REMOVE CONC (RAIL)
|
LF
|
30.000
|
$110.000
|
$80.000
|
$129.260
|
$175.000
|
|
|
|
REMOVING CONCRETE(MOW STRIP)
|
LF
|
1,611.000
|
$11.000
|
$9.000
|
$12.900
|
$15.000
|
|
|
|
EXCAVATION (ROADWAY)
|
CY
|
61,535.000
|
$17.000
|
$13.000
|
$15.200
|
$22.000
|
|
|
|
EMBANKMENT (FINAL)(DENS CONT)(TY C)
|
CY
|
33,283.000
|
$15.500
|
$11.000
|
$14.000
|
$29.000
|
|
|
|
BACKFILL (TY A OR B)
|
STA
|
666.000
|
$185.000
|
$200.000
|
$175.000
|
$155.000
|
|
|
|
FURNISHING AND PLACING TOPSOIL (4")
|
SY
|
212,420.000
|
$1.400
|
$0.500
|
$1.180
|
$2.000
|
|
|
|
DRILL SEEDING (PERM) (RURAL) (SANDY)
|
SY
|
212,420.000
|
$0.300
|
$0.340
|
$0.200
|
$0.350
|
|
|
|
VEGETATIVE WATERING
|
MG
|
3,871.500
|
$30.000
|
$35.000
|
$19.800
|
$28.000
|
|
|
|
FL BS (CMP IN PLC)(TYE GR1-2)(FNAL POS)
|
CY
|
36,849.000
|
$132.000
|
$0.000
|
$0.000
|
$0.000
|
|
|
|
LIME TRT (EXST MATL)(8")
|
SY
|
83,916.000
|
$8.000
|
$5.200
|
$4.800
|
$3.550
|
|
|
|
LIME (HYD(SLY OR DRY) COM OR QK(DRY)
|
TON
|
3,102.000
|
$260.000
|
$340.000
|
$319.000
|
$328.000
|
|
|
|
PRIME COAT (MC-30)
|
GAL
|
25,539.000
|
$8.500
|
$5.500
|
$5.360
|
$5.000
|
|
|
|
ASPH (MULTI OPTION)
|
GAL
|
49,802.000
|
$4.500
|
$3.100
|
$4.140
|
$4.000
|
|
|
|
AGGR(TY-PB GR-4S OR TY-PB GR-4)(SAC-B)
|
CY
|
4,598.000
|
$175.000
|
$150.000
|
$182.650
|
$215.000
|
|
|
|
ASPH (AC-15P OR AC-20-5TR)
|
GAL
|
147,430.000
|
$4.000
|
$4.200
|
$4.690
|
$4.000
|
|
|
|
PLANE ASPH CONC PAV(0" TO 6")
|
SY
|
3,337.000
|
$10.000
|
$7.000
|
$7.080
|
$10.000
|
|
|
|
PLANE CONC PAV(0" TO 2")
|
SY
|
1,513.000
|
$10.000
|
$5.000
|
$7.120
|
$18.000
|
|
|
|
PLANE ASPH CONC PAV (4")
|
SY
|
55,946.000
|
$4.500
|
$3.600
|
$3.780
|
$5.000
|
|
|
|
CEM STABIL BKFL
|
CY
|
50.100
|
$140.000
|
$340.000
|
$150.340
|
$87.000
|
|
|
|
CUT & RESTORE ASPH PAVING
|
SY
|
42.000
|
$180.000
|
$175.000
|
$87.700
|
$320.000
|
|
|
|
CUT AND RESTORE PAV (FLEX BASE)
|
SY
|
27.000
|
$105.000
|
$50.000
|
$135.000
|
$425.000
|
|
|
|
DRILL SHAFT (TRF SIG POLE) (36 IN)
|
LF
|
30.000
|
$550.000
|
$310.000
|
$350.000
|
$410.000
|
|
|
|
DRILL SHAFT (TRF SIG POLE) (48 IN)
|
LF
|
44.000
|
$750.000
|
$615.000
|
$475.000
|
$760.000
|
|
|
|
RIPRAP (MOW STRIP)(4 IN)
|
CY
|
188.000
|
$640.000
|
$540.000
|
$607.610
|
$760.000
|
|
|
|
RETROFIT RAIL (TY T631)
|
LF
|
120.580
|
$100.000
|
$110.000
|
$101.650
|
$210.000
|
|
|
|
