Items: 106

County: GRIMES
Length: N/A
Highway: SH 30
District: BRYAN
Control Number: 0212-04-039
DBE Goal: 750.0%
Project: BR 2B24(147)
Guaranty: N/A
Time: 429 WORKING DAYS
Engineer's Estimate: $9,446,098.30
Date: 06/06/2024 (2 years ago)
Contract Number: N/A
Type: BRIDGE REPLACEMENT
Mail/Deliver Bids To: N/A
JAMES ROBBINS
JOSEPH GREIVE
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (6)
E
Engineer's Estimate
$9,446,098.30
$12,337,845.25
Over/Under Est: 30.61% $2,891,746.95
Over/Under Est: 34.45% $3,254,548.29
Amt Left: 2.94% $362,801.34
Over/Under Est: 49.45% $4,670,789.39
Amt Left: 14.42% $1,779,042.44
Delta: -11.15% -$1,416,241.10
Over/Under Est: 52.34% $4,944,533.07
Amt Left: 16.64% $2,052,786.12
Delta: -1.94% -$273,743.68
Over/Under Est: 58.46% $5,522,326.86
Amt Left: 21.32% $2,630,579.91
Delta: -4.02% -$577,793.79
Over/Under Est: 58.6% $5,535,324.81
Amt Left: 21.43% $2,643,577.86
Delta: -0.09% -$12,997.95
Subcontractor Percentage Amount
M & D FOUNDATION DRILLING INDUSTRIES, INC. 4.26% $532,187.60
WILLOW CITY SIGN & RAIL, INC. 1.14% $142,416.40
CEN TEX HYDROSEED, INC. 0.99% $123,677.40
TORO BRAVO CONSTRUCTION, LLC 0.82% $102,439.87
HIGHWAY 1 LLC 0.64% $79,953.07
EGGEMEYER LAND CLEARING, LLC 0.53% $66,211.13
WILKO INDUSTRIAL, L.L.C. 0.24% $29,982.40
HOUSTON SAWING & DRILLING 0.13% $16,240.47
LONESTAR TRAFFIC SAFETY, LLC 0.10% $12,492.67
EMERY SAPP & SON'S INC. 0.08% $9,994.13
WEST TEXAS ROCK RESOURCES, LLC 0.04% $4,997.07
WEST TEXAS RUMBLE STRIP LLC 0.04% $4,997.07
Total: 9.01% $1,125,589.28

Bid Items & Bid Tabulations

106 Total 0 of 106
GRIMES  |  SH 30  |  BRYAN  |  0212-04-039  |  06/06/2024  |  $9,446,098.30  |  BR 2B24(147)  |  BRIDGE REPL  |  429 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
BIG CREEK CONSTRUCTION, LTD.
LARRY YOUNG PAVING, INC.
TEXAS MATERIALS GROUP, INC.
FORDE CONSTRUCTION COMPANY, INC.
