GONZALES US 87 (0143-06-027)

Items: 105

County: GONZALES
Length: N/A
Highway: US 87
District: YOAKUM
Control Number: 0143-06-027
DBE Goal: N/A
Project: NH 2018(032)
Guaranty: N/A
Time: 329 WORKING DAYS
Engineer's Estimate: $17,925,725.80
Date: 09/07/2017 (8 years ago)
Contract Number: N/A
Type: CONSTRUCT SUPER 2 LANE
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (4)
E
Engineer's Estimate
$17,925,725.80
$16,127,476.45
Over/Under Est: -10.03% -$1,798,249.35
$16,166,490.10
Over/Under Est: -9.81% -$1,759,235.70
Amt Left: 0.24% $39,013.65
$16,877,679.93
Over/Under Est: -5.85% -$1,048,045.87
Amt Left: 4.65% $750,203.48
Delta: -4.40% -$711,189.83
$17,731,831.04
Over/Under Est: -1.08% -$193,894.76
Amt Left: 9.95% $1,604,354.59
Delta: -5.06% -$854,151.11

Bid Items & Bid Tabulations

105 Total 0 of 105
GONZALES  |  US 87  |  YOAKUM  |  0143-06-027  |  09/07/2017  |  $17,925,725.80  |  NH 2018(032)  |  CONSTRUCT SUPER 2 LANE  |  329 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
ANGEL BROTHERS HOLDINGS CORP.
DEAN WORD COMPANY, LTD.
HUNTER INDUSTRIES, LTD.
RAY FARIS, INC.
PREPARING ROW
STA 4.000 $1,500.000 $10,000.000 $3,631.050 $1,218.000 $3,000.000
REMOVING CONC (DRIVEWAYS)
SY 22.000 $25.000 $25.000 $18.460 $27.750 $17.860
EXCAVATION (ROADWAY)
CY 97,135.000 $10.000 $7.000 $8.341 $8.850 $4.370
EMBANKMENT (FINAL)(ORD COMP)(TY C)
CY 53,233.000 $12.000 $3.500 $7.646 $5.610 $5.780
EMBANKMENT (VEHICLE)(ORD COMP)(TY C)
CY 3,413.000 $15.000 $7.500 $7.164 $7.710 $7.700
BACKFILL (TY B)
STA 892.000 $80.000 $75.000 $88.346 $83.250 $74.550
BLADING
HR 100.000 $100.000 $85.000 $82.070 $79.800 $59.640
DRILL SEEDING (PERM) (RURAL) (SANDY)
SY 199,418.000 $0.150 $0.140 $0.134 $0.140 $0.140
DRILL SEEDING (TEMP) (WARM)
SY 49,854.000 $0.100 $0.110 $0.103 $0.140 $0.080
DRILL SEEDING (TEMP) (COOL)
SY 49,854.000 $0.100 $0.110 $0.103 $0.140 $0.080
VEGETATIVE WATERING
MG 1,112.450 $15.000 $15.000 $13.921 $19.980 $11.300
FL BS (CMP IN PLC)(TYE GR1-2)(FNAL POS)
CY 53,327.000 $50.000 $38.750 $38.698 $44.460 $44.730
CEMENT
TON 1,662.000 $125.000 $132.500 $127.821 $126.000 $130.000
CEMENT TREAT (EXIST MATL) (6")
SY 225,607.000 $1.100 $0.960 $1.149 $1.370 $1.120
PRIME COAT (MC-30)
GAL 44,703.000 $3.000 $3.450 $3.424 $3.460 $3.490
PRIME COAT (RC-250)
GAL 8,085.000 $3.200 $3.750 $3.366 $3.360 $3.330
AGGR(TY-PE GR-4 SAC-B)
CY 5,264.000 $60.000 $85.000 $68.931 $56.730 $70.610
ASPH (AC-15P OR AC-10-2TR OR CRS-2P)
GAL 227,343.000 $2.000 $2.150 $2.282 $2.510 $2.260
D-GR HMA TY-B PG70-22
TON 48,080.000 $56.000 $53.000 $48.108 $54.630 $56.550
D-GR HMA TY-D SAC-B PG70-22
