$4.000
|
$4.750
|
$4.750
|
$4.940
|
$5.350
|
$5.250
|
$5.220
|
$5.350
|
|
|
VEGETATIVE WATERING
|
MG
|
146.900
|
$20.000
|
$25.000
|
$19.980
|
$21.758
|
$18.000
|
$250.000
|
$38.450
|
$252.000
|
|
|
D-GR HMA (SQ) TY-D PG 70-22(LEVEL-UP)
|
TON
|
9,000.000
|
$87.000
|
$76.500
|
$67.590
|
$79.887
|
$88.450
|
$102.600
|
$105.440
|
$85.000
|
|
|
SUPERPAVE MIXTURES SP-C SAC-B PG70-22
|
TON
|
65,526.000
|
$96.000
|
$74.250
|
$69.690
|
$79.676
|
$88.000
|
$97.770
|
$99.220
|
$80.000
|
|
|
SUPERPAVE MIXTURES SP-D SAC-B PG70-22
|
TON
|
13,324.000
|
$96.000
|
$75.750
|
$64.670
|
$79.953
|
$85.500
|
$82.210
|
$99.810
|
$79.000
|
|
|
FLEXIBLE PAVEMENT STRUCTURE REPAIR(8")
|
SY
|
15,529.000
|
$41.000
|
$37.500
|
$37.380
|
$38.975
|
$50.000
|
$52.800
|
$65.520
|
$41.500
|
|
|
PLANE ASPH CONC PAV (1")
|
SY
|
154,486.000
|
$0.900
|
$0.900
|
$0.530
|
$2.047
|
$1.350
|
$1.030
|
$1.200
|
$2.100
|
|
|
PLANE ASPH CONC PAV (2")
|
SY
|
564,378.000
|
$1.000
|
$0.900
|
$1.910
|
$1.956
|
$2.000
|
$1.810
|
$1.880
|
$3.400
|
|
|
RIPRAP (CONC)(4 IN)
|
CY
|
5.350
|
$480.000
|
$750.000
|
$540.000
|
$802.500
|
$525.000
|
$567.000
|
$565.610
|
$850.000
|
|
|
RIPRAP (STONE COMMON)(DRY)(6 IN)
|
CY
|
303.900
|
$200.000
|
$135.000
|
$120.000
|
$192.600
|
$150.000
|
$165.000
|
$82.400
|
$150.000
|
|
|
RIPRAP (MOW STRIP)(4 IN)
|
CY
|
223.200
|
$425.000
|
$435.000
|
$455.000
|
$535.000
|
$425.000
|
$455.000
|
$526.030
|
$420.000
|
|
|
CLEANING AND SEALING JOINTS
|
LF
|
371.000
|
$20.000
|
$45.000
|
$45.000
|
$48.150
|
$43.230
|
$47.000
|
$49.440
|
$45.000
|
|
|
CLEAN EXIST CULVERTS
|
EA
|
9.000
|
$2,500.000
|
$1,500.000
|
$2,500.000
|
$2,461.000
|
$1,800.000
|
$2,550.000
|
$2,417.160
|
$3,000.000
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$1,116,326.440
|
$625,000.000
|
$894,802.800
|
$951,715.136
|
$600,000.000
|
$345,000.000
|
$55,292.000
|
$682,000.000
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
9.000
|
$5,000.000
|
$2,500.000
|
$4,565.800
|
$5,503.318
|
$8,000.000
|
$3,000.000
|
$1,379.980
|
$23,000.000
|
|
|
CONSTRUCTION EXITS (INSTALL) (TY 1)
|
SY
|
222.000
|
$18.000
|
$13.000
|
$25.000
|
$13.520
|
$13.500
|
$13.650
|
$14.280
|
$13.500
|
|
|
CONSTRUCTION EXITS (REMOVE)
|
SY
|
222.000
|
$6.750
|
$2.000
|
$2.000
|
$2.080
|
$10.500
|
$2.100
|
$2.200
|
$10.500
|
|
|
BIODEG EROSN CONT LOGS (INSTL) (12")
|
LF
|
3,025.000
|
$4.000
|
$2.950
|
$2.950
|
$3.068
|
$5.000
|
$3.250
|
$3.240
|
$5.000
|
|
|
BIODEG EROSN CONT LOGS (REMOVE)
|
LF
|
3,025.000
|
$1.000
|
$1.000
|
$1.000
|
$1.040
|
$1.000
|
$1.100
|
$1.100
|
$1.000
|
|