JAMES CONSTRUCTION GROUP, LLC
BRICE CONSTRUCTION AND DESIGN LLC
PREPARING ROW
STA 45.000 $2,000.000 $1,750.000 $1,864.500 $10,000.000 $6,000.000 $31,000.000 $22,600.000
REMOVING CONC (RIPRAP)
SY 905.000 $30.000 $25.000 $11.630 $11.000 $36.000 $7.280 $14.590
REMOVING STAB BASE AND ASPH PAV (10")
SY 166.000 $5.700 $12.000 $16.970 $30.000 $21.000 $17.950 $14.860
RMV STAB BASE & ASPH PV (17")
SY 931.000 $7.500 $17.000 $26.430 $22.000 $26.000 $10.460 $14.770
OBLITERATING ABANDONED ROAD
STA 32.000 $1,300.000 $1,500.000 $2,986.410 $3,550.000 $1,400.000 $1,716.750 $1,219.660
EXCAVATION (ROADWAY)
CY 12,449.000 $9.000 $14.000 $16.800 $20.000 $16.000 $10.000 $8.030
EXCAVATION (CHANNEL)
CY 6,474.000 $10.000 $14.000 $17.190 $16.000 $25.000 $8.000 $15.000
EMBANKMENT (FINAL)(DENS CONT)(TY C)
CY 28,255.000 $10.000 $22.000 $19.960 $26.000 $21.000 $16.000 $12.380
FURNISHING AND PLACING TOPSOIL (4")
SY 41,100.000 $0.510 $1.250 $0.990 $0.480 $2.000 $0.650 $1.190
CELL FBR MLCH SEED(PERM)(RURAL)(SANDY)
SY 41,100.000 $0.340 $0.520 $0.660 $0.520 $0.640 $0.620 $0.520
CELL FBR MLCH SEED(TEMP)(WARM)
SY 20,550.000 $0.300 $0.500 $0.610 $0.480 $0.640 $0.620 $0.480
CELL FBR MLCH SEED(TEMP)(COOL)
SY 20,550.000 $0.300 $0.500 $0.610 $0.480 $0.640 $0.620 $0.480
VEGETATIVE WATERING
MG 411.000 $23.000 $15.000 $32.140 $30.000 $140.000 $25.000 $47.090
FL BS (CMP IN PLC)(TY D GR 4)(10")
SY 30,897.000 $18.000 $24.000 $18.390 $25.000 $35.000 $34.200 $38.630
CEMENT
TON 510.000 $130.000 $250.000 $267.150 $230.000 $240.000 $237.110 $263.410
CEMENT TREAT (NEW BASE) (10")
SY 30,897.000 $2.000 $3.750 $3.320 $3.400 $5.500 $3.200 $2.430
ASPH (RC-250)
GAL 10,240.000 $3.900 $5.000 $5.720 $5.500 $4.500 $5.150 $6.750
AGGR (TY-B GR-5 OR TY-L GR-5)
CY 303.000 $100.000 $135.000 $101.610 $207.000 $338.000 $514.740 $124.000
PLANE ASPH CONC PAV (2")
SY 10,484.000 $1.500 $2.500 $2.030 $3.600 $5.000 $2.150 $3.600
CEM STABIL BKFL
CY 456.000 $80.000 $200.000 $107.580 $174.000 $189.000 $194.030 $166.260
TEMPORARY SPL SHORING
SF 3,150.000 $20.000 $35.000 $40.000 $78.000 $30.000 $40.000 $39.230
DRILL SHAFT (24 IN)
LF 3,804.000 $150.000 $200.000 $244.190 $210.000 $225.000 $200.000 $170.280
CL C CONC (ABUT)
CY 52.800 $1,000.000 $1,800.000 $1,516.330 $2,300.000 $2,700.000 $1,549.250 $2,368.210
CL C CONC (CAP)
CY 212.000 $1,200.000 $1,800.000 $1,963.560 $2,000.000 $2,300.000 $2,051.880 $1,942.910
CL C CONC (COLUMN)
CY 88.400 $1,000.000 $1,800.000 $1,748.490 $2,500.000 $2,000.000 $1,534.120 $1,674.650
REINF CONC SLAB (SLAB BEAM)
SF 47,300.000 $15.000 $20.000 $15.760 $22.000 $19.500 $20.000 $16.390
APPROACH SLAB
CY 200.400 $500.000 $800.000 $956.080 $790.000 $734.000 $579.410 $705.700
PRESTR CONC SLAB BEAM (4SB15)
LF 8,711.760 $140.000 $165.000 $214.350 $170.000 $163.000 $169.810 $200.160