TON 103,200.000 $56.000 $56.500 $56.143 $58.310 $61.690
FLEXIBLE PAVEMENT STRUCTURE REPAIR(8")
SY 2,000.000 $70.000 $85.000 $49.388 $32.590 $27.560
PLANE ASPH CONC PAV(0" TO 2")
SY 8,000.000 $2.000 $3.500 $1.867 $1.170 $2.080
PLANE ASPH CONC PAV (2")
SY 17,134.000 $1.100 $3.000 $1.826 $1.070 $1.000
PAV JT UNDERSEAL (24")
LF 855.000 $30.000 $23.000 $20.600 $24.000 $75.500
TEMPORARY SPL SHORING
SF 1,337.000 $20.000 $27.500 $10.260 $40.950 $45.000
CONC STR REPAIR(DECK REP(PART DEPTH))
SF 10.000 $100.000 $460.000 $412.050 $115.510 $85.000
RIPRAP (CONC)(5 IN)
CY 73.000 $450.000 $685.000 $478.550 $462.030 $550.000
RIPRAP (STONE COMMON)(DRY)(12 IN)
CY 44.000 $200.000 $125.000 $152.950 $131.260 $125.000
CLEANING AND SEALING JOINTS
LF 855.000 $25.000 $30.000 $24.720 $30.000 $50.000
CONC BOX CULV (3 FT X 2 FT)
LF 205.000 $225.000 $395.000 $344.570 $435.770 $350.000
CONC BOX CULV (4 FT X 3 FT)
LF 71.000 $400.000 $550.000 $458.210 $467.280 $400.000
CONC BOX CULV (4 FT X 4 FT)
LF 34.000 $300.000 $600.000 $519.300 $483.030 $450.000
CONC BOX CULV (6 FT X 3 FT)
LF 22.000 $800.000 $730.000 $578.780 $666.790 $550.000
CONC BOX CULV (6 FT X 4 FT)
LF 73.000 $600.000 $770.000 $586.890 $606.930 $600.000
CONC BOX CULV (8 FT X 4 FT)
LF 24.000 $800.000 $985.000 $709.440 $645.790 $700.000
CONC BOX CULV (8 FT X 5 FT)
LF 35.000 $825.000 $1,075.000 $772.500 $630.040 $750.000
CONC BOX CULV(5'X 6.5')
LF 33.000 $700.000 $850.000 $742.800 $609.030 $700.000
RC PIPE (CL III)(18 IN)
LF 96.000 $65.000 $60.000 $60.030 $68.250 $80.000
RC PIPE (CL III)(24 IN)
LF 156.000 $70.000 $80.000 $73.220 $73.500 $130.000
WINGWALL (PW - 2) (HW=3 FT)
EA 1.000 $6,000.000 $3,500.000 $3,773.100 $4,305.240 $3,500.000
WINGWALL (PW - 2) (HW=4 FT)
EA 2.000 $8,000.000 $4,500.000 $7,567.050 $4,725.260 $5,500.000
WINGWALL (PW - 2) (HW=5 FT)
EA 6.000 $8,000.000 $6,200.000 $7,168.890 $5,565.310 $8,000.000
WINGWALL (PW - 2) (HW=6 FT)
EA 5.000 $12,000.000 $9,000.000 $7,720.100 $7,350.410 $10,000.000
WINGWALL (PW - 2) (HW=7 FT)
EA 3.000 $14,000.000 $13,250.000 $9,854.280 $6,825.380 $14,000.000
WINGWALL (PW - 2) (HW=8 FT)
EA 3.000 $15,000.000 $17,000.000 $13,108.400 $14,175.790 $20,000.000
WINGWALL (PW - 2) (HW=9 FT)
EA 1.000 $25,000.000 $20,500.000 $17,621.900 $14,175.790 $22,500.000
SET (TY I)(S=3 FT)(HW=3FT)(4:1)(C)
EA 6.000 $5,200.000 $5,700.000 $6,141.025 $5,985.330 $4,500.000
SET (TY I)(S=3 FT)(HW= 3 FT)(6:1)(P)
EA 2.000 $5,500.000 $8,000.000 $7,607.295 $7,140.400 $6,000.000
SET (TY I)(S=3 FT)(HW= 4 FT)(4:1)(C)
EA 3.000 $5,500.000 $8,300.000 $7,966.410 $7,087.890 $5,000.000
SET (TY I)(S=3 FT)(HW= 5 FT)(4:1)(C)
