PREPARING ROW
|
STA
|
118.030
|
$3,244.310
|
$2,500.000
|
$2,717.000
|
$1,600.000
|
|
|
REMOVING CONC (RIPRAP)
|
SY
|
1,622.000
|
$20.950
|
$8.000
|
$11.000
|
$14.000
|
|
|
REMOVING CONC (DRIVEWAYS)
|
SY
|
2,762.000
|
$10.780
|
$15.000
|
$16.760
|
$18.000
|
|
|
REMOVING CONC (CURB OR CURB & GUTTER)
|
LF
|
5,262.000
|
$10.280
|
$5.500
|
$6.600
|
$6.000
|
|
|
REMOVING CONCRETE(MOW STRIP)
|
LF
|
548.000
|
$13.860
|
$7.000
|
$6.200
|
$15.000
|
|
|
REMOVING STAB BASE AND ASPH PAV(0"-16")
|
SY
|
51,347.000
|
$8.000
|
$5.000
|
$5.000
|
$6.000
|
|
|
EXCAVATION (ROADWAY)
|
CY
|
53,096.000
|
$11.980
|
$15.000
|
$4.500
|
$12.500
|
|
|
EXCAVATION (CHANNEL)
|
CY
|
316.000
|
$11.120
|
$20.000
|
$6.000
|
$19.000
|
|
|
EMBANKMENT (FINAL)(DENS CONT)(TY B)
|
CY
|
13,352.000
|
$14.450
|
$15.000
|
$6.000
|
$12.500
|
|
|
FURNISHING AND PLACING TOPSOIL (4")
|
SY
|
56,438.000
|
$0.540
|
$1.500
|
$2.600
|
$2.000
|
|
|
BLOCK SODDING
|
SY
|
15,467.000
|
$4.640
|
$5.000
|
$3.850
|
$4.200
|
|
|
BROADCAST SEED (PERM) (RURAL) (CLAY)
|
SY
|
40,971.000
|
$1.000
|
$0.160
|
$0.140
|
$0.150
|
|
|
BROADCAST SEED (TEMP) (WARM)
|
SY
|
42,512.000
|
$1.000
|
$0.140
|
$0.120
|
$0.130
|
|
|
BROADCAST SEED (TEMP) (COOL)
|
SY
|
42,512.000
|
$1.000
|
$0.140
|
$0.120
|
$0.130
|
|
|
VEGETATIVE WATERING
|
MG
|
1,023.000
|
$32.280
|
$20.000
|
$28.000
|
$35.000
|
|
|
SOIL RETENTION BLANKETS (CL 1) (TY A)
|
SY
|
40,971.000
|
$2.000
|
$1.250
|
$0.850
|
$1.000
|
|
|
VEGETATION BARRIER
|
SY
|
18.000
|
$2.040
|
$25.000
|
$5.000
|
$50.000
|
|
|
FL BS (CMP IN PLACE)(TY A GR 1-2)(10")
|
SY
|
74,031.000
|
$21.000
|
$17.000
|
$16.000
|
$13.500
|
|
|
LIME TRT (EXST MATL) (12")
|
SY
|
78,404.000
|
$3.060
|
$5.000
|
$10.100
|
$3.700
|
|
|
LIME (HYD, COM, OR QK(SLURRY))
|
TON
|
2,116.000
|
$169.590
|
$200.000
|
$180.000
|
$190.000
|
|
|
PRIME COAT(MC-30 OR AE-P)
|
GAL
|
14,800.000
|
$4.620
|
$4.000
|
$4.000
|
$4.500
|
|
|
ASPH (CRS-2)
|
GAL
|
42,671.000
|
$2.690
|
$3.000
|
$2.650
|
$3.000
|
|
|
AGGR(TY-D GR-4 OR TY-L GR-4)
|
CY
|
527.000
|
$172.350
|
$125.000
|
$120.000
|
$185.000
|
|
|
PLANE ASPH CONC PAV(0" TO 4")
|
SY
|
9,157.000
|
$1.410
|
$2.500
|
$1.480
|
$2.400
|
|
|
CEM STABIL BKFL
|
CY
|
2,135.500
|
$100.000
