Bid Cobra

JACKSON BAGBY RD (0913-18-038)

Items: 50

County: JACKSON
Length: 0.1430 MILES
Highway: BAGBY RD
District: YOAKUM
Control Number: 0913-18-038
DBE Goal: 5.0%
Project: BR 2023(849)
Guaranty: $42,000.00
Time: 176 WORKING DAYS
Engineer's Estimate: $2,079,074.00
Date: 03/05/2025 (1 year ago)
Contract Number: 3253223
Type: BRIDGE REPLACEMENT
Project ID: A00193914
Contract Type: Federal
Project Description: REPLACE BRIDGE AND APPROACHES
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
CLAYTON HARRIS
JAMES JANAK
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (6)
E
Engineer's Estimate
$2,079,074.00
1
$1,929,626.80
Over/Under Est: -7.19% -$149,447.20
$1,955,626.00
Over/Under Est: -5.94% -$123,448.00
Amt Left: 1.35% $25,999.20
$2,039,262.00
Over/Under Est: -1.91% -$39,812.00
Amt Left: 5.68% $109,635.20
Delta: -4.28% -$83,636.00
$2,098,687.20
Over/Under Est: 0.94% $19,613.20
Amt Left: 8.76% $169,060.40
Delta: -2.91% -$59,425.20
Over/Under Est: 8.32% $172,967.80
Amt Left: 16.71% $322,415.00
Delta: -7.31% -$153,354.60
$2,772,973.09
Over/Under Est: 33.38% $693,899.09
Amt Left: 43.71% $843,346.29
Delta: -23.13% -$520,931.29
Subcontractor Percentage Amount
C&J CONTRACTORS LLC 57.55% $1,110,500.22
CARTHAGE DRILLING, LLC 9.66% $186,401.95
FLEX SUPPLY, LLC 1.20% $23,155.52
Total: 68.41% $1,320,057.69

