Show Job Controls
Bid Cobra

BEXAR FM 2790 (1741-02-036)

Items: 143

County: BEXAR
Length: N/A
Highway: FM 2790
District: SAN ANTONIO
Control Number: 1741-02-036
DBE Goal: N/A
Project: F 2023(120)
Guaranty: N/A
Time: 255 WORKING DAYS
Engineer's Estimate: $8,152,268.65
Date: 09/07/2022 (3 years ago)
Contract Number: N/A
Type: REHABILITATE EXISTING ROADWAY
Mail/Deliver Bids To: N/A
TIMOTHY PARKER1
MARCO GALINDO
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (8)
E
Engineer's Estimate
$8,152,268.65
$7,692,727.42
Over/Under Est: -5.64% -$459,541.23
$7,997,716.25
Over/Under Est: -1.9% -$154,552.40
Amt Left: 3.96% $304,988.83
Over/Under Est: -0.68% -$55,179.35
Amt Left: 5.26% $404,361.88
Delta: -1.24% -$99,373.05
Over/Under Est: 0.85% $68,891.12
Amt Left: 6.87% $528,432.35
Delta: -1.53% -$124,070.47
$8,305,622.66
Over/Under Est: 1.88% $153,354.01
Amt Left: 7.97% $612,895.24
Delta: -1.03% -$84,462.89
Over/Under Est: 2.48% $202,407.48
Amt Left: 8.6% $661,948.71
Delta: -0.59% -$49,053.47
Over/Under Est: 11.92% $971,909.78
Amt Left: 18.61% $1,431,451.01
Delta: -9.21% -$769,502.30
Over/Under Est: 18.22% $1,485,028.84
Amt Left: 25.28% $1,944,570.07
Delta: -5.62% -$513,119.06
Subcontractor Percentage Amount
TEXAS MATERIALS GROUP, INC. 25.16% $2,075,283.18
LONE STAR EROSION CONTROL 2.08% $171,565.54
FLASHER EQUIPMENT COMPANY 2.03% $167,441.37
DUSTROL, INC. 1.65% $136,097.66
EGGEMEYER LAND CLEARING, LLC 0.28% $23,095.36
THE LEVY COMPANY, INC. 0.11% $9,073.18
ENVIRONMENTAL SAFETY SERVICES, INC. 0.05% $4,124.17
Total: 31.36% $2,586,680.46

Bid Items & Bid Tabulations

143 Total 0 of 143
BEXAR  |  FM 2790  |  SAN ANTONIO  |  1741-02-036  |  09/07/2022  |  $8,152,268.65  |  F 2023(120)  |  REHAB EXIST ROADWAY  |  255 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
CAPITAL EXCAVATION COMPANY
J3 COMPANY, LLC
SALINAS CONSTRUCTION TECHNOLOGIES, LTD.
HARPER BROTHERS CONSTRUCTION LLC
DAN WILLIAMS COMPANY
AUSTIN BRIDGE & ROAD SERVICES, LP
HUNTER INDUSTRIES, LTD.
ACME BRIDGE COMPANY, INC.
