Show Job Controls
Bid Cobra

HIDALGO CS (0921-02-508)

Items: 21

County: HIDALGO
Length: N/A
Highway: CS
District: PHARR
Control Number: 0921-02-508
DBE Goal: N/A
Project: STP 2B23(057)HESG
Guaranty: N/A
Time: 57 WORKING DAYS
Engineer's Estimate: $178,883.90
Date: 08/03/2023 (2 years ago)
Contract Number: N/A
Type: HAZARD ELIMINATION & SAFETY
Mail/Deliver Bids To: N/A
HECTOR SILLER
JESUS NORIEGA
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (3)
E
Engineer's Estimate
$178,883.90
$192,172.57
Over/Under Est: 7.43% $13,288.67
Over/Under Est: 18.15% $32,467.10
Amt Left: 9.98% $19,178.43
$218,827.28
Over/Under Est: 22.33% $39,943.38
Amt Left: 13.87% $26,654.71
Delta: -3.54% -$7,476.28
Subcontractor Percentage Amount
FOREMOST PAVING, INC. 20.96% $41,503.45
TEXAS HIGHWAY SYSTEMS, INC. 5.36% $10,613.48
PAVEMENT MARKINGS INC. 2.99% $5,920.58
Total: 29.31% $58,037.51

Bid Items & Bid Tabulations

21 Total 0 of 21
HIDALGO  |  CS  |  PHARR  |  0921-02-508  |  08/03/2023  |  $178,883.90  |  STP 2B23(057)HESG  |  HAZARD ELIM & SAFETY  |  57 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
THE LEVY COMPANY, INC.
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.
TRAF-TEX, INC.
HMCL ACP TY-D AC-1.5
TON 90.000 $157.140 $461.110 $425.000 $418.000
DRILL SHAFT (RDWY ILL POLE) (30 IN)
LF 56.000 $200.040 $274.290 $245.000 $152.000
RIPRAP (CONC)(4 IN)
CY 2.500 $500.930 $1,758.860 $835.000 $1,554.000
MOBILIZATION
LS 1.000 $8,625.810 $14,396.420 $35,000.000 $32,328.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 4.000 $9,516.140 $1,987.030 $2,900.000 $2,760.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 168.000 $4.090 $5.540 $10.000 $4.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 168.000 $1.410 $1.740 $2.500 $1.220
IN RD IL (TY SA) 40T-8 (250W EQ) LED
EA 7.000 $4,420.310 $4,549.490 $3,870.000 $4,763.000
CONDT (PVC) (SCH 40) (2")
LF 925.000 $17.020 $11.210 $12.000 $21.650
CONDT (PVC) (SCH 80) (4") (BORE)
LF 222.000 $40.000 $51.620 $44.000 $36.000
ELEC CONDR (NO.6) BARE
LF 1,115.000 $2.020 $1.510 $1.500 $1.610
ELEC CONDR (NO.6) INSULATED
LF 3,000.000 $2.370 $1.650 $1.600 $1.870
GROUND BOX TY A (122311)W/APRON
EA 8.000 $1,525.650 $1,224.620 $1,070.000 $1,225.000
ELC SRV TY A 120/240 060(NS)SS(T)TP(O)
EA 2.000 $3,800.000 $6,945.680 $6,400.000 $6,650.000
IN SM RD SN SUP&AM TYS80(1)SA(T)
EA 4.000 $936.090 $1,225.000 $1,300.000 $1,116.000
REMOVE SM RD SN SUP&AM
EA 3.000 $118.210 $350.000 $375.000 $147.000
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 25.000 $6.950 $21.270 $16.000 $38.000
RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL)
LF 2,200.000 $0.720 $2.300 $1.700 $1.210
REFL PAV MRKR TY II-A-A
EA 32.000 $3.850 $10.350 $8.500 $6.060
TMA (STATIONARY)
DAY 57.000 $100.000 $113.660 $238.000 $240.000
SOLAR POWERED LED ROADSIDE SIGN
EA 2.000 $4,129.630 $2,499.420 $4,250.000 $5,155.000
Totals: $178,883.905 $192,172.570 $211,351.000 $218,827.280