GRAYSON FS 121 (0091-10-002)
Items: 91
County: GRAYSON
Length: N/A
Highway: FS 121
District: PARIS
Control Number: 0091-10-002
DBE Goal: N/A
Project: F 2021(862)
Guaranty: N/A
Time: 328 WORKING DAYS
Engineer's Estimate: $10,333,026.29
Date: 09/02/2021 (4 years ago)
Contract Number: N/A
Type: CONSTRUCT NEW ROAD
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Bidders (9)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$10,333,026.29 | |||
| $9,300,300.05 |
-9.99%
-$1,032,726.24
|
|||
| $10,133,166.03 |
-1.93%
-$199,860.26
|
8.96%
$832,865.98
|
||
| $10,145,626.47 |
-1.81%
-$187,399.82
|
9.09%
$845,326.42
|
-0.12%
-$12,460.44
|
|
| $10,270,226.18 |
-0.61%
-$62,800.11
|
10.43%
$969,926.13
|
-1.23%
-$124,599.71
|
|
| $10,422,406.09 |
0.86%
$89,379.80
|
12.07%
$1,122,106.04
|
-1.48%
-$152,179.91
|
|
| $10,610,655.16 |
2.69%
$277,628.87
|
14.09%
$1,310,355.11
|
-1.81%
-$188,249.07
|
|
| $11,262,737.09 |
9%
$929,710.80
|
21.1%
$1,962,437.04
|
-6.15%
-$652,081.93
|
|
| $11,865,069.60 |
14.83%
$1,532,043.31
|
27.58%
$2,564,769.55
|
-5.35%
-$602,332.51
|
|
| $11,991,517.73 |
16.05%
$1,658,491.44
|
28.94%
$2,691,217.68
|
-1.07%
-$126,448.13
|
E
Engineer's Estimate
$10,333,026.29
1
$9,300,300.05
Over/Under Est:
-9.99%
-$1,032,726.24
$10,133,166.03
Over/Under Est:
-1.93%
-$199,860.26
Amt Left:
8.96%
$832,865.98
$10,145,626.47
Over/Under Est:
-1.81%
-$187,399.82
Amt Left:
9.09%
$845,326.42
Delta:
-0.12%
-$12,460.44
$10,270,226.18
Over/Under Est:
-0.61%
-$62,800.11
Amt Left:
10.43%
$969,926.13
Delta:
-1.23%
-$124,599.71
$10,422,406.09
Over/Under Est:
0.86%
$89,379.80
Amt Left:
12.07%
$1,122,106.04
Delta:
-1.48%
-$152,179.91
$10,610,655.16
Over/Under Est:
2.69%
$277,628.87
Amt Left:
14.09%
$1,310,355.11
Delta:
-1.81%
-$188,249.07
$11,262,737.09
Over/Under Est:
9%
$929,710.80
Amt Left:
21.1%
$1,962,437.04
Delta:
-6.15%
-$652,081.93
$11,865,069.60
Over/Under Est:
14.83%
$1,532,043.31
Amt Left:
27.58%
$2,564,769.55
Delta:
-5.35%
-$602,332.51
$11,991,517.73
Over/Under Est:
16.05%
$1,658,491.44
Amt Left:
28.94%
$2,691,217.68
Delta:
-1.07%
-$126,448.13
| Subcontractor | Percentage | Amount |
|---|---|---|
| RAMBO CONTRACTING, INC. | 4.51% | $424,518.72 |
| PEACHTREE CONSTRUCTION, LTD. | 3.23% | $304,034.47 |
| J. H. ODEN CONTRACTING COMPANY | 1.74% | $163,783.28 |
| TRP CONSTRUCTION GROUP, LLC | 0.77% | $72,478.81 |
| FORTSON CONTRACTING, INC. | 0.62% | $58,359.56 |
| SOUTHERN CROSS CONTRACTORS, LLC | 0.51% | $48,005.44 |
| BARRICADES UNLIMITED | 0.10% | $9,412.83 |
| WEST TEXAS ROCK RESOURCES, LLC | 0.07% | $6,588.98 |
| Total: | 11.55% | $1,087,182.09 |
Bid Items & Bid Tabulations
91
Total
0 of 91