Bid Cobra

WEBB IH 35 (0018-04-067)

Items: 47

County: WEBB
Length: 54.5690 MILES
Highway: IH 35
District: LAREDO
Control Number: 0018-04-067
DBE Goal: 0.0%
Project: C 18-4-67
Guaranty: $100,000.00
Time: 120 WORKING DAYS
Engineer's Estimate: $5,545,072.68
Date: 09/04/2025 (9 months ago)
Contract Number: 9253012
Type: SEAL COAT
Project ID: A00189763
Project Description: RESURFACE OF EXISTING ROADWAY SEALCOAT AND PAVEMENT MARKING
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
JOSE VARGAS
ROGELIO CHAPA
ANGEL MARTINEZ
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (4)
E
Engineer's Estimate
$5,545,072.68
$4,828,838.85
Over/Under Est: -12.92% -$716,233.83
$5,228,386.82
Over/Under Est: -5.71% -$316,685.86
Amt Left: 8.27% $399,547.97
Over/Under Est: 15.53% $861,353.60
Amt Left: 32.67% $1,577,587.43
Delta: -22.53% -$1,178,039.46
$6,769,462.03
Over/Under Est: 22.08% $1,224,389.35
Amt Left: 40.19% $1,940,623.18
Delta: -5.67% -$363,035.75
Subcontractor Percentage Amount
VIZCAINO, L.P. 25.95% $1,253,083.68
C.L. WAGNER, LLC 2.55% $123,135.39
MPB, INC. 1.29% $62,292.02
Total: 29.79% $1,438,511.09