|
$125.000
|
$145.000
|
$157.000
|
|
|
CUT & RESTORE ASPH PAVING
|
SY
|
141.000
|
$91.090
|
$70.000
|
$60.000
|
$127.000
|
|
|
TRENCH EXCAVATION PROTECTION
|
LF
|
11,909.000
|
$5.280
|
$5.000
|
$6.000
|
$6.500
|
|
|
TEMPORARY SPL SHORING
|
SF
|
1,410.000
|
$28.620
|
$25.000
|
$22.000
|
$30.000
|
|
|
DRILL SHAFT (24 IN)
|
LF
|
192.000
|
$227.350
|
$250.000
|
$306.000
|
$380.000
|
|
|
CL C CONC (ABUT)(EXTEND)
|
CY
|
18.100
|
$2,200.000
|
$3,000.000
|
$3,130.000
|
$2,250.000
|
|
|
CL C CONC (CAP)(EXTEND)
|
CY
|
4.500
|
$5,100.000
|
$3,000.000
|
$4,925.000
|
$5,750.000
|
|
|
CL C CONC (COLUMN)
|
CY
|
3.700
|
$1,573.360
|
$3,000.000
|
$4,325.000
|
$3,350.000
|
|
|
CL C CONC (HEADWALL)
|
CY
|
7.500
|
$831.770
|
$1,500.000
|
$800.000
|
$1,050.000
|
|
|
CL C CONC (RETAINING WALL)
|
CY
|
6.000
|
$897.440
|
$2,000.000
|
$2,630.000
|
$3,000.000
|
|
|
BRIDGE SIDEWALK
|
SF
|
1,510.000
|
$11.400
|
$15.000
|
$24.000
|
$16.700
|
|
|
APPROACH SLAB
|
CY
|
114.000
|
$469.760
|
$650.000
|
$1,025.000
|
$547.000
|
|
|
CONCRETE PAN GIRDER (EXTEND)
|
CY
|
67.900
|
$2,400.000
|
$1,500.000
|
$3,550.000
|
$2,600.000
|
|
|
CONC STR REPAIR (VERTICAL & OVERHEAD)
|
SF
|
10.200
|
$176.930
|
$550.000
|
$570.000
|
$500.000
|
|
|
RIPRAP (CONC)(5 IN)
|
CY
|
50.900
|
$423.690
|
$475.000
|
$650.000
|
$535.000
|
|
|
RIPRAP (STONE PROTECTION)(12 IN)
|
CY
|
410.000
|
$135.810
|
$120.000
|
$189.000
|
$205.000
|
|
|
RIPRAP (MOW STRIP)(4 IN)
|
CY
|
30.500
|
$316.160
|
$475.000
|
$500.000
|
$573.000
|
|
|
CLEANING AND SEALING EXIST JOINTS(CL3)
|
LF
|
306.000
|
$16.540
|
$60.000
|
$26.000
|
$36.000
|
|
|
RAIL (TY C2P)
|
LF
|
201.300
|
$325.000
|
$350.000
|
$518.000
|
$400.000
|
|
|
RAIL (TY PR11)
|
LF
|
279.000
|
$84.060
|
$175.000
|
$155.000
|
$135.000
|
|
|
RAIL (TY PR22)
|
LF
|
149.300
|
$98.410
|
$250.000
|
$306.000
|
$187.000
|
|
|
CONC BOX CULV (4 FT X 2 FT)
|
LF
|
1,122.000
|
$226.840
|
$240.000
|
$245.000
|
$266.000
|
|
|
CONC BOX CULV (5 FT X 2 FT)
|
LF
|
602.000
|
$250.120
|
$310.000
|
$326.000
|
$354.000
|
|
|
CONC BOX CULV (6 FT X 3 FT)
|
LF
|
150.000
|
$349.590
|
$420.000
|
$426.000
|
$463.000
|
|
|
CONC BOX CULV (8 FT X 4 FT)
|
LF
|
70.000
|
$585.930
|
$650.000
|
$610.000
|
$663.000
|
|