PRESTR CONC SLAB BEAM (5SB15)
LF 2,177.920 $140.000 $175.000 $217.400 $170.000 $163.000 $147.370 $203.320
RIPRAP (CONC)(4 IN)
CY 958.000 $320.000 $500.000 $480.920 $512.000 $488.000 $413.920 $520.270
RIPRAP (STONE PROTECTION)(24 IN)
CY 9,857.000 $120.000 $150.000 $123.140 $171.000 $197.000 $184.900 $218.550
RIPRAP (MOW STRIP)(4 IN)
CY 83.000 $400.000 $650.000 $596.830 $680.000 $1,280.000 $556.140 $697.360
RAIL (TY T223)
LF 1,128.000 $100.000 $150.000 $130.330 $175.000 $109.000 $70.560 $109.280
ARMOR JOINT (SEALED)
LF 426.000 $75.000 $100.000 $123.730 $182.000 $127.000 $85.050 $144.900
RC PIPE (CL III)(18 IN)
LF 86.000 $50.000 $100.000 $73.030 $70.000 $77.000 $121.090 $162.150
RC PIPE (ARCH)(CL III)(DES 1)
LF 32.000 $140.000 $120.000 $168.330 $300.000 $338.000 $426.510 $355.620
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 4.000 $800.000 $1,500.000 $1,246.450 $1,200.000 $1,325.000 $1,781.670 $2,371.990
SET (TY II) (DES 1) (RCP) (6: 1) (P)
EA 2.000 $1,050.000 $1,600.000 $1,953.790 $1,200.000 $1,325.000 $2,260.240 $2,904.030
REMOV STR (SET)
EA 4.000 $600.000 $1,000.000 $500.360 $1,200.000 $1,325.000 $389.400 $667.500
REMOV STR (PIPE)
LF 48.000 $20.000 $35.000 $41.700 $60.000 $66.000 $40.740 $52.080
REMOV STR (BRIDGE 500 - 999 FT LENGTH)
EA 1.000 $100,000.000 $100,000.000 $128,477.430 $95,000.000 $200,000.000 $328,389.000 $216,782.990
REMOV STR (SMALL FENCE)
LF 2,571.000 $3.000 $5.000 $8.050 $2.400 $9.000 $2.890 $4.620
MOBILIZATION
LS 1.000 $782,000.000 $1,050,000.000 $1,270,000.000 $1,000,000.000 $1,200,000.000 $1,400,000.000 $1,487,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 27.000 $5,000.000 $3,500.000 $2,988.770 $6,000.000 $3,400.000 $2,500.000 $4,286.670
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 603.000 $30.000 $35.000 $44.450 $35.000 $45.000 $42.500 $35.000
ROCK FILTER DAMS (REMOVE)
LF 603.000 $10.000 $10.000 $12.700 $10.000 $12.000 $11.000 $10.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 222.000 $35.000 $35.000 $43.180 $34.000 $32.000 $44.920 $34.000
CONSTRUCTION EXITS (REMOVE)
SY 222.000 $10.000 $12.000 $15.240 $12.000 $16.000 $18.000 $12.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 9,938.000 $3.000 $4.000 $4.450 $3.800 $4.250 $4.000 $3.500
TEMP SEDMT CONT FENCE (REMOVE)
LF 9,938.000 $0.700 $1.000 $1.270 $1.000 $1.060 $1.000 $1.000
PORT CTB (FUR & INST)(F-SHAPE)(TY 1)
LF 3,870.000 $45.000 $45.000 $38.180 $40.000 $68.000 $30.460 $41.640
PORT CTB (MOVE)(F-SHAPE)(TY 1)
LF 2,760.000 $15.000 $12.000 $11.680 $16.000 $10.000 $6.000 $5.240
PORT CTB (REMOVE)(F-SHAPE)(TY 1)
LF 3,870.000 $8.000 $12.000 $11.680 $17.000 $17.000 $7.650 $8.050
DRIVEWAYS (ACP)
SY 145.000 $40.000 $75.000 $82.050 $29.000 $145.000 $229.720 $112.140