|
ONE-WAY TRAF CONT (FLAGGER CONT)
|
HR
|
144.000
|
$75.000
|
$85.000
|
$85.500
|
$48.800
|
$65.000
|
$100.000
|
$203.260
|
$100.000
|
|
|
ONE-WAY TRAF CONT (PILOT CAR)
|
HR
|
308.000
|
$30.000
|
$85.000
|
$96.900
|
$156.275
|
$75.000
|
$100.000
|
$269.180
|
$88.500
|
|
|
CONC CURB (TY I)
|
LF
|
196.000
|
$35.000
|
$50.000
|
$25.000
|
$21.400
|
$15.000
|
$26.250
|
$12.360
|
$20.000
|
|
|
CURB RAMPS (TY 1)
|
EA
|
2.000
|
$1,440.000
|
$2,200.000
|
$1,600.000
|
$3,182.180
|
$2,000.000
|
$1,700.000
|
$1,862.420
|
$1,500.000
|
|
|
CURB RAMPS (TY 10)
|
EA
|
1.000
|
$1,480.000
|
$2,200.000
|
$2,100.000
|
$3,386.550
|
$2,000.000
|
$2,205.000
|
$1,867.810
|
$1,750.000
|
|
|
CURB RAMPS (TY 22)
|
EA
|
1.000
|
$2,400.000
|
$2,200.000
|
$2,800.000
|
$3,422.930
|
$3,500.000
|
$2,940.000
|
$3,296.120
|
$3,500.000
|
|
|
RUMBLE STRIPS (SHOULDER)
|
LF
|
168,323.000
|
$0.250
|
$0.220
|
$0.120
|
$0.155
|
$0.250
|
$0.110
|
$0.180
|
$0.120
|
|
|
RUMBLE STRIPS (CENTERLINE)
|
LF
|
9,213.000
|
$0.250
|
$0.400
|
$0.180
|
$0.495
|
$0.380
|
$0.400
|
$0.820
|
$0.180
|
|
|
RUMBLE STRIPS (CENTERLINE) ASPHALT
|
LF
|
18,920.000
|
$0.190
|
$0.320
|
$0.180
|
$0.339
|
$0.380
|
$0.300
|
$0.270
|
$0.180
|
|
|
MTL W-BEAM GD FEN (TIM POST)
|
LF
|
2,755.000
|
$22.000
|
$17.000
|
$17.000
|
$21.320
|
$20.000
|
$17.500
|
$18.680
|
$21.950
|
|
|
MTL W-BEAM GD FEN (STEEL POST)
|
LF
|
75.000
|
$50.000
|
$50.000
|
$50.000
|
$76.388
|
$40.000
|
$55.000
|
$54.940
|
$45.450
|
|
|
MTL BEAM GD FEN TRANS (THRIE-BEAM)
|
EA
|
8.000
|
$1,800.000
|
$1,880.000
|
$2,380.000
|
$1,849.230
|
$1,800.000
|
$2,500.000
|
$2,065.570
|
$1,630.000
|
|
|
DOWNSTREAM ANCHOR TERMINAL SECTION
|
EA
|
4.000
|
$1,000.000
|
$855.000
|
$855.000
|
$1,118.000
|
$1,100.000
|
$941.000
|
$939.400
|
$925.000
|
|
|
REMOVE METAL BEAM GUARD FENCE
|
LF
|
2,767.500
|
$2.750
|
$1.000
|
$1.000
|
$1.144
|
$1.750
|
$1.100
|
$1.100
|
$2.000
|
|
|
REMOVE TERMINAL ANCHOR SECTION
|
EA
|
6.000
|
$250.000
|
$80.000
|
$80.000
|
$130.000
|
$200.000
|
$88.000
|
$87.900
|
$150.000
|
|
|
RM MTL BM GD FENCE TRANS (THRIE-BEAM)
|
EA
|
6.000
|
$165.000
|
$125.000
|
$125.000
|
$78.000
|
$100.000
|
$140.000
|
$137.340
|
$195.000
|
|
|
GUARDRAIL END TREATMENT (INSTALL)
|
EA
|
16.000
|
$2,800.000
|
$2,150.000
|
$2,150.000
|
$2,861.040
|
$2,750.000
|
$2,200.000
|
$2,362.220
|
$2,730.000
|
|
|
GUARDRAIL END TREATMENT (REMOVE)
|
EA
|
12.000
|
$250.000
|
$155.000
|
$155.000
|
$109.200
|
$150.000
|
$171.000
|
$170.300
|
$255.000
|
|
|
ALUMINUM SIGNS (TY G)
|
SF
|
533.500
|
$25.000
|
$30.000
|
$25.000
|
$36.400
|
$25.000
