CAMERON STENGER ST (0921-06-370)

Items: 88

County: CAMERON
Length: 0.0000 MILES
Highway: STENGER ST
District: PHARR
Control Number: 0921-06-370
DBE Goal: 5.0%
Project: F 2025(194)
Guaranty: $48,000.00
Time: 140 WORKING DAYS
Engineer's Estimate: $1,926,659.08
Date: 08/07/2025 (10 months ago)
Contract Number: 8253011
Type: BICYCLE AND PEDESTRIAN IMPROVEMENTS
Project ID: A00199485
Contract Type: Federal
Project Description: CONSTRUCT 10' CONCRETE SHARED USE PATH
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
ANDRES ESPINOZA
GABRIEL VILLARREAL
ANDRES ESPINOZA
GABRIEL VILLARREAL
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (8)
E
Engineer's Estimate
$1,926,659.08
$1,627,355.47
Over/Under Est: -15.53% -$299,303.61
Over/Under Est: -9.01% -$173,507.48
Amt Left: 7.73% $125,796.13
$1,783,265.98
Over/Under Est: -7.44% -$143,393.10
Amt Left: 9.58% $155,910.51
Delta: -1.72% -$30,114.38
$1,949,780.00
Over/Under Est: 1.2% $23,120.92
Amt Left: 19.81% $322,424.53
Delta: -9.34% -$166,514.02
Over/Under Est: 17.02% $327,938.92
Amt Left: 38.54% $627,242.53
Delta: -15.63% -$304,818.00
$2,338,468.13
Over/Under Est: 21.37% $411,809.05
Amt Left: 43.7% $711,112.66
Delta: -3.72% -$83,870.13
Over/Under Est: 49.44% $952,549.57
Amt Left: 76.93% $1,251,853.18
Delta: -23.12% -$540,740.52
$3,376,912.51
Over/Under Est: 75.27% $1,450,253.43
Amt Left: 107.51% $1,749,557.04
Delta: -17.29% -$497,703.86
Subcontractor Percentage Amount
SOIL TECH ADVANCE INC. 1.67% $27,176.84
PAVEMENT MARKINGS INC. 1.00% $16,273.55
TEXAS HIGHWAY SYSTEMS, INC. 0.97% $15,785.35
Total: 3.64% $59,235.74

Bid Items & Bid Tabulations

88 Total 0 of 88
CAMERON  |  STENGER ST  |  PHARR  |  0921-06-370  |  08/07/2025  |  $1,926,659.08  |  F 2025(194)  |  BICYCLE AND PEDESTRIAN IMPRVS  |  140 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
EARTHWORKS ENTERPRISE
LUCANIA CONTRACTORS LLC
ASAGO, LLC
ARTILLERY L.L.C.
TEXAS CORDIA CONSTRUCTION, LLC
CLORE EQUIPMENT LLC
P & C OIL FIELD SERVICE LLC
FOREMOST PAVING, INC.