RUMBLE STRIPS (SHOULDER)
LF 17,532.000 $0.200 $0.550 $0.400 $0.730 $0.500 $0.310 $0.320
MTL W-BEAM GD FEN (TIM POST)
LF 1,300.000 $20.000 $30.000 $32.390 $26.000 $31.000 $25.000 $25.500
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 3.000 $2,000.000 $2,500.000 $2,667.190 $2,700.000 $2,400.000 $1,800.000 $2,100.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 3.000 $1,100.000 $1,600.000 $1,968.640 $1,600.000 $1,500.000 $1,500.000 $1,550.000
MTL BM GD FEN TRANS (NON - SYM)
EA 1.000 $1,100.000 $1,250.000 $1,587.610 $1,300.000 $1,400.000 $1,100.000 $1,250.000
REMOVE METAL BEAM GUARD FENCE
LF 1,000.000 $2.000 $2.000 $2.540 $2.000 $3.530 $2.000 $2.000
RM MTL BM GD FEN TRANS (T101)
EA 4.000 $170.000 $250.000 $317.520 $260.000 $306.000 $400.000 $250.000
GUARDRAIL END TREATMENT (INSTALL)
EA 5.000 $2,800.000 $3,500.000 $3,937.290 $3,200.000 $3,800.000 $3,000.000 $3,100.000
GUARDRAIL END TREATMENT (REMOVE)
EA 4.000 $270.000 $250.000 $317.520 $260.000 $480.000 $400.000 $250.000
GDRAIL END TRT(INST)(WOOD POST)(TY III)
EA 2.000 $2,500.000 $3,500.000 $4,127.800 $3,900.000 $4,000.000 $3,300.000 $3,250.000
CRASH CUSH ATTEN (MOVE & RESET)
EA 3.000 $1,500.000 $2,000.000 $1,350.060 $2,000.000 $2,000.000 $2,750.000 $1,850.000
CRASH CUSH ATTEN (REMOVE)
EA 6.000 $1,000.000 $1,000.000 $486.390 $900.000 $960.000 $800.000 $900.000
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
EA 6.000 $8,500.000 $10,000.000 $6,527.800 $8,500.000 $9,300.000 $8,800.000 $8,500.000
GATE (REMOVE)
EA 3.000 $550.000 $500.000 $437.910 $86.000 $520.000 $351.170 $979.030
MAILBOX INSTALL-S (TWG-POST) TY 2
EA 1.000 $225.000 $350.000 $444.530 $350.000 $358.000 $315.000 $350.000
MAILBOX INSTALL-D (TWG-POST) TY 2
EA 1.000 $250.000 $400.000 $508.040 $400.000 $398.000 $350.000 $400.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 6.000 $520.000 $600.000 $717.600 $580.000 $761.000 $670.000 $565.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 2.000 $650.000 $700.000 $844.620 $680.000 $847.000 $745.000 $665.000
RELOCATE SM RD SN SUP&AM TY 10BWG
EA 2.000 $400.000 $500.000 $603.300 $500.000 $790.000 $695.000 $475.000
RELOCATE SM RD SN SUP&AM TY S80
EA 1.000 $350.000 $650.000 $806.500 $650.000 $895.000 $788.000 $635.000
REMOVE SM RD SN SUP&AM
EA 8.000 $100.000 $125.000 $146.060 $125.000 $114.000 $100.000 $115.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB
EA 12.000 $25.000 $30.000 $32.390 $26.000 $61.000 $24.000 $25.500
INSTL DEL ASSM (D-SW)SZ (BRF)GF1
EA 19.000 $30.000 $30.000 $38.100 $31.000 $83.000 $24.000 $30.000
INSTL OM ASSM (OM-2X)(WC)GND
EA 6.000 $80.000 $100.000 $114.310 $92.000 $268.000 $70.000 $90.000
WK ZN PAV MRK NON-REMOV (W)6"(SLD)
LF 11,053.000 $0.200 $0.550 $0.660 $0.540 $0.550 $0.520 $0.660