|
$85.000
|
$27.470
|
$25.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
|
EA
|
1.000
|
$300.000
|
$465.000
|
$465.180
|
$483.787
|
$450.000
|
$490.000
|
$494.420
|
$452.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
|
EA
|
119.000
|
$350.000
|
$512.000
|
$512.880
|
$533.395
|
$485.000
|
$520.000
|
$554.850
|
$507.000
|
|
|
IN SM RD SN SUP&AM TYS80(1)SB(P)
|
EA
|
8.000
|
$875.000
|
$558.000
|
$558.630
|
$580.975
|
$735.000
|
$590.000
|
$807.550
|
$738.000
|
|
|
IN SM RD SN SUP&AM TYS80(1)SB(T)
|
EA
|
72.000
|
$650.000
|
$625.000
|
$625.970
|
$651.009
|
$745.000
|
$630.000
|
$840.510
|
$768.000
|
|
|
IN SM RD SN SUP&AM TYS80(1)SB(U)
|
EA
|
9.000
|
$985.000
|
$769.000
|
$769.800
|
$800.592
|
$805.000
|
$810.000
|
$884.460
|
$808.000
|
|
|
IN SM RD SN SUP&AM (INST SIGN ONLY)
|
EA
|
381.000
|
$125.000
|
$250.000
|
$250.000
|
$260.000
|
$245.000
|
$253.000
|
$247.210
|
$226.000
|
|
|
REMOVE SM RD SN SUP&AM
|
EA
|
9.000
|
$82.000
|
$100.000
|
$100.000
|
$104.000
|
$125.000
|
$105.000
|
$137.340
|
$126.000
|
|
|
INSTL DEL ASSM (D-SW)SZ (BRF)CTB
|
EA
|
6.000
|
$14.000
|
$10.000
|
$12.860
|
$13.374
|
$25.000
|
$13.690
|
$10.990
|
$15.000
|
|
|
INSTL DEL ASSM (D-SY)SZ (BRF)CTB
|
EA
|
6.000
|
$9.500
|
$12.000
|
$12.860
|
$13.374
|
$25.000
|
$13.690
|
$13.180
|
$15.000
|
|
|
INSTL DEL ASSM (D-SY)SZ (BRF)GF1
|
EA
|
9.000
|
$13.000
|
$14.000
|
$14.000
|
$13.374
|
$25.000
|
$13.690
|
$15.380
|
$15.000
|
|
|
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
|
EA
|
22.000
|
$20.000
|
$18.000
|
$18.000
|
$17.420
|
$25.000
|
$17.600
|
$19.780
|
$18.000
|
|
|
WK ZN PAV MRK NON-REMOV (W)4"(BRK)
|
LF
|
9,204.000
|
$0.300
|
$0.500
|
$0.250
|
$0.312
|
$0.250
|
$0.260
|
$0.550
|
$0.300
|
|
|
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
|
LF
|
53,047.000
|
$0.300
|
$0.500
|
$0.250
|
$0.270
|
$0.500
|
$0.260
|
$0.550
|
$0.260
|
|
|
WK ZN PAV MRK NON-REMOV (W)8"(DOT)
|
LF
|
30.000
|
$0.500
|
$1.000
|
$0.500
|
$1.040
|
$1.000
|
$0.530
|
$1.100
|
$1.000
|
|
|
WK ZN PAV MRK NON-REMOV (W)8"(SLD)
|
LF
|
14,294.000
|
$0.600
|
$1.000
|
$0.500
|
$0.697
|
$1.000
|
$0.530
|
$1.100
|
$0.670
|
|
|
WK ZN PAV MRK NON-REMOV (W)18"(SLD)
|
LF
|
74.000
|
$4.250
|
$4.000
|
$4.500
|
$5.200
|
$4.000
|
$4.730
|
$4.390
|
$5.000
|
|
|
WK ZN PAV MRK NON-REMOV (W)24"(SLD)
|
LF
|
3,550.000
|
$4.000
|
$6.000
|
$6.500
|
$5.200
|
$4.600
|
$6.750
|
$6.590
|
$5.000
|
|
|
WK ZN PAV MRK NON-REMOV (W)(ARROW)
|
EA
|
103.000
|
$90.000
|
$200.000
|
$85.000
|
$104.000
|
$200.000
|
$89.250
|
$219.740
|
$100.000
|
|
|
WK ZN PAV MRK NON-REMOV (W)(DBL ARW)