PREPARING ROW
STA 84.000 $3,000.000 $2,400.000 $700.000 $205.070 $4,500.000 $2,200.000 $5,000.000 $1,206.360 $1,500.000
PREPARING ROW (TREE) (6" TO 24" DIA)
EA 7.000 $525.000 $640.000 $1,250.000 $1,500.790 $850.000 $1,000.000 $2,320.000 $1,080.000 $1,060.000
REMOVING CONC (MEDIANS)
SY 69.000 $14.000 $30.800 $20.000 $46.850 $10.000 $20.000 $28.300 $30.780 $25.600
REMOVING CONC (SIDEWALK OR RAMP)
SY 131.000 $11.500 $16.700 $10.000 $46.790 $10.000 $15.000 $16.510 $30.780 $22.000
REMOVING CONC (FLUME)
SY 883.850 $13.500 $11.300 $15.000 $21.510 $10.000 $10.000 $14.210 $30.780 $16.400
EXCAVATION (ROADWAY)
CY 19,504.000 $11.500 $16.000 $25.000 $10.830 $17.480 $13.500 $24.500 $23.940 $16.000
EMBANKMENT (FINAL)(DENS CONT)(TY C)
CY 3,737.000 $13.500 $8.100 $10.000 $7.710 $9.000 $16.500 $14.500 $23.940 $16.000
COMPOST MANUF TOPSOIL (4")
SY 25,504.000 $2.500 $2.000 $3.500 $2.220 $3.000 $3.000 $2.430 $1.140 $3.000
DRILL SEEDING (PERM) (RURAL) (SANDY)
SY 25,504.000 $0.200 $0.300 $0.260 $0.290 $0.290 $0.290 $0.260 $0.300 $0.170
DRILL SEED (TEMP)(WARM OR COOL)
SY 25,504.000 $0.150 $0.200 $0.180 $0.200 $0.220 $0.220 $0.180 $0.210 $0.150
VEGETATIVE WATERING
MG 397.000 $25.000 $34.000 $34.840 $41.130 $30.000 $12.000 $20.000 $23.940 $50.800
SOIL RETENTION BLANKETS (CL 1) (TY B)
SY 25,504.000 $1.500 $1.000 $0.900 $1.000 $1.650 $1.650 $0.900 $1.040 $0.900
PROOF ROLLING
HR 26.000 $100.000 $127.000 $75.000 $85.010 $75.000 $65.000 $215.490 $117.000 $91.200
FL BS (CIP)(TY D GR 1-2, OR 5)FINAL POS
CY 8,976.000 $30.000 $58.000 $80.000 $70.180 $65.000 $58.000 $60.000 $70.490 $84.000
LIME TRT (SUBGRADE)(8")
SY 40,391.000 $3.000 $4.200 $8.000 $3.620 $9.000 $2.250 $9.000 $3.510 $2.900
LIME (HYD(SLY OR DRY) COM OR QK(DRY)
TON 970.000 $220.000 $260.000 $275.000 $290.140 $285.000 $300.000 $250.000 $263.520 $300.000
PRIME COAT(MC-30 OR AE-P)
GAL 8,078.000 $3.500 $4.050 $5.000 $5.020 $3.750 $3.750 $4.030 $5.260 $3.950
PLANE ASPH CONC PAV (2")
SY 3,708.000 $5.000 $3.250 $6.000 $3.670 $3.000 $3.500 $5.920 $4.010 $3.150
CUT & RESTORE ASPH PAVING
SY 80.000 $120.000 $63.800 $75.000 $91.100 $185.000 $100.000 $166.300 $500.000 $148.000
TEMPORARY SPL SHORING
SF 72.000 $15.000 $23.050 $85.000 $239.150 $150.000 $110.000 $50.230 $150.000 $33.500
RIPRAP (CONC)(4 IN)
CY 28.000 $360.000 $640.000 $600.000 $889.820 $1,500.000 $600.000 $476.840 $800.000 $707.000
RIPRAP (CONC)(5 IN)
CY 10.000 $375.000 $640.000 $750.000 $1,120.120 $1,500.000 $600.000 $479.520 $750.000 $723.000
RIPRAP (CONC)(DISSIPATER)
CY 3.000 $2,000.000 $3,190.000 $1,000.000 $1,703.520 $1,500.000 $900.000 $1,824.100 $2,000.000 $1,140.000
RIPRAP (MOW STRIP)(4 IN)
CY 43.200 $500.000 $810.000 $750.000 $668.220 $550.000 $625.000 $499.000 $800.000 $715.000
RAIL (TY T402)
LF 175.000 $350.000 $270.000 $275.000 $323.420 $250.000 $275.000 $374.870 $350.000 $373.000
RAIL (TY T631)
LF 125.000 $115.000 $101.000 $220.000 $136.950 $123.000 $130.000 $150.000 $91.950 $130.000