PREPARING ROW
STA 55.000 $1,000.000 $398.000 $385.000 $1,200.000 $1,000.000 $1,000.000 $406.780 $3,500.000 $4,500.000
REMOV CONC (DRIVEWAYS)
SY 1,107.000 $17.500 $13.500 $20.000 $14.000 $20.000 $10.000 $28.130 $30.000 $42.000
REMOV CONC (SIDEWALK, RAMP OR SUP)
SY 1,790.000 $10.000 $13.500 $20.000 $10.000 $18.000 $10.000 $22.460 $28.000 $33.000
REMOV CONC (CURB)
LF 428.000 $15.000 $7.250 $10.000 $9.000 $12.000 $10.000 $17.430 $18.000 $6.300
REMOV CONC (CURB & GUTTER)
LF 918.000 $50.000 $7.250 $10.000 $11.000 $15.000 $10.000 $17.080 $18.000 $6.300
REMOV CONC (GUTTER)
LF 709.000 $5.000 $7.250 $10.000 $12.000 $15.000 $20.000 $17.170 $18.000 $4.600
EXCAV (ROADWAY)
CY 1,307.000 $8.000 $3.000 $17.000 $9.000 $20.000 $30.000 $24.170 $38.000 $57.300
EXCAV (CHANNEL)
CY 200.000 $35.000 $8.000 $14.000 $75.000 $50.000 $50.000 $142.160 $99.000 $34.500
EMBANK (FNL)(DC)(TY C)
CY 356.000 $9.600 $30.000 $25.000 $22.000 $20.000 $30.000 $89.510 $44.000 $59.800
EMBANK (FNL)(DC)(TY E)
CY 700.000 $25.000 $30.000 $20.000 $17.000 $25.000 $40.000 $55.680 $70.000 $80.500
FURN & PLACE TOPSOIL (4")
SY 7,864.000 $1.400 $7.250 $3.000 $1.200 $4.000 $4.000 $3.950 $3.000 $9.300
DRILL SEED (PERM_URBAN_CLAY)
SY 8,084.000 $1.000 $1.000 $0.900 $0.630 $1.000 $0.500 $0.810 $0.750 $0.700
DRILL SEED (TEMP_COOL)
SY 670.000 $1.000 $3.000 $2.700 $4.850 $1.000 $0.500 $6.770 $5.000 $5.500
VEGETATIVE WATERING
TGL 230.000 $35.000 $45.000 $25.000 $15.000 $35.000 $50.000 $130.990 $65.000 $1.000
FL BS (CMP IN PLC)(TY E GR 4) (10")
SY 369.000 $50.000 $19.000 $40.000 $37.000 $25.000 $35.000 $98.890 $55.500 $24.500
FL BS (CMP IN PLC)(TY E GR 4) (12")
SY 369.000 $100.000 $23.250 $44.000 $44.000 $30.000 $40.000 $101.900 $57.500 $22.900
FL BS (RDWY DEL)(TY E GR 4)(FNL POS)
CY 63.000 $41.000 $64.000 $100.000 $115.000 $50.000 $110.000 $177.180 $125.000 $68.600
GEOGRID BASE REINFORCEMENT (TYPE 2)
SY 369.000 $10.000 $4.000 $2.500 $4.000 $5.000 $12.000 $12.140 $4.000 $10.900
LIME (COM OR QK)(SLURRY)
TON 176.000 $300.000 $370.000 $378.000 $325.000 $350.000 $350.000 $366.900 $350.000 $456.600
LIME TRT (EXIST MATL)(8")
SY 6,166.000 $7.000 $2.000 $9.500 $6.500 $3.000 $10.000 $7.280 $7.000 $42.200
LIME TRT (EXIST MATL)(12")
SY 227.000 $8.000 $2.000 $30.000 $22.000 $4.000 $20.000 $40.410 $21.000 $80.200
LIME TRT (NEW BASE)(10")
SY 227.000 $6.000 $2.000 $30.000 $15.000 $5.000 $20.000 $40.410 $20.000 $28.400
LIME TRT (SUBGRADE)(12")
SY 19.000 $50.000 $2.000 $50.000 $250.000 $5.000 $120.000 $296.530 $250.000 $167.400
CEM TRT(PLNT MX)(CL N)(TY E)(GR 4)(10")
SY 8.000 $100.000 $40.000 $300.000 $475.000 $50.000 $550.000 $594.750 $400.000 $127.600
AGGR(TY-D GR-4 SAC-B)MATL & HAUL