|
EA
|
1.000
|
$75.000
|
$200.000
|
$95.000
|
$312.000
|
$200.000
|
$99.750
|
$219.750
|
$300.000
|
|
|
WK ZN PAV MRK NON-REMOV (W)(UTURN ARW)
|
EA
|
17.000
|
$90.000
|
$300.000
|
$125.000
|
$253.760
|
$550.000
|
$131.250
|
$329.610
|
$244.000
|
|
|
WK ZN PAV MRK NON-REMOV(W)(WORD)
|
EA
|
101.000
|
$82.000
|
$200.000
|
$135.000
|
$124.800
|
$200.000
|
$141.750
|
$219.740
|
$120.000
|
|
|
WK ZN PAV MRK NON-REMOV (Y)4"(BRK)
|
LF
|
1,275.000
|
$0.300
|
$0.500
|
$0.250
|
$0.312
|
$0.500
|
$0.260
|
$0.550
|
$0.300
|
|
|
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
|
LF
|
47,401.000
|
$0.300
|
$0.500
|
$0.250
|
$0.270
|
$0.500
|
$0.260
|
$0.550
|
$0.260
|
|
|
WK ZN PAV MRK NON-REMOV (Y)(MED NOSE)
|
EA
|
14.000
|
$350.000
|
$500.000
|
$300.000
|
$346.320
|
$500.000
|
$315.000
|
$549.350
|
$333.000
|
|
WK ZN PAV MRK SHT TERM (TAB)TY W
|
EA
|
3,987.000
|
$1.000
|
$0.600
|
$1.270
|
$1.286
|
$1.350
|
$1.250
|
$0.550
|
$1.500
|
|
WK ZN PAV MRK SHT TERM (TAB)TY Y
|
EA
|
1,948.000
|
$0.750
|
$0.600
|
$1.270
|
$1.286
|
$1.140
|
$1.250
|
$0.550
|
$1.500
|
|
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
|
EA
|
5,017.000
|
$0.850
|
$0.650
|
$1.270
|
$1.286
|
$1.000
|
$1.250
|
$0.550
|
$1.500
|
|
REFL PAV MRK TY I (W)4"(DOT)(100MIL)
|
LF
|
160.000
|
$1.000
|
$2.000
|
$2.500
|
$1.040
|
$2.000
|
$2.630
|
$2.200
|
$1.000
|
|
REFL PAV MRK TY I (W)8"(DOT)(100MIL)
|
LF
|
30.000
|
$1.000
|
$2.000
|
$3.500
|
$1.040
|
$2.000
|
$3.680
|
$2.200
|
$1.000
|
|
REFL PAV MRK TY I (W)8"(SLD)(090MIL)
|
LF
|
1,430.000
|
$0.620
|
$1.000
|
$0.950
|
$0.728
|
$1.000
|
$1.000
|
$1.100
|
$0.700
|
|
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
|
LF
|
22,538.000
|
$0.750
|
$1.000
|
$0.980
|
$0.728
|
$1.250
|
$1.000
|
$1.100
|
$0.700
|
|
REFL PAV MRK TY I (W)18"(SLD)(100MIL)
|
LF
|
74.000
|
$6.000
|
$10.000
|
$4.500
|
$5.200
|
$10.000
|
$4.730
|
$10.990
|
$5.000
|
|
REFL PAV MRK TY I (W)24"(SLD)(090MIL)
|
LF
|
348.000
|
$6.200
|
$5.500
|
$6.500
|
$6.729
|
$5.500
|
$6.830
|
$6.040
|
$6.470
|
|
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
|
LF
|
4,202.000
|
$5.250
|
$6.500
|
$6.750
|
$6.115
|
$6.500
|
$6.900
|
$7.140
|
$5.880
|
|
REFL PAV MRK TY I (W)(ARROW)(090MIL)
|
EA
|
45.000
|
$110.000
|
$125.000
|
$95.000
|
$124.800
|
$125.000
|
$100.000
|
$137.340
|
$120.000
|
|
REFL PAV MRK TY I (W)(ARROW)(100MIL)
|
EA
|
107.000
|
$95.000
|
$150.000
|
$98.000
|
$124.800
|
$150.000
|
$102.900
|
$164.810
|
$120.000
|
|
REFL PAV MRK TY I(W)(DBL ARROW)(100MIL)
|
EA
|
1.000
|
$200.000
|
$200.000
|
$120.000
|