CONC BOX CULV (3 FT X 3 FT)(EXTEND)
|
LF
|
70.000
|
$860.000
|
$1,150.000
|
$939.850
|
$1,765.000
|
|
|
|
CONC BOX CULV (7 FT X 7 FT)(EXTEND)
|
LF
|
19.000
|
$1,300.000
|
$2,150.000
|
$1,315.590
|
$2,830.000
|
|
|
|
CONC. BOX CULV (6.5 FT X 3 FT) (EXTEND)
|
LF
|
271.000
|
$2,000.000
|
$1,200.000
|
$1,237.910
|
$2,918.000
|
|
|
|
RC PIPE (CL III)(18 IN)
|
LF
|
56.000
|
$110.000
|
$110.000
|
$92.710
|
$190.000
|
|
|
|
RC PIPE (CL III)(24 IN)
|
LF
|
60.000
|
$120.000
|
$136.000
|
$125.280
|
$210.000
|
|
|
|
WINGWALL (PW - 1) (HW=4 FT)
|
EA
|
4.000
|
$18,000.000
|
$16,000.000
|
$16,887.830
|
$42,300.000
|
|
|
|
WINGWALL (PW - 1) (HW=8 FT)
|
EA
|
1.000
|
$32,000.000
|
$38,000.000
|
$46,040.650
|
$51,600.000
|
|
|
|
SET (REPLACE PIPE RUNNER)
|
EA
|
10.000
|
$3,100.000
|
$2,000.000
|
$6,076.130
|
$1,800.000
|
|
|
|
SET (TY I)(S=3 FT)(HW= 4 FT)(4:1)(C)
|
EA
|
6.000
|
$9,800.000
|
$8,000.000
|
$11,118.660
|
$7,600.000
|
|
|
|
SET (TY II) (18 IN) (RCP) (6: 1) (P)
|
EA
|
4.000
|
$1,600.000
|
$1,400.000
|
$2,113.480
|
$2,600.000
|
|
|
|
SET (TY II) (24 IN) (RCP) (6: 1) (P)
|
EA
|
4.000
|
$2,000.000
|
$1,700.000
|
$2,349.010
|
$2,900.000
|
|
|
|
SET (TY I) (S=6.5FT) (HW=4FT) (4:1)(C)
|
EA
|
8.000
|
$18,000.000
|
$9,200.000
|
$14,376.100
|
$8,500.000
|
|
|
|
CLEAN EXIST CULVERTS
|
EA
|
12.000
|
$1,900.000
|
$5,500.000
|
$2,568.250
|
$6,300.000
|
|
|
|
REMOV STR (SET)
|
EA
|
28.000
|
$550.000
|
$5,000.000
|
$1,111.800
|
$980.000
|
|
|
|
REMOV STR (PIPE)
|
LF
|
192.000
|
$25.000
|
$28.000
|
$15.440
|
$48.000
|
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$2,426,312.800
|
$2,440,000.000
|
$2,830,000.080
|
$1,010,101.000
|
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
21.000
|
$5,500.000
|
$3,000.000
|
$11,040.180
|
$14,080.000
|
|
|
|
ROCK FILTER DAMS (INSTALL) (TY 1)
|
LF
|
340.000
|
$40.000
|
$70.000
|
$51.730
|
$65.000
|
|
|
|
ROCK FILTER DAMS (REMOVE)
|
LF
|
340.000
|
$20.000
|
$33.000
|
$13.420
|
$31.000
|
|
|
|
CONSTRUCTION EXITS (INSTALL) (TY 1)
|
SY
|
940.000
|
$36.000
|
$44.000
|
$58.450
|
$48.000
|
|
|
|
CONSTRUCTION EXITS (REMOVE)
|
SY
|
940.000
|
$12.000
|
$13.000
|
$12.740
|
$21.000
|
|
|
|
TEMP SEDMT CONT FENCE (INSTALL)
|
LF
|
2,811.000
|
$4.000
|
$5.000
|
$7.380
|
$5.000
|
|
|
|
TEMP SEDMT CONT FENCE (REMOVE)
|
LF
|
2,811.000
|
$1.300
|
$1.400
|
$1.590
|
$2.000
|
|
|
|
BIODEG EROSN CONT LOGS (INSTL) (12")