EA 2.000 $7,000.000 $12,000.000 $12,840.460 $8,820.490 $5,500.000
SET (TY I)(S= 4 FT)(HW= 4 FT)(3:1) (C)
EA 1.000 $6,500.000 $6,500.000 $8,963.400 $5,775.320 $6,000.000
SET (TY I)(S= 4 FT)(HW= 4 FT)(4:1) (C)
EA 2.000 $6,000.000 $8,200.000 $10,451.180 $7,140.400 $7,000.000
SET (TY I)(S= 4 FT)(HW= 5 FT)(3:1) (C)
EA 1.000 $6,000.000 $10,000.000 $11,255.410 $7,717.930 $7,000.000
SET (TY I)(S= 4 FT)(HW= 5 FT)(4:1) (C)
EA 3.000 $6,000.000 $12,000.000 $12,033.440 $8,925.500 $7,000.000
SET (TY I)(S= 4 FT)(HW= 6 FT)(4:1) (C)
EA 1.000 $6,000.000 $17,000.000 $15,683.520 $13,650.760 $7,800.000
SET (TY I)(S= 6 FT)(HW= 5 FT)(3:1) (C)
EA 1.000 $8,500.000 $9,500.000 $13,655.885 $8,295.460 $8,000.000
SET (TY I)(S= 6 FT)(HW= 5 FT)(4:1) (C)
EA 3.000 $8,500.000 $13,000.000 $14,627.410 $12,600.700 $8,500.000
SET (TY I)(S= 6 FT)(HW= 6 FT)(4:1) (C)
EA 1.000 $8,500.000 $21,000.000 $17,271.050 $16,800.940 $8,500.000
SET (TY I)(S= 8 FT)(HW= 5 FT)(4:1) (C)
EA 1.000 $8,000.000 $12,500.000 $19,095.280 $13,125.730 $9,500.000
SET (TY I)(S= 8 FT)(HW= 6 FT)(4:1) (C)
EA 1.000 $10,000.000 $17,000.000 $21,795.720 $18,901.050 $10,500.000
SET (TY I)(S= 8 FT)(HW= 9 FT)(3:1) (C)
EA 1.000 $11,000.000 $26,000.000 $8,454.300 $22,051.230 $12,000.000
SET (TY II) (12 IN) (RCP) (6: 1) (P)
EA 6.000 $1,000.000 $1,000.000 $1,117.700 $971.300 $800.000
SET (TY II) (15 IN) (CMP) (6: 1) (P)
EA 2.000 $1,000.000 $1,200.000 $1,146.515 $971.300 $850.000
SET (TY II) (15 IN) (RCP) (6: 1) (P)
EA 2.000 $1,000.000 $1,200.000 $1,364.925 $971.300 $850.000
SET (TY II) (18 IN) (CMP) (6: 1) (P)
EA 24.000 $850.000 $1,200.000 $1,157.325 $971.300 $900.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 28.000 $1,200.000 $1,200.000 $1,332.550 $971.300 $900.000
SET (TY II) (24 IN) (CMP) (6: 1) (P)
EA 4.000 $2,000.000 $1,750.000 $1,430.685 $971.300 $1,200.000
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 12.000 $1,800.000 $1,750.000 $1,804.875 $971.300 $1,200.000
SET (TY II) (36 IN) (RCP) (6: 1) (P)
EA 2.000 $4,000.000 $3,800.000 $3,701.950 $1,995.110 $3,500.000
REMOV STR (SMALL)
EA 7.000 $800.000 $650.000 $820.000 $1,155.060 $1,200.000
MOBILIZATION
LS 1.000 $1,700,000.000 $885,000.000 $1,215,959.475 $1,252,007.860 $1,664,211.600
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 22.000 $2,500.000 $2,000.000 $3,643.153 $2,669.210 $2,150.000
ROCK FILTER DAMS (INSTALL) (TY 1)
LF 550.000 $40.000 $23.000 $26.707 $20.000 $20.000
ROCK FILTER DAMS (REMOVE)
LF 550.000 $10.000 $10.000 $7.180 $6.000 $6.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 15,648.000 $2.250 $2.250 $2.641 $1.780 $1.780
