LA SALLE IH 35 (0018-02-091)

Items: 97

County: LA SALLE
Length: N/A
Highway: IH 35
District: LAREDO
Control Number: 0018-02-091
DBE Goal: 0.0%
Project: C 18-2-91
Guaranty: N/A
Time: 198 WORKING DAYS
Engineer's Estimate: $30,359,847.66
Date: 03/06/2024 (2 years ago)
Contract Number: N/A
Type: RESURFACE ROADWAY
Mail/Deliver Bids To: N/A
CYNTHIA GARCIA
ANGEL MARTINEZ
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (2)
E
Engineer's Estimate
$30,359,847.66
$31,549,072.31
Over/Under Est: 3.92% $1,189,224.65
$35,574,335.72
Over/Under Est: 17.18% $5,214,488.06
Amt Left: 12.76% $4,025,263.41
Subcontractor Percentage Amount
K. L. DURHAM CONSTRUCTION, L.L.C. 4.04% $1,339,393.28
HIGHWAY BARRICADES AND SERVICES, LLC 1.96% $649,804.66
DEPENDABLE FENCE 1.42% $470,776.85
RC CONTRACT SERVICES LLC 1.41% $467,461.52
CHEROKEE SERVICES 0.27% $89,513.91
PROFESSIONAL TRAFFIC CONTROL LLC 0.05% $16,576.65
RPV CONSTRUCTION, LLC 0.05% $16,576.65
TEXAS ICON CONSTRUCTION, LLC 0.04% $13,261.32
SOUTHWEST ROAD & SAFETY CONTRACTORS, LTD. 0.03% $9,945.99
Total: 9.27% $3,073,310.83

Bid Items & Bid Tabulations

97 Total 0 of 97
LA SALLE  |  IH 35  |  LAREDO  |  0018-02-091  |  03/06/2024  |  $30,359,847.66  |  C 18-2-91  |  RESURF ROADWAY  |  198 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
ANDERSON COLUMBIA CO., INC.
HUNTER INDUSTRIES, LTD.
REMOVING CONC (RIPRAP)
CY 78.800 $140.000 $120.000 $115.500
REMOVING CONC (CURB AND GUTTER)
LF 470.000 $25.000 $11.000 $10.500
BACKFILL (TY B)
STA 778.814 $100.000 $120.000 $157.500
BLADING
HR 15.000 $170.000 $160.000 $132.000
FOG SEAL (CSS-1H)
GAL 11,557.000 $9.000 $5.500 $4.980
FLEXIBLE PAVEMENT STRUCTURE REPAIR(5")
SY 60,738.000 $32.000 $39.000 $44.950
FLEXIBLE PAVEMENT STRUCTURE REPAIR(8")
SY 2,274.000 $45.000 $66.000 $89.930
FLEXIBLE PAVEMENT STRUCTURE REPAIR(4")
SY 36,106.000 $25.000 $32.000 $40.210
FLEXIBLE PAVEMENT STRUCTURE REPAIR(3")
SY 28,232.000 $20.000 $24.000 $32.680
PLANE ASPH CONC PAV (2")
SY 37,102.000 $3.000 $2.300 $2.110
PLANE ASPH CONC PAV (3")
SY 357,258.000 $2.500 $3.400 $2.880
PLANE ASPH CONC PAV (2 1/2")
SY 309,351.000 $2.250 $2.900 $2.660
PLANE ASPH CONC PAV(4.5")
SY 1,335.000 $7.000 $6.100 $6.840
PLANE ASPH CONC PAV (2" TO 4 1/2")
SY 1,780.000 $3.500 $6.100 $4.640
PLANE ASPH CONC PAV(MICRO)(0"-3")
SY 2,158.000 $10.000 $28.000 $4.640
CL C CONC (RAIL FOUNDATION)(HPC)
CY 52.000 $1,100.000 $750.000 $1,300.000
RIPRAP (CONC)(5 IN)
CY 61.700 $450.000 $600.000 $1,000.000
RIPRAP (CONC)(6 IN)
CY 101.490 $495.000 $620.000 $835.000
RIPRAP (CONC)(CL B)
CY 101.000 $700.000 $620.000 $850.000
RIPRAP (MOW STRIP)(4 IN)
CY 281.000 $400.000 $520.000 $950.000
CLEANING AND SEALING EXISTING JOINTS
LF 3,495.600 $33.000 $28.000 $30.800
RAIL (TY SSTR) (HPC) (MOD)