CY 3.100 $500.000 $307.000 $500.000 $1,200.000 $100.000 $3,000.000 $406.330 $475.000 $127.500
PRIME COAT (MC-30)
GAL 37.400 $90.000 $5.250 $10.000 $60.000 $20.000 $45.000 $24.160 $7.000 $37.900
ASPH (AC-10-2TR)
GAL 118.000 $25.000 $4.000 $10.000 $20.000 $30.000 $25.000 $18.030 $7.000 $89.500
D-GR HMA TY-D SAC-A PG76-22
TON 76.000 $160.000 $150.000 $255.000 $250.000 $200.000 $125.000 $162.400 $425.000 $443.900
STRUCT EXCAV (SPECIAL)
CY 68.000 $100.000 $115.000 $65.000 $165.000 $100.000 $130.000 $33.440 $105.000 $115.000
TRENCH EXCAVATION PROTECTION
LF 307.000 $8.000 $3.500 $11.000 $4.000 $10.000 $15.000 $23.150 $5.000 $1.200
CL C CONC (RAIL FOUNDATION)
CY 2.000 $700.000 $402.000 $900.000 $2,200.000 $2,000.000 $4,500.000 $630.380 $1,750.000 $1,265.000
CL C CONC (COLLAR)
EA 5.000 $1,500.000 $1,300.000 $1,600.000 $3,500.000 $2,500.000 $3,000.000 $2,120.570 $2,000.000 $5,750.000
RIPRAP (CONC)(4 IN)
CY 23.000 $1,200.000 $390.000 $550.000 $650.000 $350.000 $1,200.000 $480.900 $0.100 $920.000
RIPRAP (CONC)(5 IN)
CY 95.000 $300.000 $400.000 $570.000 $550.000 $400.000 $1,500.000 $380.870 $610.000 $1,035.000
RIPRAP (MOW STRIP)(4 IN)
CY 29.000 $1,560.000 $390.000 $480.000 $550.000 $600.000 $1,100.000 $335.950 $1,450.000 $1,443.300
RAIL (TY T223)
LF 30.000 $350.000 $190.000 $280.000 $650.000 $400.000 $1,100.000 $145.910 $460.000 $575.000
RAIL (TY PR11)
LF 30.000 $200.000 $214.000 $400.000 $350.000 $400.000 $1,050.000 $385.280 $425.000 $402.500
CONC BOX CULV (12 FT X 9 FT)
LF 116.000 $1,300.000 $2,500.000 $2,050.000 $1,650.000 $4,000.000 $2,100.000 $1,983.310 $2,275.000 $2,144.800
RC PIPE (CL III)(12 IN)
LF 57.000 $160.000 $105.000 $90.000 $90.000 $130.000 $120.000 $137.220 $175.000 $138.000
RC PIPE (CL III)(36 IN)
LF 14.000 $260.000 $350.000 $340.000 $350.000 $405.000 $350.000 $345.310 $365.000 $345.000
RC PIPE (CL III)(48 IN)
LF 10.000 $500.000 $350.000 $640.000 $550.000 $665.000 $720.000 $623.640 $650.000 $805.000
RC PIPE (CL III)(60 IN)
LF 14.000 $500.000 $600.000 $600.000 $750.000 $1,000.000 $830.000 $578.830 $770.000 $1,610.000
WINGWALL (FW - 0) (HW=12 FT)
EA 1.000 $25,000.000 $22,000.000 $30,000.000 $28,000.000 $25,000.000 $35,820.000 $33,653.930 $32,000.000 $92,000.000
WINGWALL (PW - 1) (HW=13 FT)
EA 1.000 $18,000.000 $24,000.000 $31,000.000 $42,000.000 $30,000.000 $51,240.000 $33,703.970 $88,500.000 $120,750.000
SET (TY II) (12 IN) (RCP) (6: 1) (P)
EA 1.000 $1,500.000 $1,800.000 $1,200.000 $2,000.000 $3,000.000 $1,530.000 $1,556.420 $5,500.000 $1,725.000
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
EA 1.000 $75,000.000 $17,000.000 $30,000.000 $100,000.000 $50,000.000 $64,390.000 $56,934.590 $65,000.000 $115,000.000
MOBILIZATION