$230.880
|
$200.000
|
$126.000
|
$219.750
|
$222.000
|
|
REFL PAV MRK TY I(W)(UTURN ARW)(100MIL)
|
EA
|
17.000
|
$175.000
|
$255.000
|
$125.000
|
$289.120
|
$255.000
|
$131.250
|
$280.170
|
$278.000
|
|
REFL PAV MRK TY I(W)(LNDP ARW)(100MIL)
|
EA
|
10.000
|
$350.000
|
$300.000
|
$175.000
|
$323.440
|
$300.000
|
$185.000
|
$329.610
|
$311.000
|
|
REFL PAV MRK TY I (W)(WORD)(090MIL)
|
EA
|
7.000
|
$155.000
|
$175.000
|
$120.000
|
$139.360
|
$175.000
|
$126.000
|
$192.270
|
$134.000
|
|
REFL PAV MRK TY I (W)(WORD)(100MIL)
|
EA
|
115.000
|
$130.000
|
$200.000
|
$125.000
|
$139.360
|
$200.000
|
$131.250
|
$219.740
|
$134.000
|
|
REF PAV MRK TY I(W)18"(YLD TRI)(090MIL)
|
EA
|
17.000
|
$25.000
|
$25.000
|
$25.000
|
$45.760
|
$25.000
|
$26.250
|
$27.470
|
$44.000
|
|
REF PAV MRK TY I(W)36"(YLD TRI)(100MIL)
|
EA
|
364.000
|
$42.000
|
$35.000
|
$26.000
|
$45.760
|
$35.000
|
$27.300
|
$38.450
|
$44.000
|
|
REFL PAV MRK TY I (Y)24"(SLD)(100MIL)
|
LF
|
27.000
|
$5.000
|
$7.000
|
$6.500
|
$8.320
|
$7.000
|
$6.830
|
$7.690
|
$8.000
|
|
REFL PAV MRK TY I(Y)(MED NOSE)(100MIL)
|
EA
|
22.000
|
$330.000
|
$300.000
|
$400.000
|
$392.080
|
$300.000
|
$425.000
|
$329.610
|
$377.000
|
|
|
PAVEMENT SEALER 4"
|
LF
|
199,669.000
|
$0.240
|
$0.080
|
$0.150
|
$0.260
|
$0.080
|
$0.160
|
$0.090
|
$0.250
|
|
|
PAVEMENT SEALER 6"
|
LF
|
215,176.000
|
$0.120
|
$0.100
|
$0.180
|
$0.364
|
$0.180
|
$0.190
|
$0.110
|
$0.350
|
|
|
PAVEMENT SEALER 8"
|
LF
|
23,998.000
|
$0.280
|
$0.150
|
$0.300
|
$0.458
|
$0.150
|
$0.320
|
$0.160
|
$0.440
|
|
|
PAVEMENT SEALER 18"
|
LF
|
74.000
|
$2.250
|
$0.450
|
$2.000
|
$2.496
|
$0.450
|
$2.100
|
$0.490
|
$2.400
|
|
|
PAVEMENT SEALER 24"
|
LF
|
4,577.000
|
$2.100
|
$0.800
|
$3.000
|
$2.881
|
$0.800
|
$3.150
|
$0.880
|
$2.770
|
|
|
PAVEMENT SEALER (ARROW)
|
EA
|
152.000
|
$25.000
|
$20.000
|
$65.000
|
$65.520
|
$50.000
|
$68.250
|
$21.970
|
$63.000
|
|
|
PAVEMENT SEALER (WORD)
|
EA
|
122.000
|
$30.000
|
$20.000
|
$75.000
|
$65.520
|
$20.000
|
$78.750
|
$21.970
|
$63.000
|
|
|
PAVEMENT SEALER (MED NOSE)
|
EA
|
22.000
|
$80.000
|
$25.000
|
$200.000
|
$253.760
|
$25.000
|
$210.000
|
$27.470
|
$244.000
|
|
|
PAVEMENT SEALER (DBL ARROW)
|
EA
|
1.000
|
$72.000
|
$25.000
|
$75.000
|
$96.720
|
$25.000
|
$79.000
|
$27.460
|
$93.000
|
|
|
PAVEMENT SEALER (UTURN ARROW)
|
EA
|
17.000
|
$71.000
|
$25.000
|
$78.000
|
$149.760
|
$25.000
|
$81.900
|
$27.470
|
$144.000
|
|
|
PAVEMENT SEALER (LNDP ARROW)
|
EA
|
10.000
|
$141.000
|
$25.000
|
$85.000
|
$184.080
|
$25.000
|
$89.250
|
$27.470
|
$177.000
|
|
|
PAVEMENT SEALER (YLD TRI)