|
LF
|
50.000
|
$6.000
|
$11.000
|
$6.640
|
$22.000
|
|
|
|
BIODEG EROSN CONT LOGS (REMOVE)
|
LF
|
50.000
|
$2.600
|
$5.500
|
$1.590
|
$10.000
|
|
|
|
CONC CURB (RIBBON)
|
LF
|
16.500
|
$60.000
|
$130.000
|
$59.400
|
$170.000
|
|
|
|
INTERSECTIONS (ACP)
|
SY
|
73.000
|
$65.000
|
$100.000
|
$101.200
|
$160.000
|
|
|
|
DRIVEWAYS (ACP)
|
SY
|
1,780.000
|
$60.000
|
$72.000
|
$55.200
|
$160.000
|
|
|
|
RUMBLE STRIPS (SHOULDER) ASPHALT
|
LF
|
157,860.000
|
$0.200
|
$0.110
|
$0.100
|
$0.250
|
|
|
|
RUMBLE STRIPS (CENTERLINE) ASPHALT
|
LF
|
78,930.000
|
$0.200
|
$0.120
|
$0.110
|
$0.250
|
|
|
|
MTL W-BEAM GD FEN (TIM POST)
|
LF
|
1,717.500
|
$27.000
|
$28.000
|
$25.550
|
$31.000
|
|
|
|
MTL BEAM GD FEN TRANS (THRIE-BEAM)
|
EA
|
6.000
|
$2,400.000
|
$3,035.000
|
$2,685.000
|
$2,675.000
|
|
|
|
MTL W - BEAM GD FEN (LOW FILL CULVERT)
|
LF
|
70.000
|
$100.000
|
$115.000
|
$106.350
|
$130.000
|
|
|
|
REMOVE METAL BEAM GUARD FENCE
|
LF
|
800.000
|
$3.500
|
$5.500
|
$5.000
|
$6.000
|
|
|
|
RM MTL BM GD FENCE TRANS (THRIE-BEAM)
|
EA
|
8.000
|
$250.000
|
$245.000
|
$225.000
|
$280.000
|
|
|
|
GUARDRAIL END TREATMENT (INSTALL)
|
EA
|
18.000
|
$3,300.000
|
$3,680.000
|
$3,380.000
|
$4,250.000
|
|
|
|
GUARDRAIL END TREATMENT (REMOVE)
|
EA
|
12.000
|
$325.000
|
$245.000
|
$225.000
|
$280.000
|
|
|
|
CONDT (PVC) (SCH 40) (2")
|
LF
|
200.000
|
$14.000
|
$21.000
|
$13.500
|
$23.000
|
|
|
|
CONDT (PVC) (SCH 40) (4")
|
LF
|
225.000
|
$22.000
|
$31.000
|
$28.000
|
$34.000
|
|
|
|
CONDT (PVC) (SCH 80) (2") (BORE)
|
LF
|
215.000
|
$28.000
|
$35.000
|
$35.000
|
$39.000
|
|
|
|
CONDT (PVC) (SCH 80) (4") (BORE)
|
LF
|
635.000
|
$37.000
|
$52.000
|
$45.000
|
$60.000
|
|
|
|
ELEC CONDR (NO.8) INSULATED
|
LF
|
410.000
|
$2.000
|
$2.200
|
$1.550
|
$3.000
|
|
|
|
ELEC CONDR (NO.6) INSULATED
|
LF
|
135.000
|
$2.500
|
$2.400
|
$1.950
|
$3.000
|
|
|
|
TRAY CABLE (4 CONDR) (12 AWG)
|
LF
|
655.000
|
$5.500
|
$2.700
|
$2.400
|
$3.000
|
|
|
|
GROUND BOX TY D (162922)W/APRON
|
EA
|
6.000
|
$1,300.000
|
$1,515.000
|
$1,400.000
|
$1,720.000
|
|
|
|
REMOVE ELECTRICAL SERVICES
|
EA
|
1.000
|
$700.000
|
$408.000
|
$800.000
|
$465.000
|
|
|
|
ELC SRV TY D 120/240 060(NS)SS(E)TS(O)
|
EA
|
1.000
|
$6,000.000
|
$2,727.000
|
$4,800.000
|
$3,100.000
|
|
|
|
ALUMINUM SIGNS (TY A)
|
SF
|
1.400
|
$35.000
|
$70.000
|
$50.000
|
$82.000
|