CMP (GAL STL 30 IN)
LF 72.000 $250.000 $151.000 $160.000 $133.650 $200.000 $100.000 $179.490 $147.000 $118.000
CONC BOX CULV (10 FT X 6 FT)
LF 220.000 $705.000 $850.000 $1,100.000 $950.540 $1,070.000 $1,150.000 $1,187.430 $1,417.490 $1,320.000
RC PIPE (CL III)(18 IN)
LF 239.000 $90.000 $81.700 $125.000 $68.800 $120.000 $80.000 $94.560 $103.950 $110.000
RC PIPE (CL III)(24 IN)
LF 255.000 $108.000 $97.600 $130.000 $88.980 $125.000 $80.000 $103.910 $120.750 $129.000
RC PIPE (CL III)(30 IN)
LF 8.000 $115.000 $270.000 $215.000 $169.890 $190.000 $250.000 $338.990 $262.500 $185.000
RC PIPE (CL III)(36 IN)
LF 19.000 $130.000 $201.000 $250.000 $272.300 $350.000 $245.000 $258.540 $278.250 $255.000
JCTBOX(COMPL)(PJB)(6FTX6FT)
EA 1.000 $9,000.000 $9,700.000 $12,500.000 $10,289.860 $15,000.000 $11,000.000 $10,708.570 $14,699.910 $14,100.000
HEADWALL (CH - PW - 0) (DIA= 30 IN)
EA 1.000 $8,700.000 $3,340.000 $10,000.000 $34,706.900 $20,000.000 $8,250.000 $15,916.670 $20,000.000 $6,130.000
HEADWALL (CH - PW - 0) (DIA= 36 IN)
EA 1.000 $9,000.000 $6,700.000 $10,000.000 $17,868.120 $16,000.000 $9,500.000 $16,870.630 $12,000.000 $7,380.000
WINGWALL (PW - 1) (HW=8 FT)
EA 1.000 $30,500.000 $54,000.000 $65,000.000 $70,820.420 $42,000.000 $90,000.000 $25,627.770 $70,000.000 $47,200.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 14.000 $1,300.000 $2,350.000 $2,000.000 $1,478.990 $2,500.000 $1,600.000 $1,812.590 $2,992.480 $1,900.000
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 6.000 $1,800.000 $2,970.000 $2,600.000 $2,783.150 $3,800.000 $2,500.000 $2,306.460 $3,044.980 $2,050.000
CLEAN EXIST CULVERTS
EA 11.000 $1,700.000 $920.000 $1,200.000 $2,407.330 $1,500.000 $1,450.000 $426.430 $2,624.980 $3,800.000
MOBILIZATION
LS 1.000 $743,193.980 $650,000.000 $380,000.000 $625,815.580 $785,000.000 $822,000.000 $800,000.000 $906,311.530 $823,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 16.000 $7,000.000 $4,120.000 $10,000.000 $2,027.620 $5,000.000 $20,000.000 $4,010.260 $7,500.000 $6,000.000
ROCK FILTER DAMS (INSTALL) (TY 1)
LF 160.000 $25.000 $30.700 $28.000 $31.450 $33.500 $34.000 $28.000 $32.470 $29.600
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 130.000 $30.000 $35.050 $32.000 $35.990 $42.000 $42.000 $32.000 $37.110 $33.800
ROCK FILTER DAMS (REMOVE)
LF 290.000 $8.000 $10.950 $10.000 $11.360 $6.500 $6.000 $10.000 $11.600 $10.600
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 702.000 $20.000 $21.900 $20.000 $22.150 $18.000 $18.000 $20.000 $23.190 $21.100
CONSTRUCTION EXITS (REMOVE)
SY 702.000 $6.000 $5.500 $5.000 $5.650 $6.000 $5.500 $5.000 $5.800 $5.300
TEMP SEDMT CONT FENCE (INSTALL)
LF 665.000 $3.000 $3.550 $3.250 $3.730 $4.000 $4.000 $3.250 $3.770 $3.450
TEMP SEDMT CONT FENCE (REMOVE)
LF 665.000 $1.000 $1.350 $1.250 $1.530 $0.500 $0.500 $1.250 $1.450 $1.300
CONSTRUCTING DETOURS
SY 3,164.200 $50.000 $55.000 $48.000 $67.900 $75.000 $34.500 $70.000 $72.900 $93.400
