Control Number County Highway Bid Date Low Bidder Pay Estimates % of Contract Amount % Complete Contract Amount
0913-18-038 JACKSON BAGBY RD 03/05/2025 LAKEY, INC. 05/26 | 04/26 | 03/26 | 02/26 | 01/26 57.55% $1,110,500.22 49.00% $1,929,626.80
0202-09-033 GRAYSON FM 697 03/04/2025 LAKEY, INC. 05/26 | 04/26 | 03/26 | 02/26 | 01/26 21.52% $1,079,143.70 59.00% $5,014,608.26
0784-04-027 ORANGE FM 1131 03/04/2025 LAKEY, INC. 05/26 | 04/26 | 03/26 | 02/26 | 01/26 12.17% $621,213.07 88.00% $5,104,462.40
0911-28-063 HOUSTON VA 08/01/2024 DREWERY CONSTRUCTION COMPANY, INCORPORATED 12/25 | 11/25 | 10/25 | 09/25 | 08/25 21.69% $339,804.52 90.00% $1,566,641.40
0123-05-015 RUSK US 84 01/06/2023 DREWERY CONSTRUCTION COMPANY, INCORPORATED 05/26 | 04/26 | 03/26 | 02/26 | 01/26 14.30% $1,971,994.19 98.00% $13,790,169.14
0610-07-097 BOWIE IH 30 06/02/2022 LONGVIEW BRIDGE AND ROAD, LTD. 05/26 | 04/26 | 03/26 | 02/26 | 01/26 0.07% $42,951.64 52.00% $61,359,488.60
0118-08-075 NACOGDOCHES SH 21 01/07/2022 DREWERY CONSTRUCTION COMPANY, INCORPORATED 10/24 | 09/24 | 08/24 | 07/24 | 06/24 37.99% $945,998.39 100.00% $2,490,124.75
0176-03-097 ANGELINA US 59 12/04/2019 SACYR CONSTRUCTION USA LLC 05/26 | 04/26 | 03/26 | 02/26 | 01/26 1.68% $2,446,131.14 102.00% $145,603,043.87