|
RC PIPE (CL III)(18 IN)
|
LF
|
573.000
|
$55.230
|
$65.000
|
$51.000
|
$55.000
|
|
|
RC PIPE (CL III)(24 IN)
|
LF
|
7,540.000
|
$96.950
|
$75.000
|
$62.000
|
$67.000
|
|
|
RC PIPE (CL III)(36 IN)
|
LF
|
5,428.000
|
$219.130
|
$125.000
|
$116.000
|
$126.000
|
|
|
RC PIPE (CL III)(48 IN)
|
LF
|
171.000
|
$176.520
|
$190.000
|
$188.000
|
$204.000
|
|
|
JCTBOX(COMPL)(PJB)(3FTX5FT)
|
EA
|
1.000
|
$4,209.940
|
$5,100.000
|
$4,134.000
|
$4,500.000
|
|
|
JCTBOX(COMPL)(PJB)(8FTX8FT)
|
EA
|
3.000
|
$13,981.420
|
$10,000.000
|
$8,832.000
|
$9,600.000
|
|
|
INLET (COMPL)(PCO)(3FT)(NONE)
|
EA
|
8.000
|
$5,049.980
|
$4,400.000
|
$3,207.000
|
$3,500.000
|
|
|
INLET (COMPL)(PCO)(3FT)(LEFT)
|
EA
|
27.000
|
$5,029.370
|
$5,000.000
|
$3,958.000
|
$4,300.000
|
|
|
INLET (COMPL)(PCO)(3FT)(RIGHT)
|
EA
|
9.000
|
$5,093.460
|
$4,700.000
|
$3,660.000
|
$4,000.000
|
|
|
INLET (COMPL)(PCO)(3FT)(BOTH)
|
EA
|
49.000
|
$6,500.000
|
$5,400.000
|
$4,462.000
|
$4,850.000
|
|
|
INLET (COMPL)(PCO)(4FT)(NONE)
|
EA
|
2.000
|
$5,346.200
|
$6,700.000
|
$5,566.000
|
$6,050.000
|
|
|
INLET (COMPL)(PCO)(4FT)(LEFT)
|
EA
|
2.000
|
$5,727.520
|
$5,900.000
|
$4,775.000
|
$5,200.000
|
|
|
INLET (COMPL)(PCO)(4FT)(RIGHT)
|
EA
|
7.000
|
$5,509.490
|
$6,500.000
|
$5,218.000
|
$5,700.000
|
|
|
INLET (COMPL)(PCO)(4FT)(BOTH)
|
EA
|
14.000
|
$6,405.170
|
$6,700.000
|
$5,433.000
|
$5,900.000
|
|
|
INLET (COMPL)(PCO)(6FT)(NONE)
|
EA
|
1.000
|
$5,831.900
|
$7,500.000
|
$6,096.000
|
$6,600.000
|
|
|
INLET (COMPL)(PCO)(6FT)(LEFT)
|
EA
|
1.000
|
$6,125.500
|
$7,600.000
|
$5,773.000
|
$6,300.000
|
|
|
INLET (COMPL)(PCO)(6FT)(BOTH)
|
EA
|
1.000
|
$9,356.260
|
$7,700.000
|
$6,287.000
|
$6,800.000
|
|
|
INLET (COMPL)(PCU)(3FT)(BOTH)
|
EA
|
1.000
|
$5,952.670
|
$6,000.000
|
$5,227.000
|
$5,600.000
|
|
|
INLET (COMPL)(PSL)(RC)(4FTX4FT)
|
EA
|
7.000
|
$4,725.360
|
$6,900.000
|
$5,854.000
|
$6,300.000
|
|
|
INLET (COMPL)(PSL)(RC)(5FTX5FT)
|
EA
|
1.000
|
$5,471.110
|
$8,700.000
|
$7,720.000
|
$8,300.000
|
|
|
INLET (COMPL)(PSL)(FG)(3FTX3FT-3FTX3FT)
|
EA
|
11.000
|
$4,220.350
|
$5,800.000
|
$3,904.000
|
$4,200.000
|
|
|
INLET (COMPL)(PSL)(FG)(4FTX4FT-4FTX4FT)
|
EA
|
6.000
|
$5,264.130
|
$7,200.000
|
$5,076.000
|
$5,500.000
