POLK CR (0911-04-094)

Items: 42

County: POLK
Length: N/A
Highway: CR
District: LUFKIN
Control Number: 0911-04-094
DBE Goal: 350.0%
Project: BR 2022(565)
Guaranty: N/A
Time: 405 WORKING DAYS
Engineer's Estimate: $3,615,026.50
Date: 05/03/2024 (2 years ago)
Contract Number: N/A
Type: BRIDGE REPLACEMENT
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (4)
E
Engineer's Estimate
$3,615,026.50
Over/Under Est: -1.88% -$67,963.70
Over/Under Est: 13.46% $486,722.82
Amt Left: 15.64% $554,686.52
$4,170,340.62
Over/Under Est: 15.36% $555,314.12
Amt Left: 17.57% $623,277.82
Delta: -1.67% -$68,591.30
Over/Under Est: 88.11% $3,185,062.46
Amt Left: 91.71% $3,253,026.16
Delta: -63.06% -$2,629,748.34
Subcontractor Percentage Amount
TRUE ROADS, LLC 39.91% $1,415,632.76
CARTHAGE DRILLING, LLC 12.59% $446,575.21
M & D FOUNDATION DRILLING INDUSTRIES, INC. 4.05% $143,656.04
ODUM SERVICES, LLC 4.04% $143,301.34
J. H. ODEN CONTRACTING COMPANY 1.13% $40,081.81
FLEX SUPPLY, LLC 1.12% $39,727.10
Total: 62.84% $2,228,974.26

Bid Items & Bid Tabulations

42 Total 0 of 42
POLK  |  CR  |  LUFKIN  |  0911-04-094  |  05/03/2024  |  $3,615,026.50  |  BR 2022(565)  |  BRIDGE REPL  |  405 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
DCC CONSTRUCTION AND SERVICES, L.L.C.
LONGVIEW BRIDGE AND ROAD, LTD.
C. E. BARKER, LTD.
JAMES CONSTRUCTION GROUP, LLC
PREPARING ROW
STA 23.500 $3,000.000 $500.000 $8,000.000 $17,000.000 $28,500.000
REMOVING STAB BASE AND ASPH PAV (4")
SY 235.000 $10.000 $2.000 $8.500 $3.750 $10.740
EXCAVATION (ROADWAY)
CY 3,113.000 $25.000 $30.000 $25.000 $43.550 $18.870
EMBANKMENT (FINAL)(ORD COMP)(TY B)
CY 2,154.000 $25.000 $30.000 $35.000 $46.580 $39.030
FURNISHING AND PLACING TOPSOIL (4")
SY 10,764.000 $3.000 $2.000 $2.400 $3.220 $2.630
BOND FBR MTRX SEED (PERM)(RURAL)(SAND)
SY 10,764.000 $2.000 $1.000 $1.050 $2.140 $0.980
BONDED FBR MTRX SEED (TEMP)(WARM)
SY 5,383.000 $2.000 $1.000 $1.050 $1.080 $0.960
BONDED FBR MTRX SEED (TEMP)(COOL)
SY 5,383.000 $2.000 $1.000 $1.050 $1.080 $0.960
VEGETATIVE WATERING
MG 430.800 $25.000 $1.000 $20.000 $74.960 $100.000
FL BS (CMP IN PLC)(TY D GR 1-2 OR 5)6"
SY 4,894.000 $20.000 $75.000 $40.700 $62.910 $32.720
CEM STABIL BKFL
CY 338.800 $250.000 $80.000 $355.000 $235.580 $190.580
DRILL SHAFT (18 IN)
LF 272.000 $90.000 $240.000 $250.000 $248.660 $138.940
DRILL SHAFT (24 IN)
LF 996.000 $275.000 $275.000 $350.000 $277.350 $117.890
DRILL SHAFT (36 IN)
LF 1,016.000 $360.000 $350.000 $450.000 $337.490 $323.050
CL C CONC (ABUT)
CY 127.900 $2,000.000 $1,500.000 $1,540.000 $1,329.960 $2,500.000
CL C CONC (CAP)
CY 63.700 $2,200.000 $2,500.000 $1,540.000 $1,858.600 $3,000.000
CL C CONC (COLUMN)
CY 21.400 $2,700.000 $2,500.000 $1,540.000 $1,816.120 $4,000.000
REINF CONC SLAB
SF 6,630.000 $40.000 $29.000 $30.000 $23.720 $205.150
REINF CONC SLAB (SLAB BEAM)
SF 5,850.000 $40.000 $29.000 $23.250 $23.720 $200.000
PRESTR CONC SLAB BEAM (5SB15)
LF 1,109.600 $350.000 $245.000 $370.000 $317.440 $239.230
PRESTR CONC GIRDER (TX28)
LF 1,011.200 $300.000 $255.000 $290.000 $327.420 $274.000
RIPRAP (STONE PROTECTION)(18 IN)
CY 740.700 $250.000 $175.000 $300.000 $277.070 $195.400
RAIL (TY T631LS)
LF 1,132.000 $85.000 $100.000 $70.000 $32.120 $78.500
TYPE A JOINT
LF 420.000 $115.000 $50.000 $78.000 $37.480 $109.870
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
EA 4.000 $25,000.000 $50,000.000 $33,000.000 $32,124.750 $100,000.000
REMOV STR (PIPE)
EA 1.000 $5,000.000 $200.000 $1,000.000 $1,499.160 $3,378.400
MOBILIZATION
LS 1.000 $171,000.000 $300,000.000 $400,000.000 $400,000.000 $660,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 36.000 $2,500.000 $1,000.000 $3,000.000 $3,212.480 $1,322.350
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 280.000 $50.000 $20.000 $50.000 $37.480 $42.000
ROCK FILTER DAMS (REMOVE)
LF 280.000 $10.000 $1.000 $11.000 $13.390 $12.000
CONSTRUCTION PERIMETER FENCE
LF 419.000 $5.000 $20.000 $5.500 $4.690 $10.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 2,757.000 $5.000 $15.000 $3.300 $4.280 $4.250
TEMP SEDMT CONT FENCE (REMOVE)
LF 2,757.000 $1.000 $1.000 $1.100 $1.080 $0.650
MTL W-BEAM GD FEN (TIM POST)
LF 930.500 $35.000 $35.000 $30.250 $32.120 $24.500
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 8.000 $1,700.000 $1,550.000 $1,540.000 $1,284.990 $1,550.000
GUARDRAIL END TREATMENT (INSTALL)
EA 8.000 $3,500.000 $3,500.000 $3,135.000 $3,212.480 $3,100.000
WIRE FENCE (TY C)
LF 642.000 $20.000 $15.000 $34.000 $21.420 $20.000
WIRE FENCE (WATER GAP)
LF 229.000 $50.000 $20.000 $190.000 $149.920 $65.000
MAILBOX INSTALL-M (TWG-POST) TY 1
EA 1.000 $750.000 $250.000 $687.500 $535.410 $750.000
REMOVE SM RD SN SUP&AM
EA 16.000 $100.000 $50.000 $137.500 $128.500 $162.000
INSTL DEL ASSM (D-SW)SZ (BRF)GF1 (BI)
EA 24.000 $35.000 $50.000 $27.500 $21.420 $25.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 8.000 $30.000 $45.000 $41.250 $32.120 $35.000
Totals: $3,615,026.500 $3,547,062.800 $4,101,749.325 $4,170,340.661 $6,800,088.972