ONE-WAY TRAF CONT (FLAGGER CONT)
HR 512.000 $66.000 $140.000 $40.000 $123.280 $68.000 $30.000 $30.890 $128.700 $140.000
PORT CTB (FUR & INST)(SGL SLOPE)(TY 1)
LF 6,870.000 $30.000 $19.850 $28.000 $40.680 $9.000 $45.000 $50.000 $40.000 $92.400
PORT CTB (MOVE)(SGL SLP)(TY 1)
LF 10,320.000 $4.000 $6.650 $4.000 $9.120 $2.000 $6.000 $5.130 $10.000 $5.900
PORT CTB (REMOVE)(SGL SLP)(TY 1)
LF 6,870.000 $6.000 $18.000 $12.000 $10.230 $13.000 $12.000 $9.020 $10.000 $14.500
CONC CURB (TY II)
LF 682.000 $18.000 $25.500 $20.000 $15.340 $35.000 $24.000 $16.000 $32.000 $27.700
CONC CURB (SLOTTED)
LF 214.000 $32.000 $76.900 $25.000 $30.540 $50.000 $26.000 $75.000 $40.000 $49.100
DRIVEWAYS (CONC)
SY 90.000 $62.000 $151.000 $120.000 $153.070 $105.000 $95.000 $84.090 $125.000 $167.000
DRIVEWAYS AND TURNOUTS (ACP)
SY 1,871.000 $35.000 $36.450 $70.000 $61.580 $40.000 $30.000 $77.640 $49.500 $35.700
CONC SIDEWALKS (4")
SY 456.000 $45.000 $63.900 $55.000 $30.580 $65.000 $54.000 $71.090 $70.000 $87.400
CURB RAMPS (TY 1)
EA 1.000 $1,950.000 $2,040.000 $1,500.000 $2,950.880 $2,700.000 $1,300.000 $2,166.530 $2,500.000 $1,810.000
CURB RAMPS (TY 3)
EA 1.000 $2,000.000 $7,300.000 $1,500.000 $3,429.340 $2,500.000 $1,300.000 $2,166.530 $3,400.000 $1,940.000
CURB RAMPS (TY 7)
EA 1.000 $2,000.000 $3,740.000 $1,500.000 $2,923.380 $2,800.000 $1,300.000 $2,166.530 $3,400.000 $2,210.000
CURB RAMPS (TY 22)
EA 1.000 $2,500.000 $2,020.000 $2,000.000 $4,345.390 $4,500.000 $4,000.000 $2,666.530 $4,600.000 $2,550.000
CONC DIRECTIONAL ISLAND
SY 194.000 $85.000 $102.000 $70.000 $139.970 $85.000 $85.000 $34.090 $125.000 $78.400
MTL W-BEAM GD FEN (TIM POST)
LF 462.500 $20.000 $32.450 $35.000 $32.670 $30.000 $35.000 $29.600 $24.440 $31.300
MTL THRIE-BEAM GD FEN (TIM POST)
LF 2.000 $40.000 $2,340.000 $2,135.000 $4,042.450 $3,650.000 $2,500.000 $2,135.000 $2,385.820 $2,610.000
REMOVE METAL BEAM GUARD FENCE
LF 325.000 $3.000 $2.200 $2.000 $3.620 $3.000 $5.500 $2.000 $2.000 $2.100
REMOVE TERMINAL ANCHOR SECTION
EA 2.000 $275.000 $380.000 $350.000 $354.150 $275.000 $195.000 $350.000 $455.470 $370.000
GUARDRAIL END TREATMENT (INSTALL)
EA 2.000 $3,000.000 $3,400.000 $3,105.000 $3,852.150 $3,455.000 $4,000.000 $3,105.000 $3,204.540 $3,280.000
GUARDRAIL END TREATMENT (REMOVE)
EA 2.000 $400.000 $490.000 $450.000 $1,619.150 $1,425.000 $400.000 $450.000 $355.470 $475.000
CRASH CUSH ATTEN (DES SOURCE)
EA 30.000 $3,500.000 $550.000 $1,000.000 $2,808.440 $2,550.000 $10,000.000 $500.000 $2,689.130 $528.000
CRASH CUSH ATTEN (MOVE & RESET)
EA 24.000 $625.000 $550.000 $500.000 $1,057.910 $950.000 $650.000 $500.000 $1,150.190 $528.000
CRASH CUSH ATTEN (REMOVE)
EA 30.000 $1,000.000 $550.000 $500.000 $1,055.330 $950.000 $1,000.000 $500.000 $1,100.000 $528.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 9.000 $550.000 $630.000 $568.000 $636.280 $568.000 $546.000 $568.000 $568.000 $600.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 11.000 $600.000 $750.000 $685.000 $762.890 $685.000 $660.000 $685.000 $685.000 $723.000