|
|
|
INLET (COMPL)(JUNCTION BOX)(7' TO 10')
|
EA
|
1.000
|
$10,000.000
|
$10,000.000
|
$8,832.000
|
$9,600.000
|
|
|
HEADWALL (CH - PW - 0) (DIA= 48 IN)
|
EA
|
2.000
|
$10,801.320
|
$7,600.000
|
$8,476.000
|
$9,200.000
|
|
|
WINGWALL (PW - 1) (HW=6 FT)
|
EA
|
1.000
|
$18,854.530
|
$15,000.000
|
$10,225.000
|
$11,000.000
|
|
|
WINGWALL (PW - 1) (HW=7 FT)
|
EA
|
1.000
|
$12,439.330
|
$23,500.000
|
$14,000.000
|
$15,000.000
|
|
|
WINGWALL (PW - 1) (HW=8 FT)
|
EA
|
3.000
|
$28,640.530
|
$28,000.000
|
$18,500.000
|
$20,000.000
|
|
|
SET (TY II) (18 IN) (RCP) (6: 1) (P)
|
EA
|
10.000
|
$1,039.420
|
$1,050.000
|
$1,131.000
|
$1,200.000
|
|
|
ADJUSTING MANHOLES
|
EA
|
19.000
|
$1,166.180
|
$1,800.000
|
$594.000
|
$650.000
|
|
|
REMOV STR (BOX CULVERT)
|
EA
|
4.000
|
$7,784.380
|
$3,600.000
|
$1,137.000
|
$1,250.000
|
|
|
REMOV STR (MANHOLE)
|
EA
|
1.000
|
$642.440
|
$500.000
|
$1,365.000
|
$1,500.000
|
|
|
REMOV STR (SET)
|
EA
|
14.000
|
$2,500.000
|
$500.000
|
$853.000
|
$900.000
|
|
|
REMOV STR (WINGWALL)
|
EA
|
155.000
|
$1,600.000
|
$500.000
|
$300.000
|
$325.000
|
|
|
REMOV STR (PIPE)
|
EA
|
82.000
|
$345.380
|
$300.000
|
$430.000
|
$465.000
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$1,136,444.000
|
$1,500,000.000
|
$1,560,000.000
|
$1,590,000.000
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
34.000
|
$7,129.780
|
$10,725.000
|
$9,000.000
|
$7,500.000
|
|
|
ROCK FILTER DAMS (INSTALL) (TY 2)
|
LF
|
1,225.000
|
$25.120
|
$35.000
|
$28.000
|
$30.000
|
|
|
ROCK FILTER DAMS (REMOVE)
|
LF
|
1,225.000
|
$9.200
|
$3.000
|
$9.000
|
$9.000
|
|
|
CONSTRUCTION EXITS (INSTALL) (TY 1)
|
SY
|
448.000
|
$10.000
|
$25.000
|
$24.000
|
$16.000
|
|
|
CONSTRUCTION EXITS (REMOVE)
|
SY
|
448.000
|
$5.870
|
$3.000
|
$11.000
|
$4.000
|
|
|
TEMP SEDMT CONT FENCE (INSTALL)
|
LF
|
11,828.000
|
$3.620
|
$3.000
|
$2.850
|
$6.000
|
|
|
TEMP SEDMT CONT FENCE (REMOVE)
|
LF
|
11,828.000
|
$1.150
|
$0.500
|
$0.750
|
$0.750
|
|
|
CONSTRUCTING DETOURS
|
SY
|
12,765.000
|
$46.890
|
$75.000
|
$80.000
|
$95.000
|
|
|
PORT CTB (DES SOURCE)(LOW PROF)(TY 1)
|
LF
|
10,040.000
|
$42.700
|
$12.000
|
$10.000
|
$13.600
|
|
|
PORT CTB (DES SOURCE)(LOW PROF)(TY 2)
|
LF
|
2,000.000
|
$9.720
