KENDALL RM 1376 (1899-02-021)

Items: 103

County: KENDALL
Length: N/A
Highway: RM 1376
District: SAN ANTONIO
Control Number: 1899-02-021
DBE Goal: N/A
Project: STP 2023(956)VRU
Guaranty: N/A
Time: 160 WORKING DAYS
Engineer's Estimate: $5,986,126.27
Date: 06/27/2023 (2 years ago)
Contract Number: N/A
Type: HAZARD ELIMINATION & SAFETY
Mail/Deliver Bids To: N/A
ANDRES GONZALEZ
JOSE C MENDEZ
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (5)
E
Engineer's Estimate
$5,986,126.27
$5,653,830.45
Over/Under Est: -5.55% -$332,295.82
$6,135,556.65
Over/Under Est: 2.5% $149,430.38
Amt Left: 8.52% $481,726.20
$7,134,352.15
Over/Under Est: 19.18% $1,148,225.88
Amt Left: 26.19% $1,480,521.70
Delta: -16.28% -$998,795.50
Over/Under Est: 19.55% $1,170,577.35
Amt Left: 26.58% $1,502,873.17
Delta: -0.31% -$22,351.47
Over/Under Est: 56.43% $3,378,046.91
Amt Left: 65.63% $3,710,342.73
Delta: -30.84% -$2,207,469.56
Subcontractor Percentage Amount
STX CIVIL 10.58% $603,871.98
A K FUQUAY CONSTRUCTION 5.74% $327,620.52
TRP CONSTRUCTION GROUP, LLC 3.46% $197,485.54
ROADWAY SPECIALTIES, INC. 2.23% $127,281.14
FLASHER EQUIPMENT COMPANY 1.71% $97,601.24
EGGEMEYER LAND CLEARING, LLC 0.48% $27,396.84
THE LEVY COMPANY, INC. 0.22% $12,556.88
Total: 24.42% $1,393,814.14

Bid Items & Bid Tabulations

103 Total 0 of 103
KENDALL  |  RM 1376  |  SAN ANTONIO  |  1899-02-021  |  06/27/2023  |  $5,986,126.27  |  STP 2023(956)VRU  |  HAZARD ELIM & SAFETY  |  160 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
HUNTER INDUSTRIES, LTD.
ALLEN KELLER COMPANY
CK NEWBERRY, LLC
ACME BRIDGE COMPANY, INC.
TEXAS MATERIALS GROUP, INC.
PREPARING ROW
STA 158.500 $1,000.000 $594.310 $1,500.000 $500.000 $2,120.000 $1,900.000
REMOVING CONC (RIPRAP)
SY 90.000 $20.000 $24.500 $24.750 $30.000 $37.100 $38.000
REMOVING STAB BASE AND ASPH PAV (6")
SY 758.000 $8.000 $7.000 $11.750 $15.000 $11.500 $20.000
REMOVING STAB BASE AND ASPH PAV(8")
SY 18,623.000 $10.000 $5.700 $4.050 $15.000 $3.650 $29.000
EXCAVATION (ROADWAY)
CY 16,542.000 $16.000 $23.600 $13.750 $22.000 $23.800 $65.000
EMBANKMENT (FINAL)(ORD COMP)(TY C)
CY 8,709.000 $25.000 $21.100 $6.550 $23.000 $22.800 $54.000
EMBANKMENT (FINAL)(ORD COMP)(TY C1)
CY 1,376.000 $100.000 $56.340 $76.500 $85.000 $96.400 $103.000
FURNISHING AND PLACING TOPSOIL (4")
SY 81,092.000 $1.250 $1.570 $1.000 $2.000 $3.220 $4.660
DRILL SEEDING (PERM) (RURAL) (CLAY)
SY 81,092.000 $0.350 $0.300 $0.300 $0.400 $0.330 $0.300
DRILL SEED (TEMP)(WARM OR COOL)
SY 81,092.000 $0.250 $0.200 $0.200 $0.200 $0.220 $0.200
VEGETATIVE WATERING
MG 2,530.600 $25.000 $24.500 $14.000 $18.000 $33.100 $35.000
SOIL RETENTION BLANKETS (CL 1) (TY A)
SY 81,092.000 $1.100 $1.750 $1.700 $2.000 $1.100 $1.750
PROOF ROLLING
HR 45.000 $160.000 $108.000 $133.000 $100.000 $91.700 $160.000
AGGR(TY-PD GR-4 SAC-B)
CY 529.000 $210.000 $134.820 $145.000 $200.000 $201.000 $145.000