IN SM RD SN SUP&AM TYS80(1)SA(T)
EA 3.000 $750.000 $980.000 $892.000 $991.530 $892.000 $910.000 $892.000 $892.000 $942.000
IN SM RD SN SUP&AM TYS80(1)SA(T-2EXT)
EA 1.000 $900.000 $1,430.000 $1,295.000 $1,434.830 $1,295.000 $1,205.000 $1,295.000 $1,295.000 $1,370.000
IN SM RD SN SUP&AM TYS80(1)SA(U)
EA 1.000 $1,000.000 $1,240.000 $1,122.000 $1,244.530 $1,122.000 $1,050.000 $1,122.000 $1,122.000 $1,180.000
IN SM RD SN SUP&AM TYS80(1)SA(U-1EXT)
EA 1.000 $1,000.000 $1,650.000 $1,497.000 $1,657.030 $1,497.000 $1,095.000 $1,497.000 $1,497.000 $1,580.000
REMOVE SM RD SN SUP&AM
EA 23.000 $90.000 $148.000 $134.000 $156.380 $134.000 $50.000 $134.000 $134.000 $142.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 10.000 $25.000 $35.250 $32.000 $45.530 $32.000 $40.000 $32.000 $32.000 $33.800
INSTL OM ASSM (OM-2Z)(WFLX)SRF(BI)
EA 2.000 $70.000 $162.000 $147.000 $172.030 $147.000 $94.000 $147.000 $147.000 $155.000
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
LF 33,661.000 $0.250 $0.400 $0.350 $0.390 $0.350 $0.250 $0.350 $0.350 $0.370
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 33,878.000 $0.250 $0.400 $0.350 $0.390 $0.350 $0.250 $0.350 $0.350 $0.370
WK ZN PAV MRK REMOV (REFL) TY I-A
EA 1,454.000 $3.400 $3.850 $3.500 $3.990 $3.500 $5.250 $3.500 $3.500 $3.700
WK ZN PAV MRK REMOV (REFL) TY II-A-A
EA 2,897.000 $5.000 $3.850 $3.500 $3.920 $3.500 $5.250 $3.500 $3.500 $3.700
WK ZN PAV MRK REMOV (W)4"(SLD)
LF 29,071.000 $0.500 $0.650 $0.600 $0.670 $0.600 $0.850 $0.600 $0.600 $0.630
WK ZN PAV MRK REMOV (Y)4"(SLD)
LF 28,970.000 $0.500 $0.650 $0.600 $0.670 $0.600 $0.850 $0.600 $0.600 $0.630
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 1,013.000 $1.750 $1.600 $2.500 $1.490 $1.000 $2.000 $2.000 $1.550 $1.650
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 1,013.000 $1.750 $1.600 $2.500 $1.490 $1.000 $2.000 $2.000 $1.550 $1.650
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 4,795.000 $1.000 $1.100 $1.000 $1.120 $1.000 $1.700 $1.000 $1.000 $1.050
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 298.000 $5.000 $7.700 $7.000 $8.050 $7.000 $10.000 $7.000 $7.000 $7.400
REFL PAV MRK TY I (W)(ARROW)(100MIL)
EA 10.000 $150.000 $193.000 $175.000 $202.830 $175.000 $150.000 $175.000 $175.000 $185.000
REFL PAV MRK TY I (W)(WORD)(100MIL)
EA 10.000 $150.000 $209.000 $190.000 $219.330 $190.000 $200.000 $190.000 $190.000 $201.000
REF PAV MRK TY I(W)36"(YLD TRI)(100MIL)
EA 6.000 $50.000 $44.050 $40.000 $61.220 $40.000 $50.000 $40.000 $40.000 $42.200
REFL PAV MRK TY I(Y)(MED NOSE)(100MIL)
EA 1.000 $300.000 $500.000 $450.000 $598.310 $450.000 $800.000 $450.000 $450.000 $475.000
RE PM W/RET REQ TY I (W)4"(BRK)(100MIL)
LF 30.000 $0.350 $0.550 $0.490 $3.980 $0.490 $3.000 $0.490 $0.490 $0.200
RE PM W/RET REQ TY I (W)6"(SLD)(100MIL)