|
$12.000
|
$21.000
|
$13.600
|
|
|
PORT CTB (MOVE)(LOW PROF)(TY 1)
|
LF
|
12,300.000
|
$3.840
|
$6.000
|
$5.000
|
$11.750
|
|
|
PORT CTB (MOVE)(LOW PROF)(TY 2)
|
LF
|
3,260.000
|
$3.780
|
$6.000
|
$14.000
|
$11.750
|
|
|
PORT CTB (STKPL)(LOW PROF)(TY 1)
|
LF
|
10,040.000
|
$4.760
|
$8.000
|
$9.000
|
$13.000
|
|
|
PORT CTB (STKPL)(LOW PROF)(TY 2)
|
LF
|
2,000.000
|
$4.840
|
$8.000
|
$19.000
|
$13.000
|
|
|
CONC CURB & GUTTER (TY II)
|
LF
|
23,695.000
|
$19.300
|
$20.000
|
$20.000
|
$22.500
|
|
|
CONC CURB (TY C1)
|
LF
|
364.000
|
$111.080
|
$100.000
|
$35.000
|
$200.000
|
|
|
INTERSECTIONS (ACP)
|
SY
|
8,284.000
|
$34.000
|
$75.000
|
$80.000
|
$100.000
|
|
|
DRIVEWAYS (CONC)
|
SY
|
3,527.000
|
$54.220
|
$95.000
|
$80.000
|
$100.000
|
|
|
CONC SIDEWALKS (6")
|
SY
|
2,705.000
|
$58.130
|
$68.500
|
$60.000
|
$65.000
|
|
|
CURB RAMPS (TY 2)
|
EA
|
2.000
|
$1,700.000
|
$2,000.000
|
$1,300.000
|
$2,450.000
|
|
|
CURB RAMPS (TY 7)
|
EA
|
2.000
|
$1,791.630
|
$2,000.000
|
$1,300.000
|
$2,450.000
|
|
|
CURB RAMPS (TY 10)
|
EA
|
8.000
|
$1,495.390
|
$1,500.000
|
$1,700.000
|
$2,450.000
|
|
|
MTL W-BEAM GD FEN (STEEL POST)
|
LF
|
350.000
|
$25.560
|
$45.000
|
$28.000
|
$39.000
|
|
|
MTL BEAM GD FEN TRANS (THRIE-BEAM)
|
EA
|
8.000
|
$1,914.080
|
$2,500.000
|
$2,050.000
|
$3,100.000
|
|
|
REMOVE METAL BEAM GUARD FENCE
|
LF
|
525.000
|
$2.100
|
$3.000
|
$2.000
|
$2.150
|
|
|
RM MTL BM GD FENCE TRANS (THRIE-BEAM)
|
EA
|
8.000
|
$178.000
|
$250.000
|
$200.000
|
$217.000
|
|
|
GUARDRAIL END TREATMENT (INSTALL)
|
EA
|
8.000
|
$2,740.230
|
$3,500.000
|
$2,700.000
|
$3,300.000
|
|
|
GUARDRAIL END TREATMENT (REMOVE)
|
EA
|
8.000
|
$211.000
|
$250.000
|
$200.000
|
$217.000
|
|
|
MAILBOX INSTALL-S (WC-POST) TY 3
|
EA
|
27.000
|
$220.000
|
$300.000
|
$200.000
|
$215.000
|
|
|
MAILBOX INSTALL-D (WC-POST) TY 3
|
EA
|
1.000
|
$199.110
|
$400.000
|
$250.000
|
$270.000
|
|
|
ALUMINUM SIGNS (TY A)
|
SF
|
20.000
|
$58.000
|
$30.000
|
$50.000
|
$54.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
|
EA
|
28.000
|
$585.710
|
$600.000
|
$600.000
|
$650.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
|
EA
|
42.000
|
$620.990
|
$700.000
|
$700.000
|
$760.000