TEMP SEDMT CONT FENCE (REMOVE)
LF 15,648.000 $0.500 $0.650 $0.449 $0.550 $0.550
INTERSECTIONS (ACP)
SY 424.000 $40.000 $36.000 $14.626 $17.520 $30.800
DRIVEWAYS (CONC)
SY 22.000 $80.000 $90.000 $118.450 $89.250 $131.240
DRIVEWAYS (ACP)
SY 5,737.000 $40.000 $29.000 $13.761 $14.280 $25.640
RUMBLE STRIPS (SHOULDER)
LF 182,704.000 $0.150 $0.130 $0.123 $0.180 $0.070
RUMBLE STRIPS (CENTERLINE)
LF 91,352.000 $0.200 $0.160 $0.164 $0.180 $0.070
MAILBOX INSTALL-S (TWG-POST) TY 1
EA 6.000 $200.000 $125.000 $118.450 $115.000 $115.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 148.000 $450.000 $455.000 $442.900 $430.000 $430.000
REMOVE SM RD SN SUP&AM
EA 148.000 $80.000 $50.000 $41.200 $40.000 $40.000
INSTL OM ASSM (OM-2Z)(FLX)GND(BI)
EA 26.000 $50.000 $55.000 $53.560 $52.000 $52.000
WK ZN PAV MRK NON-REMOV (Y)4"(BRK)
LF 44,028.000 $0.150 $0.110 $0.185 $0.180 $0.240
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 176,113.000 $0.150 $0.110 $0.185 $0.180 $0.240
WK ZN PAV MRK REMOV (W)4"(SLD)
LF 176,113.000 $0.300 $0.260 $0.185 $0.180 $0.490
WK ZN PAV MRK REMOV (Y)4"(SLD)
LF 176,113.000 $0.300 $0.260 $0.185 $0.180 $0.490
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 4,403.000 $1.500 $0.900 $1.202 $1.760 $1.020
REFL PAV MRK TY I (W)8"(SLD)(090MIL)
LF 5,950.000 $1.000 $0.420 $0.979 $0.960 $0.700
RE PM W/RET REQ TY I (W)4"(BRK)(090MIL)
LF 14,751.000 $0.250 $0.330 $0.391 $0.380 $0.330
RE PM W/RET REQ TY I (W)4"(SLD)(090MIL)
LF 179,214.000 $0.250 $0.330 $0.309 $0.300 $0.320
RE PM W/RET REQ TY I (Y)4"(BRK)(090MIL)
LF 5,196.000 $0.250 $0.330 $0.371 $0.360 $0.340
RE PM W/RET REQ TY I (Y)4"(SLD)(090MIL)
LF 184,334.000 $0.250 $0.330 $0.309 $0.300 $0.320
PREFAB PAV MRK TY C (W) (8") (DOT)
LF 570.000 $2.000 $5.300 $3.502 $3.420 $4.000
PREFAB PAV MRK TY C (W) (12") (SLD)
LF 1,090.000 $3.000 $8.500 $6.077 $5.940 $5.870
PREFAB PAV MRK TY C (W) (24") (SLD)
LF 275.000 $8.000 $11.650 $14.832 $14.500 $12.300
PREFAB PAV MRK TY C (W) (ARROW)
EA 13.000 $200.000 $135.000 $226.600 $221.540 $188.000
PREFAB PAV MRK TY C (W) (WORD)
EA 9.000 $300.000 $160.000 $267.800 $261.820 $209.000
PREFAB PAV MRK TY C (Y) (12") (SLD)
LF 605.000 $7.000 $8.500 $5.562 $5.440 $6.110
REFL PAV MRKR TY I-C
EA 726.000 $2.500 $4.250 $2.987 $2.920 $3.770
REFL PAV MRKR TY II-A-A
EA 3,151.000 $2.500 $4.250 $2.884 $2.820 $3.330
ELIM EXT PV MRK & MRKS (RUMBLE STRIP)
LF 154,099.000 $0.250 $0.580 $0.567 $0.460 $2.090
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $8,000.000 $25,000.000 $9,270.000 $7,866.600 $7,000.000
Totals: $17,925,725.800 $16,127,476.450 $16,166,490.252 $16,877,679.931 $17,731,831.045