ASPH (AC-15P, AC-20-5TR OR AC-20XP)
GAL 31,616.000 $5.500 $5.030 $5.350 $6.000 $5.100 $5.000
AGGR (TY-PB GR-4)
CY 350.000 $200.000 $134.720 $185.000 $225.000 $201.000 $265.000
CUT & RESTORING PAV
SY 258.000 $125.000 $120.000 $226.000 $125.000 $140.000 $205.000
FLOWABLE BACKFILL
CY 36.000 $400.000 $212.300 $160.000 $240.000 $334.000 $300.000
TRENCH EXCAVATION PROTECTION
LF 470.000 $100.000 $8.660 $11.250 $10.000 $34.500 $31.000
RIPRAP (CONC)(4 IN)
CY 24.500 $600.000 $616.640 $489.000 $675.000 $947.000 $850.000
RIPRAP (MOW STRIP)(4 IN)
CY 96.000 $680.000 $550.000 $969.000 $700.000 $752.000 $675.000
GABION MATTRESSES (GALV)(12 IN)
SY 192.000 $100.000 $115.850 $106.000 $200.000 $89.100 $110.000
CONC BOX CULV (5 FT X 5 FT)
LF 135.000 $800.000 $651.410 $824.000 $725.000 $1,280.000 $1,150.000
CONC BOX CULV (7 FT X 5 FT)
LF 70.000 $1,200.000 $970.100 $1,310.000 $1,100.000 $1,960.000 $1,755.000
RC PIPE (CL III)(18 IN)
LF 254.000 $100.000 $84.980 $84.750 $95.000 $150.000 $135.000
RC PIPE (CL III)(24 IN)
LF 190.000 $150.000 $108.330 $107.000 $120.000 $284.000 $255.000
RC PIPE (CL III)(36 IN)
LF 280.000 $200.000 $192.740 $160.000 $215.000 $407.000 $365.000
RC PIPE (CL III)(42 IN)
LF 88.000 $300.000 $247.400 $199.000 $275.000 $490.000 $440.000
RC PIPE (CL III)(48 IN)
LF 86.000 $350.000 $296.760 $228.000 $300.000 $496.000 $445.000
HEADWALL (CH - PW - 0) (DIA= 42 IN)
EA 2.000 $16,000.000 $19,361.100 $10,800.000 $22,000.000 $12,800.000 $11,500.000
HEADWALL (CH - PW - 0) (DIA= 48 IN)
EA 2.000 $20,000.000 $23,135.920 $11,390.000 $26,000.000 $14,300.000 $12,800.000
WINGWALL (PW - 1) (HW=7 FT)
EA 4.000 $30,000.000 $27,598.750 $31,490.000 $31,000.000 $33,500.000 $30,100.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 4.000 $2,200.000 $2,078.740 $1,500.000 $2,300.000 $2,120.000 $1,900.000
SET (TY II) (24 IN) (RCP) (6: 1) (C)
EA 4.000 $2,800.000 $2,573.220 $1,740.000 $2,900.000 $3,120.000 $2,800.000
SET (TY II) (36 IN) (RCP) (4: 1) (C)
EA 6.000 $4,000.000 $6,132.550 $2,620.000 $6,800.000 $4,230.000 $3,800.000
REMOV STR (WINGWALL)
EA 4.000 $2,300.000 $1,982.920 $1,570.000 $2,200.000 $568.000 $510.000
REMOV STR (HEADWALL)
EA 6.000 $2,100.000 $1,586.340 $1,040.000 $1,800.000 $1,230.000 $1,100.000
REMOV STR (PIPE)
LF 370.000 $30.000 $19.180 $32.250 $30.000 $11.100 $10.000
REMOV STR (BOX CULVERT)
LF 46.000 $100.000 $78.720 $160.000 $100.000 $123.000 $110.000
MOBILIZATION
LS 1.000 $546,175.120 $541,954.770 $405,000.000 $700,000.000 $635,000.000 $936,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 10.000 $9,000.000 $3,839.320 $8,160.000 $3,000.000 $4,310.000 $11,650.000
ROCK FILTER DAMS (INSTALL) (TY 1)
LF 650.000 $40.000 $30.400 $29.500 $45.000 $42.300 $31.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 500.000 $40.000 $36.550 $35.500 $55.000 $50.100 $37.000
ROCK FILTER DAMS (REMOVE)
LF 1,150.000 $15.000 $7.500 $7.250 $17.000 $16.700 $7.500