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(U-1EXT)
|
EA
|
1.000
|
$973.360
|
$1,200.000
|
$800.000
|
$870.000
|
|
|
RELOCATE SM RD SN SUP&AM TY 10BWG
|
EA
|
10.000
|
$150.000
|
$650.000
|
$400.000
|
$430.000
|
|
|
REMOVE SM RD SN SUP&AM
|
EA
|
62.000
|
$81.400
|
$100.000
|
$150.000
|
$150.000
|
|
|
RELOCATE SM RD SN SUP & AM TY TEMP
|
EA
|
3.000
|
$228.000
|
$500.000
|
$200.000
|
$215.000
|
|
|
INSTL OM ASSM (OM-2Y)(WC)GND
|
EA
|
18.000
|
$106.380
|
$75.000
|
$100.000
|
$108.000
|
|
|
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
|
LF
|
20,310.000
|
$0.180
|
$0.350
|
$0.300
|
$0.330
|
|
|
WK ZN PAV MRK NON-REMOV (W)24"(SLD)
|
LF
|
418.000
|
$2.670
|
$4.000
|
$3.000
|
$3.260
|
|
|
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
|
LF
|
39,451.000
|
$0.180
|
$0.350
|
$0.300
|
$0.330
|
|
|
WK ZN PAV MRK REMOV (REFL) TY I-C
|
EA
|
1,088.000
|
$3.370
|
$4.000
|
$3.200
|
$3.480
|
|
|
WK ZN PAV MRK REMOV (REFL) TY II-A-A
|
EA
|
3,217.000
|
$4.120
|
$4.000
|
$3.200
|
$3.480
|
|
|
WK ZN PAV MRK REMOV (W)4"(BRK)
|
LF
|
1,176.000
|
$0.830
|
$1.500
|
$1.000
|
$1.090
|
|
|
WK ZN PAV MRK REMOV (W)4"(SLD)
|
LF
|
22,500.000
|
$0.620
|
$0.650
|
$0.600
|
$0.650
|
|
|
WK ZN PAV MRK REMOV (W)8"(SLD)
|
LF
|
247.000
|
$0.860
|
$1.500
|
$1.000
|
$1.090
|
|
|
WK ZN PAV MRK REMOV (Y)4"(SLD)
|
LF
|
64,339.000
|
$0.590
|
$0.650
|
$0.600
|
$0.650
|
|
WK ZN PAV MRK SHT TERM (TAB)TY W
|
EA
|
1,191.000
|
$1.010
|
$1.500
|
$1.140
|
$1.400
|
|
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
|
EA
|
1,469.000
|
$1.060
|
$1.500
|
$1.140
|
$1.400
|
|
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
|
LF
|
1,772.000
|
$0.860
|
$1.500
|
$1.000
|
$1.090
|
|
REFL PAV MRK TY I (W)12"(SLD)(100MIL)
|
LF
|
463.000
|
$4.200
|
$4.000
|
$3.500
|
$3.800
|
|
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
|
LF
|
554.000
|
$5.450
|
$6.500
|
$6.000
|
$6.520
|
|
REFL PAV MRK TY II (W) 8" (DOT)
|
LF
|
75.000
|
$1.000
|
$2.000
|
$1.000
|
$1.090
|
|
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
|
LF
|
20,774.000
|
$0.660
|
$0.600
|
$0.500
|
$0.540
|
|
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
|
LF
|
3,630.000
|
$0.810
|
$0.600
|
$0.500
|
$0.540
|
|