WK ZN PAV MRK NON-REMOV (W)8"(DOT)
LF 39.000 $0.500 $1.000 $1.270 $1.050 $3.200 $1.000 $1.450
WK ZN PAV MRK NON-REMOV (Y)6"(SLD)
LF 15,300.000 $0.200 $0.550 $0.660 $0.540 $0.550 $0.520 $0.660
WK ZN PAV MRK REMOV (TRAF BTN) TY Y
LF 1,225.000 $1.000 $1.250 $1.560 $1.250 $2.150 $1.230 $1.000
WK ZN PAV MRK REMOV (W)6"(SLD)
LF 4,745.000 $0.500 $1.250 $1.560 $1.250 $1.600 $1.230 $1.250
WK ZN PAV MRK REMOV (W)8"(DOT)
LF 57.000 $1.500 $4.000 $4.450 $3.600 $5.300 $3.500 $5.000
WK ZN PAV MRK REMOV (W)8"(SLD)
LF 1,629.000 $1.400 $2.500 $2.830 $2.300 $2.650 $2.230 $3.000
WK ZN PAV MRK REMOV (Y)6"(SLD)
LF 10,806.000 $1.000 $1.250 $1.560 $1.250 $1.600 $1.230 $1.250
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 464.000 $1.000 $1.500 $0.710 $1.600 $2.150 $3.000 $5.000
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 1,164.000 $1.000 $1.500 $0.710 $1.600 $2.150 $3.000 $5.000
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 1,210.000 $1.000 $2.000 $2.480 $2.000 $1.600 $1.950 $1.800
REFL PAV MRK TY II (W) 6" (BRK)
LF 160.000 $0.100 $0.600 $0.740 $0.600 $2.150 $0.580 $0.750
REFL PAV MRK TY II (W) 6" (SLD)
LF 1,226.000 $0.100 $0.600 $0.740 $0.600 $1.050 $0.580 $0.750
REFL PAV MRK TY II (Y) 6" (SLD)
LF 2,452.000 $0.100 $0.600 $0.740 $0.600 $1.050 $0.580 $0.750
PAVEMENT SEALER 6"
LF 3,838.000 $0.100 $0.100 $0.130 $0.100 $1.050 $0.100 $0.750
RE PM W/RET REQ TY I (W)6"(BRK)(100MIL)
LF 1,180.000 $0.300 $0.950 $1.210 $1.000 $1.050 $0.950 $0.900
RE PM W/RET REQ TY I (W)6"(SLD)(100MIL)
LF 10,250.000 $0.300 $0.950 $1.140 $0.920 $0.800 $0.900 $0.840
RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL)
LF 23,281.000 $0.300 $0.950 $1.140 $0.920 $0.800 $0.900 $0.840
REFL PAV MRKR TY I-C
EA 58.000 $3.000 $7.000 $8.890 $7.200 $6.300 $0.700 $20.000
REFL PAV MRKR TY II-A-A
EA 60.000 $3.100 $7.000 $8.890 $7.200 $6.300 $0.700 $20.000
ELIM EXT PAV MRK & MRKS (4")
LF 8,606.000 $0.500 $0.500 $0.620 $0.500 $0.550 $0.490 $0.800
ELIM EXT PAV MRK & MRKS (8")
LF 310.000 $1.000 $1.000 $1.270 $1.000 $1.060 $1.000 $2.600
PAV SURF PREP FOR MRK (6")
LF 3,838.000 $0.100 $0.100 $0.010 $0.010 $0.550 $0.010 $0.500
PAV SURF PREP FOR MRK (RPM)
EA 68.000 $1.000 $1.000 $0.640 $0.520 $5.300 $0.500 $0.500
SP MIXES SP-C PG64-22
TON 12,878.000 $100.000 $103.000 $109.500 $137.000 $118.000 $151.400 $122.500
PORTABLE CHANGEABLE MESSAGE SIGN
EA 3.000 $7,500.000 $12,400.000 $6,350.460 $12,800.000 $16,000.000 $10,876.520 $20,132.770
TMA (STATIONARY)
DAY 239.000 $275.000 $250.000 $204.480 $200.000 $170.000 $69.340 $291.250
TMA (MOBILE OPERATION)
DAY 30.000 $300.000 $500.000 $506.130 $480.000 $170.000 $1,073.900 $659.130
Totals: $9,446,098.300 $12,337,845.250 $12,700,646.616 $14,116,887.690 $14,390,631.370 $14,968,425.178 $14,981,423.124