LF 2,469.000 $1.000 $0.650 $0.600 $0.700 $0.600 $1.000 $0.600 $0.600 $0.630
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 14,234.000 $0.350 $0.450 $0.400 $0.450 $0.400 $0.700 $0.400 $0.400 $0.420
REF PROF PAV MRK TY I(W)6"(SLD)(100MIL)
LF 13,821.000 $1.000 $0.850 $0.750 $2.130 $0.750 $1.250 $0.750 $0.750 $0.790
REF PROF PAV MRK TY I(Y)4"(BRK)(100MIL)
LF 220.000 $0.500 $0.650 $0.600 $1.130 $0.600 $3.000 $0.600 $0.600 $0.630
REF PROF PAV MRK TY I(Y)4"(SLD)(100MIL)
LF 5,413.000 $0.500 $0.650 $0.600 $0.680 $0.600 $1.200 $0.600 $0.600 $0.630
REFL PAV MRKR TY I-C
EA 427.000 $3.500 $5.500 $5.000 $5.740 $5.000 $4.500 $5.000 $5.000 $5.300
REFL PAV MRKR TY II-A-A
EA 805.000 $3.000 $6.050 $5.500 $6.310 $5.000 $4.000 $5.500 $5.500 $5.800
REFL PAV MRKR TY II-C-R
EA 1.000 $3.000 $6.050 $5.500 $16.380 $6.000 $10.000 $5.500 $5.500 $5.800
ELIM EXT PAV MRK & MRKS (4")
LF 27,676.000 $0.500 $0.450 $0.410 $0.460 $0.450 $0.850 $0.410 $0.410 $0.430
HYDROSTATIC PRESSURE TEST
EA 2.000 $3,000.000 $6,700.000 $5,000.000 $2,993.310 $6,620.000 $2,750.000 $4,043.950 $16,000.000 $8,300.000
TRENCH EXCAVATION PROTECTION
LF 5,487.000 $5.000 $4.800 $6.500 $3.210 $3.000 $1.000 $5.750 $5.000 $23.700
FLOWABLE FILL BACKFILL
CY 216.000 $180.000 $184.000 $230.000 $229.660 $215.000 $200.000 $214.430 $175.000 $214.000
TEMPORARY BLOW-OFF(COMPLETE)(2")
EA 1.000 $2,350.000 $2,550.000 $6,000.000 $4,520.810 $2,800.000 $2,700.000 $4,854.170 $3,300.000 $8,900.000
DUCTILE IRON FITTINGS
TON 3.100 $12,500.000 $18,500.000 $24,000.000 $15,350.630 $8,500.000 $30,000.000 $22,036.210 $13,000.000 $12,900.000
CONCRETE SADDLE
CY 4.000 $400.000 $940.000 $650.000 $489.130 $400.000 $300.000 $627.260 $800.000 $237.000
DUCTILE IRON PIPE (16")
LF 5,113.000 $300.000 $164.000 $155.000 $181.530 $155.000 $140.000 $146.050 $165.000 $225.000
ADJUST VALVE BOX
EA 3.000 $600.000 $1,790.000 $2,100.000 $345.350 $750.000 $1,500.000 $1,986.340 $1,800.000 $2,610.000
RECONNECT SHORT SERVICE (1")
EA 1.000 $2,500.000 $2,910.000 $5,000.000 $3,598.920 $1,500.000 $3,000.000 $3,666.170 $5,500.000 $4,510.000
GATE VALVE & BOX (COMPLETE)(16")
EA 7.000 $9,500.000 $11,000.000 $14,000.000 $14,587.160 $13,000.000 $13,500.000 $13,170.170 $11,250.000 $17,300.000
TIE-IN (COMPLETE)(16")
EA 1.000 $8,500.000 $7,800.000 $9,000.000 $8,760.890 $9,000.000 $10,500.000 $7,391.740 $10,000.000 $9,490.000
NEW METER BOX
EA 1.000 $925.000 $670.000 $500.000 $712.030 $750.000 $1,450.000 $371.840 $1,500.000 $1,900.000
FIRE HYDRANT ASSEMBLY
EA 9.000 $6,500.000 $7,500.000 $9,500.000 $7,274.640 $8,500.000 $9,000.000 $8,299.370 $9,500.000 $12,600.000
WATER MAIN BREAKS LEAK REPAIR
EA 1.000 $1,000.000 $15,900.000 $7,000.000 $6,957.840 $3,000.000 $5,500.000 $5,053.750 $6,500.000 $9,610.000
WATER SERVICE LINE BREAKS LEAK REPAIR
EA 1.000 $1,000.000 $3,110.000 $5,000.000 $4,978.920 $1,500.000 $4,500.000 $2,885.650 $5,500.000 $3,920.000
STEEL CASING (30")(OPEN CUT)