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(P)
|
EA
|
25.000
|
$800.000
|
$1,035.000
|
$732.500
|
$1,175.000
|
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(T)
|
EA
|
2.000
|
$1,000.000
|
$1,170.000
|
$892.500
|
$1,300.000
|
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(U-EXAL)
|
EA
|
5.000
|
$1,400.000
|
$1,360.000
|
$1,372.500
|
$1,550.000
|
|
|
|
RELOCATE SM RD SN SUP&AM TY S80
|
EA
|
18.000
|
$650.000
|
$735.000
|
$565.000
|
$800.000
|
|
|
|
REMOVE SM RD SN SUP&AM
|
EA
|
16.000
|
$100.000
|
$92.000
|
$105.000
|
$105.000
|
|
|
|
RELOCATE SM RD SN SUP & AM TY TEMP
|
EA
|
21.000
|
$290.000
|
$380.000
|
$195.000
|
$435.000
|
|
|
|
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
|
EA
|
23.000
|
$38.000
|
$70.000
|
$26.500
|
$81.000
|
|
|
|
INSTL OM ASSM (OM-2Z)(WFLX)GND(BI)
|
EA
|
27.000
|
$105.000
|
$147.000
|
$85.000
|
$170.000
|
|
|
|
WK ZN PAV MRK NON-REMOV (W)6"(BRK)
|
LF
|
10,680.000
|
$0.700
|
$0.500
|
$0.170
|
$0.600
|
|
|
|
WK ZN PAV MRK NON-REMOV (W)6"(DOT)
|
LF
|
1,458.000
|
$1.300
|
$0.500
|
$0.320
|
$0.600
|
|
|
|
WK ZN PAV MRK NON-REMOV (W)6"(SLD)
|
LF
|
298,728.000
|
$0.450
|
$0.500
|
$0.170
|
$0.600
|
|
|
|
WK ZN PAV MRK NON-REMOV (W)8"(SLD)
|
LF
|
4,444.000
|
$0.800
|
$0.650
|
$0.250
|
$0.600
|
|
|
|
WK ZN PAV MRK NON-REMOV (Y)6"(BRK)
|
LF
|
1,640.000
|
$0.700
|
$0.500
|
$0.200
|
$0.600
|
|
|
|
WK ZN PAV MRK NON-REMOV (Y)6"(SLD)
|
LF
|
127,641.000
|
$0.450
|
$0.500
|
$0.170
|
$0.600
|
|
|
|
WK ZN PAV MRK SHT TERM (TAB)TY W
|
EA
|
1,732.000
|
$2.000
|
$1.800
|
$1.630
|
$4.000
|
|
|
|
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
|
EA
|
12,885.000
|
$2.000
|
$1.800
|
$1.630
|
$4.000
|
|
|
|
REFL PAV MRK TY I (W)6"(DOT)(090MIL)
|
LF
|
1,575.000
|
$1.700
|
$0.700
|
$0.930
|
$1.000
|
|
|
|
REFL PAV MRK TY I (W)8"(DOT)(090MIL)
|
LF
|
576.000
|
$3.000
|
$0.800
|
$1.140
|
$1.000
|
|
|
|
REFL PAV MRK TY I (W)8"(SLD)(090MIL)
|
LF
|
3,820.000
|
$1.000
|
$0.800
|
$1.140
|
$1.000
|
|
|
|
REFL PAV MRK TY I (W)24"(SLD)(090MIL)
|
LF
|
117.000
|
$10.000
|
$13.000
|
$8.000
|
$15.000
|
|
|
|
REF PAV MRK TY I(W)36"(YLD TRI)(090MIL)
|
EA
|
5.000
|
$75.000
|
$108.000
|
$77.000
|
$130.000
|
|
|
|
REFL PAV MRK TY I (Y)24"(SLD)(090MIL)
|
LF
|
899.000
|
$10.000
|
$15.000
|
$6.250
|
$18.000
|
|
|
|
RE PM W/RET REQ TY I (W)6"(BRK)(090MIL)
|
LF
|
10,750.000
|
$0.700
|
$0.800