LF 412.500 $120.000 $280.000 $187.000
RETROFIT RAIL (ADD HSS)
LF 726.750 $115.000 $110.000 $109.540
MOBILIZATION
LS 1.000 $2,991,939.070 $2,550,000.000 $2,936,794.300
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 10.000 $2,500.000 $9,000.000 $12,367.690
BIODEG EROSN CONT LOGS (INSTL) (8")
LF 1,200.000 $5.000 $8.000 $8.500
BIODEG EROSN CONT LOGS (REMOVE)
LF 1,200.000 $2.000 $4.000 $2.000
ONE-WAY TRAF CONT (FLAGGER CONT)
HR 1,190.000 $82.000 $68.000 $132.000
ONE-WAY TRAF CONT (PILOT CAR)
HR 120.000 $150.000 $170.000 $174.000
PTB (FRN&INSTL)(SGL SLP)(TY 1) OR (STL)
LF 600.000 $90.000 $39.000 $95.000
PTB (REMOVE)(SGL SLP)(TY 1) OR (STL)
LF 600.000 $60.000 $39.000 $30.000
CONC CURB (MONO) (TY II)
LF 844.560 $21.000 $22.000 $30.000
CONC CURB (DOWEL) (TY II)
LF 1,203.000 $16.000 $25.000 $22.000
RUMBLE STRIPS (SHOULDER) ASPHALT
LF 81,788.000 $0.200 $0.100 $0.260
RUMBLE STRIPS (CENTERLINE) ASPHALT
LF 40,895.000 $0.200 $0.100 $0.300
MTL W-BEAM GD FEN (TIM POST)
LF 4,700.000 $30.000 $25.000 $23.990
MTL W-BEAM GD FEN (STEEL POST)
LF 50.000 $48.000 $30.000 $29.510
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 24.000 $1,800.000 $2,900.000 $2,798.250
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 17.000 $1,250.000 $1,750.000 $1,701.000
MTL BM GD FEN TRANS (NON - SYM)
EA 7.000 $1,000.000 $770.000 $756.000
MTL W - BEAM GD FEN (LOW FILL CULVERT)
LF 75.000 $85.000 $110.000 $106.790
REMOVE METAL BEAM GUARD FENCE
LF 3,938.000 $2.000 $3.200 $3.150
REMOVE TERMINAL ANCHOR SECTION
EA 3.000 $180.000 $216.000 $210.000
REMOVE DOWNSTREAM ANCHOR TERMINAL
EA 4.000 $250.000 $216.000 $210.000
RM MTL BM GD FENCE TRANS (THRIE-BEAM)
EA 21.000 $250.000 $216.000 $210.000
GUARDRAIL END TREATMENT (INSTALL)
EA 18.000 $3,200.000 $3,500.000 $3,354.750
GUARDRAIL END TREATMENT (REMOVE)
EA 20.000 $250.000 $215.000 $210.000
CRASH CUSH ATTEN (REMOVE)
EA 1.000 $2,500.000 $850.000 $840.000
CRASH CUSH ATTEN (INSTL)(L)(N)(TL3)
EA 1.000 $35,000.000 $34,400.000 $35,894.780
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
EA 1.000 $10,000.000 $8,750.000 $8,505.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 6.000 $700.000 $1,200.000 $1,100.000
IN SM RD SN SUP&AM TY10BWG(2)SA(P)
EA 1.000 $1,250.000 $2,100.000 $1,950.000
REMOVE SM RD SN SUP&AM
EA 6.000 $125.000 $135.000 $125.000
REMOVE DELIN & OBJECT MARKER ASSMS
EA 134.000 $16.500 $54.000 $50.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
EA 58.000 $30.000 $47.000 $45.410
INSTL DEL ASSM (D-SY)SZ 1(BRF)GF2
EA 19.000 $27.000 $47.000 $45.410
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BR)
EA 55.000 $30.000 $26.000 $25.410
INSTL DEL ASSM (D-SY)SZ (BRF)CTB (BR)
EA 9.000 $36.000 $26.000 $25.410
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 34,566.000 $1.800 $1.700 $1.630