LF 276.000 $300.000 $290.000 $220.000 $346.760 $275.000 $325.000 $196.260 $465.000 $480.000
WATER MAIN REMOVAL (16" & SMALLER)
LF 5,296.000 $35.000 $24.700 $16.000 $29.330 $16.100 $8.000 $14.560 $47.500 $42.100
AIR RELEASE VALVE (COMPLETE)(2")
EA 1.000 $14,000.000 $6,800.000 $42,000.000 $23,150.340 $24,000.000 $20,000.000 $39,289.540 $22,000.000 $26,900.000
CARRIER PIPE (IN CASING) (DI) (24")
LF 79.000 $305.000 $320.000 $220.000 $542.220 $275.000 $375.000 $206.950 $245.000 $1,140.000
CARRIER PIPE (OPEN CUT) (DI) (16")
LF 276.000 $200.000 $198.000 $180.000 $242.020 $215.000 $200.000 $171.310 $215.000 $344.000
GROUT ABANDONMENT WATER MAIN (16")
LF 40.000 $24.000 $85.100 $160.000 $147.460 $120.000 $230.000 $152.540 $165.000 $59.300
TEMPORARY BLOW-OFF (COMPLETE)(4 IN)
EA 1.000 $6,185.000 $13,500.000 $24,000.000 $16,550.020 $14,000.000 $13,000.000 $22,657.540 $15,000.000 $20,300.000
BUTTERFLY VALVE AND BOX (COMPL) (24")
EA 1.000 $24,000.000 $32,000.000 $38,000.000 $39,005.560 $33,000.000 $40,000.000 $35,619.800 $35,000.000 $43,900.000
TIE-IN (COMPLETE) (24")
EA 1.000 $15,000.000 $15,700.000 $10,000.000 $10,764.640 $10,500.000 $6,300.000 $8,679.530 $12,500.000 $16,800.000
24" DUCTILE IRON PIPE
LF 19.000 $450.000 $310.000 $300.000 $498.450 $225.000 $350.000 $272.290 $250.000 $439.000
STEEL CASING (42") (OPEN CUT)
LF 79.000 $430.000 $570.000 $245.000 $591.270 $550.000 $600.000 $231.900 $840.000 $819.000
WATER MAIN REMOVAL (24")
LF 118.000 $59.000 $52.600 $28.000 $63.090 $26.000 $30.000 $24.720 $70.000 $89.000
TREE TRIMMING / BRUSH REMOVAL
MI 0.240 $25,000.000 $3,860.000 $20,000.000 $20,481.830 $36,869.000 $90,000.000 $2,000.000 $16,200.000 $8,447.920
D-GR HMA TY-B PG64-22
TON 13,707.060 $105.000 $95.000 $90.000 $89.600 $90.000 $92.000 $85.000 $102.420 $92.900
TACK COAT
GAL 10,713.000 $2.750 $1.100 $5.000 $5.660 $1.000 $1.000 $4.300 $4.240 $1.050
D-GR HMA TY-C SAC-B PG70-22 (EXEMPT)
TON 203.900 $155.000 $173.000 $165.000 $165.780 $160.000 $175.000 $213.350 $140.040 $169.000
SP MIXES SP-C SAC-B PG70-22
TON 5,645.350 $110.000 $125.000 $115.000 $107.990 $117.000 $125.000 $97.000 $114.300 $123.000
TACK COAT
GAL 9,042.000 $3.000 $1.100 $5.000 $4.720 $1.000 $1.000 $4.350 $4.280 $1.050
BONDING COURSE
GAL 12,570.000 $3.000 $1.100 $5.000 $5.030 $1.000 $1.000 $4.030 $4.280 $1.050
GEOGRID BASE REINFORCEMENT (TY II)
SY 40,391.000 $1.500 $1.500 $1.750 $1.730 $2.000 $2.000 $1.320 $1.390 $2.200
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $13,000.000 $20,900.000 $9,000.000 $16,172.890 $9,500.000 $15,000.000 $15,000.000 $10,161.750 $13,300.000
TMA (STATIONARY)
DAY 27.000 $170.000 $14.350 $350.000 $190.640 $350.000 $250.000 $350.000 $355.660 $185.000
TMA (MOBILE OPERATION)
HR 234.000 $150.000 $38.700 $90.000 $198.000 $67.000 $55.000 $50.000 $101.620 $90.200
Totals: $8,152,268.655 $7,692,727.430 $7,997,716.250 $8,097,089.339 $8,221,159.770 $8,305,622.660 $8,354,676.144 $9,124,178.449 $9,637,297.495