|
$0.810
|
$1.000
|
|
|
|
RE PM W/RET REQ TY I (W)6"(SLD)(090MIL)
|
LF
|
133,153.000
|
$0.700
|
$0.800
|
$0.820
|
$1.000
|
|
|
|
RE PM W/RET REQ TY I (Y)6"(BRK)(090MIL)
|
LF
|
1,840.000
|
$0.700
|
$0.800
|
$0.810
|
$1.000
|
|
|
|
RE PM W/RET REQ TY I (Y)6"(SLD)(090MIL)
|
LF
|
128,901.000
|
$0.700
|
$0.800
|
$0.820
|
$1.000
|
|
|
|
PREFAB PAV MRK TY C (W) (ARROW)
|
EA
|
18.000
|
$260.000
|
$190.000
|
$215.000
|
$220.000
|
|
|
|
PREFAB PAV MRK TY C (W) (LNDP ARROW)
|
EA
|
8.000
|
$450.000
|
$550.000
|
$500.000
|
$600.000
|
|
|
|
PREFAB PAV MRK TY C (W) (WORD)
|
EA
|
18.000
|
$330.000
|
$300.000
|
$289.000
|
$340.000
|
|
|
|
REFL PAV MRKR TY I-C
|
EA
|
886.000
|
$5.000
|
$5.500
|
$3.750
|
$6.000
|
|
|
|
REFL PAV MRKR TY II-A-A
|
EA
|
2,156.000
|
$5.000
|
$5.500
|
$3.750
|
$6.000
|
|
|
|
ELIM EXT PAV MRK & MRKS (6")
|
LF
|
149,364.000
|
$0.500
|
$0.900
|
$0.130
|
$2.150
|
|
|
|
INSTALL HWY TRF SIG (ISOLATED)
|
EA
|
1.000
|
$28,900.000
|
$24,500.000
|
$33,900.000
|
$27,750.000
|
|
|
|
REMOVING TRAFFIC SIGNALS
|
EA
|
1.000
|
$6,500.000
|
$2,940.000
|
$6,900.000
|
$3,400.000
|
|
|
|
VEH SIG SEC (12")LED(GRN)
|
EA
|
8.000
|
$350.000
|
$270.000
|
$245.000
|
$320.000
|
|
|
|
VEH SIG SEC (12")LED(GRN ARW)
|
EA
|
2.000
|
$350.000
|
$280.000
|
$245.000
|
$330.000
|
|
|
|
VEH SIG SEC (12")LED(YEL)
|
EA
|
8.000
|
$350.000
|
$270.000
|
$245.000
|
$320.000
|
|
|
|
VEH SIG SEC (12")LED(YEL ARW)
|
EA
|
4.000
|
$350.000
|
$280.000
|
$245.000
|
$330.000
|
|
|
|
VEH SIG SEC (12")LED(RED)
|
EA
|
8.000
|
$350.000
|
$270.000
|
$245.000
|
$320.000
|
|
|
|
VEH SIG SEC (12")LED(RED ARW)
|
EA
|
2.000
|
$350.000
|
$270.000
|
$245.000
|
$320.000
|
|
|
|
BACKPLATE W/REFL BRDR(4 SEC)
|
EA
|
2.000
|
$370.000
|
$185.000
|
$185.000
|
$210.000
|
|
|
|
BACKPLATE W/REFL BRDR(3 SEC)
|
EA
|
8.000
|
$320.000
|
$158.000
|
$157.000
|
$180.000
|
|
|
|
TRF SIG CBL (TY A)(14 AWG)(7 CONDR)
|
LF
|
445.000
|
$3.250
|
$2.600
|
$2.050
|
$3.000
|
|
|
|
TRF SIG CBL (TY A)(14 AWG)(16 CONDR)
|
LF
|
665.000
|
$4.000
|
$5.000
|
$4.100
|
$6.000
|
|
|
|
RELOCT RDSD FLSH BCN AM (SOLAR PWRD)
|
EA
|
3.000
|
$10,000.000
|
$2,020.000
|
$3,500.000
|
$2,300.000
|
|
|
|
INS TRF SIG PL AM(S)1 ARM(44')LUM
|
EA
|
2.000
|
$14,500.000
|
$23,400.000
|
$16,800.000
|
$27,200.000
|
|
|
|
INS TRF SIG PL AM(S)1 ARM(50')
|
EA
|
1.000
|
$30,400.000
|
$35,000.000
|
$35,100.000