Bid Items & Bid Tabulations

50 Total 0 of 50
JACKSON  |  BAGBY RD  |  YOAKUM  |  0913-18-038  |  03/05/2025  |  $2,079,074.00  |  BR 2023(849)  |  BRIDGE REPL  |  176 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
LAKEY, INC.
CONSTAR CONSTRUCTION
STX CIVIL
TREVWAY, INC.
E-Z BEL CONSTRUCTION, LLC
C. E. BARKER, LTD.
PREPARING ROW
STA 5.850 $5,000.000 $3,650.000 $3,400.000 $7,000.000 $5,622.000 $13,000.000 $45,000.000
EXCAV (ROADWAY)
CY 560.000 $22.000 $23.797 $20.000 $30.000 $24.000 $18.000 $31.110
EXCAV (CHANNEL)
CY 1,164.000 $25.000 $28.600 $23.000 $30.000 $11.000 $22.000 $28.150
EMBANK (FNL)(OC)(TY C)
CY 1,262.000 $28.000 $51.500 $21.000 $35.000 $21.000 $35.000 $43.920
BLADING
HR 32.000 $100.000 $125.000 $50.000 $100.000 $173.000 $175.000 $122.490
BROADCAST SEED (PERM_RURAL_SAND)
SY 1,429.000 $2.000 $0.620 $1.000 $2.000 $2.000 $1.500 $1.520
BROADCAST SEED (PERM_RURAL_CLAY)
SY 513.000 $2.000 $1.000 $1.000 $1.000 $2.000 $3.000 $3.500
BROADCAST SEED (TEMP_WARM)
SY 485.000 $2.000 $1.000 $1.000 $1.500 $2.000 $3.500 $3.970
BROADCAST SEED (TEMP_COOL)
SY 485.000 $2.000 $1.000 $1.000 $1.500 $2.000 $3.500 $3.970
VEGETATIVE WATERING
TGL 22.400 $120.000 $34.500 $210.000 $100.000 $200.000 $90.000 $61.240
FL BS (CMP IN PLC)(TY E GR 5)(FNAL POS)
CY 459.000 $130.000 $110.000 $142.000 $105.000 $200.000 $124.000 $137.070
ASPH (RC-250)
GAL 396.000 $15.000 $11.000 $24.000 $20.000 $23.000 $18.000 $29.160
AGGR (TY-E, GR-5)(SAC-B)
CY 14.000 $600.000 $582.370 $1,700.000 $1,000.000 $1,700.000 $1,263.500 $2,449.760
AGGR (TY-PE, GR-4)(SAC-B)
CY 15.100 $600.000 $364.000 $1,600.000 $1,000.000 $1,550.000 $1,188.000 $2,799.720
ASPH (AC 20-5TR OR AC-20XP OR CRS-2P)
GAL 671.000 $15.000 $7.400 $19.000 $15.000 $17.980 $14.000 $23.330
CEM STABIL BKFL
CY 194.000 $215.000 $225.000 $120.000 $175.000 $192.000 $240.000 $297.470
DRILL SHAFT (24 IN)
LF 990.000 $300.000 $300.000 $273.000 $305.000 $421.000 $250.000 $314.170
CL C CONC (ABUT)
CY 43.600 $1,600.000 $1,000.000 $1,200.000 $1,600.000 $1,167.000 $1,600.000 $2,944.070
CL C CONC (CAP)
CY 31.200 $1,800.000 $1,540.000 $1,400.000 $1,800.000 $1,000.000 $1,600.000 $2,955.550
CL C CONC (COLUMN)
CY 14.000 $2,000.000 $1,500.000 $2,400.000 $2,000.000 $2,065.000 $2,100.000 $4,092.270
REINF CONC SLAB (SLAB BEAM)
SF 6,552.000 $30.000 $26.080 $21.000 $28.000 $20.110 $20.000 $36.840
PRESTR CONC SLAB BEAM (4SB12)
LF 908.000 $255.000 $250.000 $252.000 $280.000 $244.000 $310.000 $230.600
PRESTR CONC SLAB BEAM (5SB15)
LF 561.000 $260.000 $233.180 $262.000 $280.000 $256.000 $418.000 $249.440
RIPRAP (STONE PROTECTION)(18 IN)
CY 1,328.000 $200.000 $205.000 $205.000 $165.000 $233.000 $225.000 $227.770
RAIL (TY T223)
LF 468.000 $160.000 $150.000 $150.000 $165.000 $110.000 $210.000 $210.410
ARMOR JOINT (SEALED)
LF 119.000 $150.000 $200.000 $134.000 $125.000 $250.000 $300.000 $163.030
RC PIPE (CL III)(24 IN)
LF 156.000 $125.000 $127.300 $115.000 $110.000 $103.000 $190.000 $208.690
RC PIPE (CL III)(30 IN)
LF 136.000 $175.000 $138.800 $125.000 $150.000 $168.000 $230.000 $232.300
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 1.000 $4,000.000 $2,137.850 $3,800.000 $3,000.000 $4,800.000 $1,500.000 $3,007.830
SET (TY II) (30 IN) (RCP) (6: 1) (P)
EA 1.000 $5,000.000 $3,946.350 $5,800.000 $4,000.000 $5,578.000 $1,500.000 $3,527.080
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
EA 2.000 $30,000.000 $26,200.000 $33,000.000 $28,000.000 $20,000.000 $25,000.000 $34,617.370
MOBILIZATION
LS 1.000 $190,000.000 $113,500.000 $170,000.000 $150,000.000 $200,000.000 $200,000.000 $234,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 12.000 $2,500.000 $5,000.000 $2,200.000 $2,000.000 $1,000.000 $1,500.000 $6,999.300
ROCK FILTER DAMS (INSTALL) (TY 1)
CY 3.000 $1,000.000 $12.000 $670.000 $500.000 $500.000 $650.000 $758.260
ROCK FILTER DAMS (REMOVE)
CY 6.000 $70.000 $260.000 $330.000 $50.000 $100.000 $290.000 $338.300
SANDBAGS FOR EROSION CONTROL
EA 76.000 $25.000 $14.000 $10.000 $20.000 $7.000 $10.000 $11.670
TEMP SEDMT CONT FENCE (INSTALL)
LF 1,311.000 $4.500 $4.570 $6.000 $5.000 $3.000 $6.000 $7.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 1,311.000 $1.500 $1.250 $2.000 $3.000 $1.000 $1.000 $1.170
ROCK FILTER DAMS (INSTALL) (TY 1) 6:1
CY 6.000 $320.000 $260.000 $450.000 $500.000 $300.000 $450.000 $524.950
DRIVEWAYS (BASE)
SY 42.000 $125.000 $90.000 $96.000 $45.000 $110.000 $70.000 $93.530
MTL W-BEAM GD FEN (TIM POST)
LF 100.000 $40.000 $28.645 $41.000 $31.500 $55.000 $32.000 $40.830
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 4.000 $2,000.000 $2,370.000 $3,070.000 $2,700.000 $2,400.000 $2,300.000 $2,566.410
MTL BEAM GD FEN TRANS (TL2)
EA 4.000 $1,500.000 $1,400.000 $1,800.000 $1,900.000 $1,900.000 $1,414.000 $1,749.830
REMOVE TERMINAL ANCHOR SECTION
EA 4.000 $350.000 $236.135 $170.000 $260.000 $400.000 $325.000 $262.470
GUARDRAIL END TREATMENT (INSTALL)
EA 8.000 $3,500.000 $3,331.540 $4,400.000 $3,500.000 $3,100.000 $3,700.000 $4,082.930
WIRE FENCE (TY A)
LF 437.000 $25.000 $22.500 $33.000 $41.000 $11.000 $33.500 $21.000
WIRE FENCE (TY C)
LF 648.000 $30.000 $30.000 $31.000 $41.000 $12.000 $38.000 $21.000
WIRE FENCE (WATER GAP)
LF 120.000 $100.000 $50.000 $67.000 $100.000 $55.000 $80.000 $58.330
INSTL DEL ASSM (D-SW)SZ 1(BRF)CTB (BI)
EA 10.000 $40.000 $25.000 $33.000 $30.000 $25.000 $25.000 $29.160
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 12.000 $40.000 $35.000 $40.000 $36.000 $25.000 $15.000 $52.490
Totals: $2,079,074.000 $1,929,626.800 $1,955,626.000 $2,039,262.000 $2,098,687.200 $2,252,041.800 $2,772,973.090
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $500.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $1,000.00
Total: $1,500.00