LS 1.000 $154,870.000 $30,000.000 $116,000.000 $175,000.000 $100,000.000 $200,000.000 $222,154.470 $150,000.000 $300,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 9.000 $5,000.000 $2,400.000 $3,400.000 $6,000.000 $2,500.000 $200.000 $5,629.000 $1,200.000 $8,054.700
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 280.000 $50.000 $105.000 $40.000 $70.000 $50.000 $40.000 $81.190 $65.000 $92.300
CONSTRUCTION EXITS (INSTALL) (TY 2)
SY 156.000 $60.000 $18.000 $30.000 $30.000 $25.000 $20.000 $37.880 $30.000 $69.000
CONSTRUCTION EXITS (REMOVE)
SY 156.000 $26.980 $9.000 $9.000 $10.000 $15.000 $20.000 $11.370 $11.000 $35.700
TEMP SEDMT CONT FENCE (INSTALL)
LF 5,302.000 $4.000 $5.500 $4.000 $7.000 $3.000 $4.000 $4.150 $4.500 $4.200
TEMP SEDMT CONT FENCE (REMOVE)
LF 5,302.000 $1.250 $2.000 $1.000 $0.500 $1.500 $1.000 $1.900 $2.750 $1.800
BIODEG EROSN CONT LOGS (INSTL) (6")
LF 142.000 $2.500 $14.000 $4.000 $10.000 $8.000 $3.000 $10.090 $10.500 $11.300
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 46.000 $8.000 $14.000 $5.000 $20.000 $10.000 $3.000 $19.030 $11.250 $12.400
BIODEG EROSN CONT LOGS (REMOVE)
LF 187.000 $2.000 $7.230 $1.500 $1.000 $2.000 $3.000 $6.640 $6.650 $6.900
CONC CURB (TY II)
LF 190.000 $13.000 $43.000 $30.000 $25.000 $25.000 $70.000 $54.140 $89.000 $53.700
CONC CURB & GUTTER (TY II)
LF 1,760.000 $21.000 $43.000 $28.000 $26.000 $35.000 $30.000 $58.220 $89.000 $34.800
CONCRETE C&G (VALLEY GUTTER)
LF 331.000 $56.000 $43.000 $98.000 $40.000 $35.000 $70.000 $120.820 $92.000 $87.300
INTERSECTIONS (ACP)
SY 416.000 $70.000 $40.000 $95.000 $85.000 $80.000 $60.000 $99.980 $170.000 $157.000
DRIVEWAYS (CONC)
SY 1,067.000 $100.000 $79.000 $85.000 $65.000 $90.000 $130.000 $98.270 $100.000 $124.400
DRIVEWAYS (ACP)
SY 506.000 $38.000 $40.000 $85.000 $65.000 $70.000 $50.000 $76.120 $105.000 $111.100
CONC SIDEWALKS (4")
SY 336.000 $51.000 $72.000 $75.000 $55.000 $54.000 $80.000 $100.360 $125.000 $115.300
CURB RAMPS (TY 1)
EA 3.000 $2,200.000 $1,870.000 $1,950.000 $1,750.000 $2,000.000 $2,220.000 $2,407.130 $3,000.000 $3,000.400
CURB RAMPS (TY 7)
EA 30.000 $2,900.000 $1,870.000 $1,950.000 $1,750.000 $2,000.000 $2,370.000 $3,044.220 $3,700.000 $2,860.400
CONC SIDEWALKS (SPECIAL)
SY 3,718.000 $100.000 $75.000 $68.000 $55.000 $63.000 $90.000 $97.430 $160.000 $101.400
MTL W-BEAM GD FEN (TIM POST)
LF 250.000 $35.000 $34.000 $32.000 $35.000 $35.000 $30.000 $36.280 $35.000 $32.500
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 4.000 $3,500.000 $2,700.000 $1,600.000 $2,000.000 $2,500.000 $1,970.000 $2,420.140 $2,200.000 $2,875.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 2.000 $2,300.000 $1,750.000 $1,800.000 $2,750.000 $2,000.000 $1,500.000 $1,549.480 $1,200.000 $2,443.800