|
$40,700.000
|
|
|
|
INS TRF SIG PL AM(S)1 ARM(50')LUM
|
EA
|
1.000
|
$32,200.000
|
$38,600.000
|
$38,100.000
|
$44,700.000
|
|
|
|
INSTALL OF FND FOR GROUND MNT CABINETS
|
EA
|
1.000
|
$5,800.000
|
$3,200.000
|
$10,800.000
|
$3,700.000
|
|
|
|
TREE TRIMMING / BRUSH REMOVAL
|
MI
|
12.620
|
$5,000.000
|
$8,030.000
|
$8,250.000
|
$7,500.000
|
|
|
|
TREE TRIMMING / BRUSH REMOVAL(CHANNELS)
|
AC
|
0.300
|
$6,500.000
|
$4,530.000
|
$44,000.000
|
$4,200.000
|
|
|
|
CARBON FIBER REINF POLYMER PROTECTION
|
SF
|
70.000
|
$165.000
|
$380.000
|
$500.000
|
$450.000
|
|
|
|
D-GR HMA TY-B SAC-B PG64-22
|
TON
|
28,748.000
|
$105.000
|
$105.000
|
$124.300
|
$120.000
|
|
|
|
TACK COAT
|
GAL
|
40,459.000
|
$5.000
|
$5.000
|
$3.780
|
$5.000
|
|
|
|
STONE-MTRX-ASPH SMA-D SAC-A PG76-22
|
TON
|
45,371.000
|
$150.000
|
$144.000
|
$189.200
|
$165.000
|
|
|
|
FILLING MILLED ASPHALT RUMBLE STRIPS
|
LF
|
149,364.000
|
$5.000
|
$2.300
|
$3.500
|
$1.100
|
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
EA
|
4.000
|
$16,000.000
|
$30,000.000
|
$11,500.000
|
$9,500.000
|
|
|
|
ITS COM CBL (ETHERNET)
|
LF
|
120.000
|
$4.000
|
$3.400
|
$3.150
|
$4.000
|
|
|
|
CCTV FIELD EQUIPMENT (DIGITAL)
|
EA
|
1.000
|
$8,000.000
|
$5,230.000
|
$2,000.000
|
$6,100.000
|
|
|
|
CCTV MOUNT (POLE)
|
EA
|
1.000
|
$700.000
|
$550.000
|
$210.000
|
$630.000
|
|
|
|
BBU SYSTEM (EXTERNAL BATT CABINET)
|
EA
|
1.000
|
$9,500.000
|
$8,200.000
|
$10,000.000
|
$9,500.000
|
|
|
|
TMA (STATIONARY)
|
DAY
|
160.000
|
$225.000
|
$137.000
|
$250.000
|
$440.000
|
|
|
|
TMA (MOBILE OPERATION)
|
HR
|
40.000
|
$70.000
|
$62.000
|
$90.000
|
$160.000
|
|
|
|
SOLAR POWERED LED ROADSIDE SIGN
|
EA
|
1.000
|
$5,000.000
|
$6,800.000
|
$2,765.000
|
$4,400.000
|
|
|
|
RVDS(PRESENCE DETECTION ONLY)
|
EA
|
4.000
|
$10,200.000
|
$10,500.000
|
$8,600.000
|
$12,200.000
|
|
|
|
RVDS(ADVANCE DETECTION ONLY)
|
EA
|
2.000
|
$8,500.000
|
$10,300.000
|
$8,600.000
|
$11,900.000
|
|
|
|
INST OF FIELD HARDENED ETHERNET SWITCH
|
EA
|
1.000
|
$250.000
|
$10,000.000
|
$300.000
|
$11,600.000
|
|
|
|
INSTALLATION OF CELLULAR MODEM
|
EA
|
1.000
|
$250.000
|
$3,800.000
|
$300.000
|
$4,400.000
|
|
1
|
|
FL BS (CMP IN PLC)(TY A GR 5)(FNAL POS)
|
CY
|
36,849.000
|
$132.000
|
$120.000
|
$124.460
|
$144.600
|
|
Totals: |
$31,553,508.800
|
$24,833,825.300
|
$28,320,663.696
|
$28,597,946.100
|