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 112.000 $25.000 $19.500 $19.000 $15.000 $39.000 $19.500
CONSTRUCTION EXITS (REMOVE)
SY 112.000 $10.000 $6.400 $6.200 $5.000 $13.400 $6.400
TEMP SEDMT CONT FENCE (INSTALL)
LF 18,115.000 $3.000 $3.350 $3.250 $6.000 $5.300 $3.350
TEMP SEDMT CONT FENCE (REMOVE)
LF 18,115.000 $0.800 $0.350 $0.350 $2.000 $1.400 $0.350
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 1,080.000 $5.000 $6.250 $6.050 $10.000 $7.800 $6.250
BIODEG EROSN CONT LOGS (REMOVE)
LF 1,080.000 $1.000 $1.000 $0.950 $3.000 $1.650 $1.000
ONE-WAY TRAF CONT (FLAGGER CONT)
HR 1,184.000 $80.000 $114.000 $216.000 $175.000 $73.600 $91.000
ONE-WAY TRAF CONT (PILOT CAR)
HR 496.000 $120.000 $132.000 $280.000 $200.000 $211.000 $166.000
ONE-WAY TRAF CONT (PORT TRAF SIG)
MO 6.000 $5,700.000 $11,490.880 $2,000.000 $8,000.000 $5,090.000 $7,000.000
PORT CTB (FUR & INST)(SGL SLOPE)(TY 1)
LF 180.000 $100.000 $120.000 $15.000 $150.000 $131.000 $62.000
PORT CTB (MOVE)(SGL SLP)(TY 1)
LF 720.000 $15.000 $95.000 $10.000 $125.000 $22.500 $49.000
PORT CTB (REMOVE)(SGL SLP)(TY 1)
LF 180.000 $20.000 $85.000 $10.000 $100.000 $73.800 $45.000
INTERSECTIONS (ACP)
SY 570.000 $60.000 $55.200 $68.000 $100.000 $71.800 $90.000
DRIVEWAYS (SURF TREAT)
SY 1,005.000 $50.000 $41.400 $59.250 $50.000 $73.100 $73.000
TURNOUTS (ACP)
SY 76.000 $55.000 $101.200 $96.500 $100.000 $175.000 $86.000
MTL W-BEAM GD FEN (TIM POST)
LF 1,150.000 $25.000 $24.620 $24.250 $30.000 $27.400 $25.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 7.000 $1,500.000 $1,349.970 $1,670.000 $1,600.000 $1,500.000 $1,155.000
MTL BM GD FEN (LONG SPAN SYSTEM)
EA 4.000 $2,000.000 $1,268.060 $1,260.000 $1,500.000 $1,410.000 $1,155.000
GUARDRAIL END TREATMENT (INSTALL)
EA 7.000 $3,500.000 $3,173.680 $2,910.000 $3,800.000 $3,540.000 $3,000.000
CRASH CUSH ATTEN (MOVE & RESET)
EA 16.000 $1,770.000 $1,131.390 $500.000 $2,400.000 $1,260.000 $1,400.000
CRASH CUSH ATTEN (REMOVE)
EA 4.000 $1,850.000 $908.540 $500.000 $2,800.000 $1,010.000 $650.000
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
EA 4.000 $8,850.000 $9,439.790 $2,000.000 $23,000.000 $10,500.000 $10,500.000
GATE (TY 1)
EA 2.000 $2,000.000 $750.000 $1,450.000 $800.000 $1,620.000 $1,000.000
MAILBOX INSTALL-S (TWW-POST) TY 4
EA 6.000 $310.000 $350.000 $339.000 $350.000 $390.000 $300.000
MAILBOX INSTALL-M (TWW-POST) TY 4
EA 1.000 $860.000 $775.000 $751.000 $375.000 $863.000 $310.000
ALUMINUM SIGNS (TY A)
SF 35.000 $50.000 $42.500 $41.250 $50.000 $47.400 $28.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 19.000 $600.000 $750.000 $727.000 $800.000 $836.000 $680.000
IN SM RD SN SUP&AM TYS80(1)SA(T)
EA 4.000 $1,600.000 $1,035.000 $1,000.000 $1,250.000 $1,150.000 $1,050.000
IN SM RD SN SUP&AM TYS80(1)SA(T-2EXT)
EA 1.000 $1,700.000 $1,150.000 $1,110.000 $1,300.000 $1,280.000 $1,095.000