Bid Items & Bid Tabulations

47 Total 0 of 47
WEBB  |  IH 35  |  LAREDO  |  0018-04-067  |  09/04/2025  |  $5,545,072.68  |  C 18-4-67  |  SEAL COAT  |  120 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
RONALD R. WAGNER & CO., LP
CK NEWBERRY, LLC
CLARK CONSTRUCTION OF TEXAS, INC.
STX CIVIL
ASPH (AC-20XP)
GAL 520,663.000 $3.400 $3.010 $3.400 $3.610 $4.890
AGGR (TY-PB, GR-3S)(SAC-B)
CY 11,613.000 $93.000 $81.550 $112.000 $121.550 $129.160
AGGR (TY-PD, GR-3)(SAC-B)
CY 3,614.000 $111.000 $86.620 $115.000 $123.740 $138.390
CLEANING AND SEALING EXISTING JOINTS
LF 890.000 $47.000 $77.000 $75.000 $100.000 $79.970
MOBILIZATION
LS 1.000 $504,097.500 $684,553.000 $325,000.000 $1,199,592.000 $475,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 6.000 $4,000.000 $0.010 $10,000.000 $7,500.000 $5,000.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $1,500.000 $0.010 $100.000 $3,000.000 $8,910.980
TMA (STATIONARY)
DAY 34.000 $100.000 $0.010 $1.000 $100.000 $228.490
TMA (MOBILE OPERATION)
DAY 133.000 $100.000 $0.010 $1.000 $100.000 $350.000
ONE-WAY TRAF CONT (PILOT CAR)
HR 118.000 $80.000 $0.010 $0.010 $100.000 $165.530
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 953.000 $0.500 $0.010 $0.010 $0.010 $1.000
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 50,179.000 $0.500 $0.010 $0.010 $0.010 $1.000
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 1,048.000 $0.800 $0.800 $0.800 $0.800 $1.260
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 1,735.000 $7.000 $2.000 $6.000 $6.000 $8.000
REFL PAV MRK TY I (W)(ARROW)(100MIL)
EA 42.000 $120.000 $200.000 $200.000 $200.000 $142.800
REFL PAV MRK TY I (W)(WORD)(100MIL)
EA 6.000 $150.000 $300.000 $200.000 $200.000 $285.610
REFL PAV MRK TY I (W)(RR XING)(100MIL)
EA 1.000 $600.000 $700.000 $700.000 $700.000 $685.460
REF PAV MRK TY I(W)36"(YLD TRI)(100MIL)
EA 88.000 $12.500 $30.000 $25.000 $25.000 $34.270
RE PROFILE PM TY I(W)6"(SLD)(100MIL)
LF 342,143.000 $0.850 $0.700 $0.600 $0.590 $0.660
RE PROFILE PM TY I(Y)6"(SLD)(100MIL)
LF 94,218.000 $0.930 $0.800 $0.600 $0.590 $0.740
RE PROFILE PM TY I(Y)6"(BRK)(100MIL)
LF 44,751.000 $0.890 $0.800 $0.600 $0.590 $0.740
PAVEMENT SLER 6"
LF 1,504,702.000 $0.250 $0.150 $0.150 $0.160 $0.190
PAVEMENT SLER 8"
LF 1,048.000 $0.400 $0.250 $0.300 $0.300 $0.480
PAVEMENT SLER 24"
LF 1,735.000 $3.000 $3.000 $5.000 $5.000 $1.260
PAVEMENT SLER (ARROW)
EA 42.000 $55.000 $1.000 $50.000 $50.000 $22.850
PAVEMENT SLER (WORD)
EA 6.000 $55.000 $1.000 $50.000 $50.000 $22.850
PAVEMENT SLER (RR XING)
EA 1.000 $150.000 $1.000 $400.000 $400.000 $45.700
PAVEMENT SLER (YLD TRI)
EA 68.000 $5.000 $30.000 $10.000 $10.000 $17.140
REFL PAV MRK TY I (W)6"(BRK)(100MIL)
LF 3,166.000 $0.600 $0.500 $0.500 $0.500 $0.890
REFL PAV MRK TY I (W)6"(SLD)(100MIL)
LF 630,251.000 $0.600 $0.500 $0.500 $0.500 $0.590
REFL PAV MRK TY I (Y)6"(BRK)(100MIL)
LF 51,429.000 $0.600 $0.500 $0.500 $0.500 $0.640
REFL PAV MRK TY I (Y)6"(SLD)(100MIL)
LF 338,744.000 $0.600 $0.500 $0.500 $0.500 $0.590
PRFB RUMBLE STRIP (BLK)(1')(CENTERLINE)
LF 41,261.000 $4.000 $2.000 $4.000 $4.000 $4.570
REFL PAV MRKR TY I-C
EA 216.000 $3.000 $5.000 $6.000 $6.000 $5.710
REFL PAV MRKR TY II-A-A
EA 10,157.000 $4.000 $3.500 $4.500 $4.500 $4.000
REFL PAV MRKR TY II-C-R
EA 107.000 $5.000 $5.000 $6.000 $6.000 $5.710
ELIM EXT PM & MRKS (4")
LF 22,706.000 $0.600 $0.500 $0.500 $0.500 $0.570
ELIM EXT PM & MRKS (8")
LF 581.000 $1.500 $1.000 $2.000 $2.000 $0.690
ELIM EXT PM & MRKS (24")
LF 48.000 $2.000 $3.000 $5.000 $5.000 $4.570
ELIM EXT PM & MRKS (ARROW)
EA 5.000 $75.000 $80.000 $50.000 $50.000 $79.970
ELIM EXT PM & MRKS (WORD)
EA 5.000 $75.000 $80.000 $50.000 $50.000 $79.970
ELIM EXT PM & MRKS (36")(YLD TRI)
EA 68.000 $7.000 $20.000 $10.000 $10.000 $34.270
PAV SURF PREP FOR MRK (6")
LF 22,706.000 $0.350 $0.020 $0.010 $0.010 $0.050
PAV SURF PREP FOR MRK (24")
LF 48.000 $1.000 $0.020 $0.010 $0.010 $0.230
PAV SURF PREP FOR MRK (ARROW)
EA 5.000 $2.000 $0.020 $0.010 $0.010 $34.270
PAV SURF PREP FOR MRK (WORD)
EA 5.000 $5.000 $0.020 $0.010 $0.010 $34.270
PAV SURF PREP FOR MRK (36")(YLD TRI)
EA 68.000 $5.000 $0.020 $0.010 $0.010 $22.850
Totals: $5,545,072.680 $4,828,838.850 $5,228,386.820 $6,406,426.280 $6,769,462.030
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) $1,000.00
LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) $50,000.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) $22,899.79
Total: $73,899.79