REMOVE METAL BEAM GUARD FENCE
LF 280.000 $30.000 $3.610 $10.000 $50.000 $6.000 $20.000 $5.190 $3.000 $5.800
GUARDRAIL END TREATMENT (INSTALL)
EA 2.000 $4,300.000 $8,500.000 $4,200.000 $4,200.000 $4,000.000 $3,530.000 $3,914.750 $3,400.000 $3,743.300
ALUMINUM SIGNS (TY A)
SF 41.000 $40.000 $37.000 $55.000 $17.000 $50.000 $50.000 $24.360 $30.000 $74.800
IN SM RD SN SUP&AM TYS80(1)SA(P)
EA 36.000 $1,000.000 $1,180.000 $720.000 $750.000 $1,000.000 $970.000 $817.290 $1,000.000 $948.800
IN SM RD SN SUP&AM TYS80(1)SA(P-BM)
EA 10.000 $1,200.000 $1,250.000 $800.000 $1,100.000 $1,000.000 $630.000 $1,055.440 $1,450.000 $1,017.800
REMOVE SM RD SN SUP&AM
EA 17.000 $300.000 $300.000 $200.000 $130.000 $350.000 $150.000 $108.250 $100.000 $212.800
INSTL DEL ASSM (D-SW)SZ 1(BRF)CTB
EA 6.000 $35.000 $18.000 $50.000 $100.000 $25.000 $20.000 $26.520 $50.000 $97.800
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
EA 9.000 $40.000 $61.000 $50.000 $88.000 $75.000 $30.000 $32.480 $60.000 $97.800
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 642.000 $12.000 $15.000 $14.250 $6.120 $7.000 $20.000 $7.040 $18.500 $20.700
REFL PAV MRK TY I (W)(ARROW)(100MIL)
EA 2.000 $100.000 $350.000 $336.000 $204.000 $250.000 $350.000 $243.570 $400.000 $402.500
REFL PAV MRK TY I (W)(WORD)(100MIL)
EA 1.000 $100.000 $350.000 $336.000 $408.000 $500.000 $350.000 $460.060 $475.000 $517.500
ALL-WTHER PM TY I (W)6"(SLD)(100MIL)
LF 183.000 $30.000 $3.370 $3.500 $1.380 $1.500 $3.000 $1.620 $5.750 $6.400
ALL-WTHER PM TY I (W)6"(BRK)(100MIL)
LF 62.000 $30.000 $3.370 $3.500 $1.380 $1.500 $3.000 $1.620 $5.750 $6.400
ALL-WTHER PM TY I (Y)6"(SLD)(100MIL)
LF 121.000 $30.000 $3.370 $3.500 $1.380 $1.500 $3.000 $1.620 $5.750 $6.400
REFL PAV MRK TY I (W)4"(SLD)(100MIL)
LF 422.000 $2.000 $3.370 $3.500 $0.920 $1.250 $3.000 $1.080 $4.000 $4.100
REFL PAV MRK TY I (Y)4"(BRK)(100MIL)
LF 514.000 $2.000 $3.370 $3.500 $0.920 $1.500 $3.000 $1.080 $4.000 $4.100
REFL PAV MRK TY I (Y)4"(SLD)(100MIL)
LF 1,351.000 $2.000 $3.370 $3.500 $0.920 $1.500 $3.000 $1.080 $4.000 $3.500
PRE PM TY B(BL&WH)(ACC PRK)(W/BORDR)LG
EA 1.000 $1,200.000 $520.000 $500.000 $285.600 $350.000 $520.000 $324.750 $1,600.000 $1,725.000
BIRD EXCLUSION METHOD
SF 2,800.000 $8.000 $8.430 $2.500 $1.000 $10.000 $4.000 $10.830 $5.000 $17.300
Totals: $1,926,659.080 $1,627,355.470 $1,753,151.600 $1,783,265.980 $1,949,780.000 $2,254,598.000 $2,338,468.137 $2,879,208.650 $3,376,912.510
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $27,059.34
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $54,118.69
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $27,053.94
Total: $108,231.97