IN SM RD SN SUP&AM TYS80(1)SA(U-1EXT)
EA 1.000 $1,800.000 $1,365.000 $1,320.000 $1,400.000 $1,520.000 $1,175.000
REMOVE SM RD SN SUP&AM
EA 23.000 $120.000 $130.000 $126.000 $100.000 $145.000 $80.000
INSTL OM ASSM (OM-2X)(WC)GND
EA 17.000 $70.000 $72.000 $69.750 $65.000 $80.200 $80.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 71.000 $35.000 $37.000 $69.750 $30.000 $41.200 $32.000
INSTL OM ASSM (OM-2Z)(WFLX)SRF(BI)
EA 3.000 $103.000 $125.000 $121.000 $125.000 $139.000 $77.000
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 38,213.000 $0.400 $0.500 $0.450 $0.750 $0.560 $1.250
WK ZN PAV MRK REMOV (W)4"(SLD)
LF 44,256.000 $0.800 $0.750 $0.950 $0.900 $0.840 $1.200
WK ZN PAV MRK REMOV (W)24"(SLD)
LF 200.000 $6.500 $7.500 $21.500 $9.000 $8.400 $25.000
WK ZN PAV MRK REMOV (Y)4"(SLD)
LF 48,050.000 $0.800 $0.750 $0.950 $0.900 $0.840 $1.250
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 1,584.000 $2.000 $1.630 $3.000 $2.000 $1.850 $1.660
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 1,584.000 $1.500 $1.630 $3.000 $2.000 $1.850 $1.660
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 85.000 $1.100 $2.000 $1.700 $2.500 $2.250 $3.000
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 40.000 $10.000 $12.000 $10.250 $15.000 $13.400 $25.000
REF PAV MRK TY I(W)36"(YLD TRI)(100MIL)
EA 4.000 $60.000 $75.000 $62.250 $90.000 $83.600 $75.000
PAVEMENT SEALER 6"
LF 63,585.000 $0.350 $0.200 $0.600 $0.250 $0.220 $0.210
PAVEMENT SEALER 8"
LF 85.000 $0.600 $0.500 $0.900 $0.600 $0.560 $1.000
PAVEMENT SEALER 24"
LF 40.000 $5.000 $2.000 $2.050 $2.500 $2.250 $4.000
PAVEMENT SEALER (YLD TRI)
EA 4.000 $15.000 $15.000 $15.000 $18.000 $16.700 $10.000
REF PROF PAV MRK TY I(W)6"(SLD)(090MIL)
LF 31,895.000 $1.100 $1.100 $1.250 $1.300 $1.250 $1.100
REF PROF PAV MRK TY I(Y)6"(SLD)(090MIL)
LF 31,690.000 $1.100 $1.100 $1.250 $1.300 $1.250 $1.100
REFL PAV MRKR TY I-C
EA 25.000 $6.000 $6.000 $6.000 $7.000 $6.700 $6.000
REFL PAV MRKR TY II-A-A
EA 406.000 $6.500 $6.000 $8.300 $7.000 $6.700 $6.000
ELIM EXT PAV MRK & MRKS (4")
LF 38,155.000 $0.800 $0.550 $0.950 $0.750 $0.610 $1.300
RELOCT RDSD FLSH BCN AM (SOLAR PWRD)
EA 1.000 $7,500.000 $10,850.000 $10,510.000 $13,000.000 $12,100.000 $10,850.000
D-GR HMA TY-B PG64-22
TON 19,313.000 $100.000 $92.200 $124.000 $116.000 $123.000 $139.000
TACK COAT
GAL 4,199.000 $5.000 $4.640 $5.600 $6.000 $3.600 $4.520
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 32.000 $125.000 $125.000 $134.000 $200.000 $83.600 $400.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $16,000.000 $9,000.000 $35,150.000 $25,000.000 $13,400.000 $20,000.000
TMA (STATIONARY)
DAY 102.000 $250.000 $500.000 $179.000 $450.000 $169.000 $300.000
TMA (MOBILE OPERATION)
DAY 32.000 $400.000 $750.000 $242.000 $250.000 $536.000 $600.000
Totals: $5,986,126.270 $5,653,830.455 $6,135,556.650 $7,134,352.150 $7,156,703.620 $9,364,173.180