LIBERTY FM 1413 (1421-01-027)
Items: 67
County: LIBERTY
Length: 7.7890 MILES
Highway: FM 1413
District: BEAUMONT
Control Number: 1421-01-027
DBE Goal: 0.0%
Project: STP 2026(498)MM
Guaranty: $100,000.00
Time: 169 WORKING DAYS
Engineer's Estimate: $6,892,326.85
Date: 1:00 PM JULY 02, 2026 (in 22 days)
Contract Number: 7263240
Type: HAZARD ELIMINATION & SAFETY
Project ID: A00180186
Contract Type: Federal
Project Description: FM 1413-2020 HSIP (SAFETY TREAT FIXED OBJECTS, MILLED EDGELINE RUMBLE STRIPS)
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
ROBERTO RODRIGUEZ
ROBERTO M RODRIGUEZ
JOHN SERNA
LIBERTY FM 1413 (1421-01-027)
Project Name: N/A
Project: STP 2026(498)MM
Length: 2.3100 MILES
Project Type: CONSTRUCTION
Limits From: US 90, SOUTH
Limits To: HATCHERVILLE ROAD (CR 486)
Project Description: FM 1413-2020 HSIP (SAFETY TREAT FIXED OBJECTS, MILLED EDGELINE RUMBLE STRIPS)
LIBERTY FM 1413 (1421-01-028)
Project Name: FM 1413-(US 90-SH 146) FDBR, OVERLAY
Project: STP 2026(498)MM
Length: 5.4790 MILES
Project Type: RESTORATION
Limits From: US 90, SOUTH
Limits To: SH 146
Project Description: FM 1413-(US 90, SOUTH TO SH 146) FULL DEPTH BASE REPAIR, AND OVERLAY
Bid Items & Bid Tabulations
67
Total
0 of 67
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
| Description | Amount |
|---|---|
| EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) | $5,000.00 |
| SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) | $5,000.00 |
| Total: | $10,000.00 |