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
|
LF
|
26,497.000
|
$0.640
|
$0.600
|
$0.500
|
$0.540
|
|
PREFAB PAV MRK TY C (W) (ARROW)
|
EA
|
16.000
|
$220.680
|
$250.000
|
$190.000
|
$206.000
|
|
PREFAB PAV MRK TY C (W) (WORD)
|
EA
|
8.000
|
$311.120
|
$300.000
|
$230.000
|
$250.000
|
|
PREFAB PAV MRK TY C (W) (RR XING)
|
EA
|
1.000
|
$700.000
|
$1,000.000
|
$750.000
|
$815.000
|
|
PREFAB PAV MRK TY C (W) (36")(YLD TRI)
|
EA
|
24.000
|
$39.780
|
$70.000
|
$55.000
|
$60.000
|
|
REFL PAV MRKR TY I-C
|
EA
|
63.000
|
$2.730
|
$5.000
|
$4.000
|
$4.350
|
|
REFL PAV MRKR TY II-A-A
|
EA
|
1,010.000
|
$2.630
|
$4.000
|
$3.500
|
$3.800
|
|
REFL PAV MRKR TY II-C-R
|
EA
|
14.000
|
$3.890
|
$5.000
|
$4.000
|
$4.350
|
|
|
ELIM EXT PAV MRK & MRKS (4")
|
LF
|
34,325.000
|
$0.550
|
$0.500
|
$0.450
|
$0.490
|
|
|
ELIM EXT PAV MRK & MRKS (24")
|
LF
|
599.000
|
$3.290
|
$4.000
|
$3.000
|
$3.260
|
|
|
ELIM EXT PAV MRK & MRKS (ARROW)
|
EA
|
4.000
|
$76.310
|
$150.000
|
$100.000
|
$108.000
|
|
|
ELIM EXT PAV MRK & MRKS (WORD)
|
EA
|
4.000
|
$114.320
|
$150.000
|
$100.000
|
$108.000
|
|
|
INSTL RDSD FLSH BCN ASSM (SOLAR PWRD)
|
EA
|
2.000
|
$5,924.280
|
$10,000.000
|
$14,000.000
|
$12,000.000
|
|
|
REMOV RDSD FLSH BCN AM (SOLAR PWRD)
|
EA
|
2.000
|
$588.860
|
$1,000.000
|
$1,600.000
|
$2,000.000
|
|
|
MEMBRANE UNDERSEAL
|
GAL
|
2,001.000
|
$3.250
|
$3.000
|
$3.150
|
$3.250
|
|
|
D-GR HMA TY-B SAC-B PG64-22
|
TON
|
14,351.000
|
$85.180
|
$75.000
|
$96.000
|
$84.000
|
|
|
SP MIXES SP-C SAC-B PG70-22
|
TON
|
7,869.000
|
$86.840
|
$80.000
|
$120.000
|
$99.000
|
|
|
BONDING COURSE
|
GAL
|
17,885.000
|
$3.150
|
$3.000
|
$0.010
|
$3.250
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
DAY
|
30.000
|
$67.510
|
$150.000
|
$135.000
|
$175.000
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
EA
|
2.000
|
$7,855.120
|
$12,000.000
|
$18,400.000
|
$10,000.000
|
|
|
TMA (STATIONARY)
|
DAY
|
26.000
|
$90.560
|
$250.000
|
$240.000
|
$500.000
|
|
|
TMA (MOBILE OPERATION)
|
HR
|
72.000
|
$167.180
|
$75.000
|
$24.000
|
$85.000
|
|
|
CURB INLET SEDIMENT PROTECTION
|
LF
|
2,130.000
|
$3.000
|
$8.000
|
$32.180
|
$25.000
|
|
Totals: |
$15,388,382.986
|
$15,387,558.270
|
$15,603,362.510
|
$15,983,915.940
|