|
EA
|
17.000
|
$20.000
|
$7.000
|
$20.000
|
$34.320
|
$7.000
|
$21.000
|
$7.690
|
$33.000
|
|
|
REF PROF PAV MRK TY I(W)6"(SLD)(090MIL)
|
LF
|
65,555.000
|
$1.000
|
$1.350
|
$0.650
|
$1.279
|
$1.350
|
$0.660
|
$1.480
|
$1.230
|
|
RE PM W/RET REQ TY I (W)4"(BRK)(100MIL)
|
LF
|
28,341.000
|
$0.400
|
$0.350
|
$0.300
|
$0.437
|
$0.350
|
$0.320
|
$0.380
|
$0.420
|
|
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
|
LF
|
53,047.000
|
$0.350
|
$0.350
|
$0.300
|
$0.416
|
$0.350
|
$0.310
|
$0.380
|
$0.400
|
|
RE PM W/RET REQ TY I (W)6"(SLD)(100MIL)
|
LF
|
75,482.000
|
$0.500
|
$0.550
|
$0.450
|
$0.562
|
$0.550
|
$0.460
|
$0.600
|
$0.540
|
|
RE PM W/RET REQ TY I (Y)4"(BRK)(090MIL)
|
LF
|
5,800.000
|
$0.300
|
$0.550
|
$0.280
|
$0.458
|
$0.550
|
$0.300
|
$0.600
|
$0.440
|
|
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
|
LF
|
1,275.000
|
$0.400
|
$0.350
|
$0.300
|
$0.458
|
$0.350
|
$0.320
|
$0.380
|
$0.440
|
|
RE PM W/RET REQ TY I (Y)4"(SLD)(090MIL)
|
LF
|
63,645.000
|
$0.320
|
$0.350
|
$0.280
|
$0.416
|
$0.350
|
$0.290
|
$0.380
|
$0.400
|
|
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
|
LF
|
47,401.000
|
$0.350
|
$0.350
|
$0.300
|
$0.416
|
$0.350
|
$0.320
|
$0.380
|
$0.400
|
|
RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL)
|
LF
|
74,139.000
|
$0.500
|
$0.550
|
$0.450
|
$0.562
|
$0.580
|
$0.460
|
$0.600
|
$0.540
|
|
REFL PAV MRKR TY I-C
|
EA
|
511.000
|
$3.250
|
$3.000
|
$5.000
|
$3.921
|
$3.000
|
$5.250
|
$3.300
|
$3.770
|
|
REFL PAV MRKR TY II-A-A
|
EA
|
2,905.000
|
$2.950
|
$3.000
|
$5.000
|
$3.463
|
$3.000
|
$5.150
|
$3.300
|
$3.330
|
|
REFL PAV MRKR TY II-C-R
|
EA
|
2,510.000
|
$4.000
|
$3.000
|
$5.000
|
$3.463
|
$3.000
|
$5.150
|
$3.300
|
$3.330
|
|
|
TREE TRIMMING / BRUSH REMOVAL
|
MI
|
7.300
|
$12,000.000
|
$5,000.000
|
$5,775.000
|
$10,257.530
|
$5,000.000
|
$5,100.000
|
$8,569.910
|
$4,940.000
|
|
|
UNDERSEAL COURSE
|
GAL
|
144,854.000
|
$2.900
|
$2.700
|
$3.080
|
$4.115
|
$3.500
|
$3.150
|
$1.000
|
$4.150
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
DAY
|
345.000
|
$55.000
|
$70.000
|
$81.190
|
$101.650
|
$75.000
|
$100.000
|
$104.380
|
$82.500
|
|
|
TMA (STATIONARY)
|
DAY
|
79.000
|
$165.000
|
$100.000
|
$270.620
|
$273.920
|
$200.000
|
$400.000
|
$274.680
|
$322.000
|
|
|
TMA (MOBILE OPERATION)
|
DAY
|
310.000
|
$130.000
|
$100.000
|
$108.250
|
$299.722
|
$250.000
|
$150.000
|
$181.290
|
$1,142.000
|
|
Totals: |
$12,796,765.435
|
$10,328,208.030
|
$10,608,086.482
|
$12,469,772.543
|
$12,739,192.009
|
$13,001,020.162
|
$13,085,234.844
|
$13,629,366.570
|