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 7,292.000 $1.800 $1.700 $1.630
REFL PAV MRK TY I (W)6"(DOT)(100MIL)
LF 500.000 $0.850 $0.650 $0.600
REFL PAV MRK TY I (W)8"(DOT)(100MIL)
LF 5,276.000 $1.250 $0.950 $0.880
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 27,806.000 $1.300 $0.800 $0.740
REFL PAV MRK TY I (W)12"(SLD)(100MIL)
LF 6,435.000 $2.500 $2.000 $2.000
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 1,846.000 $11.000 $8.000 $7.000
REFL PAV MRK TY I (W)(ARROW)(100MIL)
EA 200.000 $110.000 $108.000 $100.000
REFL PAV MRK TY I (W)(WORD)(100MIL)
EA 148.000 $200.000 $162.000 $150.000
REFL PAV MRK TY I (W)(RR XING)(100MIL)
EA 2.000 $400.000 $540.000 $500.000
REF PAV MRK TY I(W)36"(YLD TRI)(100MIL)
EA 52.000 $30.000 $27.000 $25.000
RE PV MRK TY I(BLACK)6"(SHADOW)(100MIL)
LF 2,010.000 $1.100 $1.300 $1.200
PAVEMENT SEALER 6"
LF 28,074.000 $0.400 $0.300 $0.280
RE PM W/RET REQ TY I (W)6"(BRK)(100MIL)
LF 63,776.000 $0.580 $0.650 $0.600
RE PM W/RET REQ TY I (W)6"(SLD)(100MIL)
LF 300,532.000 $0.750 $0.650 $0.600
RE PM W/RET REQ TY I (Y)6"(BRK)(100MIL)
LF 6,835.000 $0.580 $0.650 $0.600
RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL)
LF 307,729.000 $0.750 $0.650 $0.600
REFL PAV MRK TY I (W)12"(DOT)(100MIL)
LF 475.000 $2.700 $1.300 $1.200
REFL PAV MRKR TY I-C
EA 3,995.000 $5.000 $5.400 $5.000
REFL PAV MRKR TY II-A-A
EA 2,435.000 $5.100 $5.400 $5.000
REFL PAV MRKR TY II-C-R
EA 951.000 $5.800 $5.400 $5.000
ELIM EXT PAV MRK & MRKS (4")
LF 27,355.000 $0.980 $0.400 $0.350
ELIM EXT PAV MRK & MRKS (8")
LF 525.000 $1.800 $0.800 $0.750
ELIM EXT PAV MRK & MRKS (12")
LF 2,630.000 $2.250 $1.000 $1.000
ELIM EXT PAV MRK & MRKS (24")
LF 617.000 $3.500 $4.300 $4.000
PAV SURF PREP FOR MRK (6")
LF 37,447.000 $0.050 $0.110 $0.100
CONCRETE RAIL REPAIR (IN-KIND)
LF 6.000 $350.000 $720.000 $1,100.000
D-GR HMA TY-C SAC-A PG76-22
TON 40,024.000 $138.000 $128.000 $119.150
D-GR HMA TY-D PG70-22 (LEVEL-UP)
TON 3,143.000 $145.000 $129.000 $113.700
SP MIXES SP-C SAC-A PG76-22
TON 24,275.000 $128.000 $131.000 $149.500
STONE-MTRX-ASPH SMA-C SAC-A PG76-22
TON 74,649.000 $130.000 $144.000 $173.700
STONE-MTRX-ASPH SMA-D SAC-A PG76-22
TON 179.000 $200.000 $415.000 $175.700
BONDING COURSE
GAL 190,922.000 $4.000 $1.720 $3.780
PORTABLE CHANGEABLE MESSAGE SIGN
EA 4.000 $15,000.000 $15,506.750 $9,201.250
LONG CHANNEL MOUNT CURB SYS (INSTALL)
LF 645.000 $90.000 $105.000 $105.000
LONG CHANNEL MOUNT CURB SYS (REMOVE)
LF 1,248.000 $6.500 $7.000 $7.500
TMSP RADAR SPEED CONTROL MONITOR
EA 2.000 $9,510.000 $10,700.000 $10,825.000
TMA (STATIONARY)
DAY 220.000 $260.000 $186.000 $250.000
TMA (MOBILE OPERATION)
HR 1,550.000 $60.000 $67.000 $120.000
Totals: $30,359,847.660 $31,549,072.310 $35,574,335.730