Show Job Controls
Bid Cobra

ATASCOSA UA 281 (0073-13-012)

Items: 101

County: ATASCOSA
Length: N/A
Highway: UA 281
District: SAN ANTONIO
Control Number: 0073-13-012
DBE Goal: 500.0%
Project: BR 2024(971)
Guaranty: N/A
Time: 254 WORKING DAYS
Engineer's Estimate: $5,427,205.24
Date: 05/03/2024 (2 years ago)
Contract Number: N/A
Type: BRIDGE REPLACEMENT
Mail/Deliver Bids To: N/A
FRANCES MERECKA
ENRIQUE MANUEL GONZALEZ
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (7)
E
Engineer's Estimate
$5,427,205.24
1
$4,880,363.38
Over/Under Est: -10.08% -$546,841.86
Over/Under Est: -9.96% -$540,451.03
Amt Left: 0.13% $6,390.83
Over/Under Est: -6.6% -$358,293.15
Amt Left: 3.86% $188,548.71
Delta: -3.73% -$182,157.88
Over/Under Est: -6.41% -$347,746.85
Amt Left: 4.08% $199,095.01
Delta: -0.21% -$10,546.30
$5,241,890.50
Over/Under Est: -3.41% -$185,314.74
Amt Left: 7.41% $361,527.12
Delta: -3.20% -$162,432.11
Over/Under Est: 0% -$205.24
Amt Left: 11.2% $546,636.62
Delta: -3.53% -$185,109.50
Over/Under Est: 13.05% $708,388.00
Amt Left: 25.72% $1,255,229.86
Delta: -13.06% -$708,593.24
Subcontractor Percentage Amount
GREGORY PILE DRIVING, INC. 5.06% $246,946.39
LONE STAR EROSION CONTROL 2.49% $121,521.05
LONE STAR EROSION CONTROL 2.38% $116,152.65
TORO BRAVO CONSTRUCTION, LLC 1.16% $56,612.22
FLASHER EQUIPMENT COMPANY 0.73% $35,626.65
MURRAY CONSTRUCTION 0.62% $30,258.25
Total: 12.44% $607,117.21

Bid Items & Bid Tabulations

101 Total 0 of 101
ATASCOSA  |  UA 281  |  SAN ANTONIO  |  0073-13-012  |  05/03/2024  |  $5,427,205.24  |  BR 2024(971)  |  BRIDGE REPL  |  254 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
RELMCO, INC.
DEAN WORD COMPANY, LTD.
ACME BRIDGE COMPANY, INC.
SALINAS CONSTRUCTION TECHNOLOGIES, LTD.
J3 COMPANY, LLC
HARPER BROTHERS CONSTRUCTION LLC
HUNTER INDUSTRIES, LTD.
PREPARING ROW
STA 14.000 $3,390.000 $10,000.000 $7,000.000 $3,250.000 $3,775.190 $2,500.000 $18,000.000 $4,600.000
REMOVING CONC (RIPRAP)
SY 674.000 $25.230 $20.000 $20.040 $18.700 $20.440 $20.000 $15.000 $31.500
REMOVING CONC (FLUME)
SY 34.000 $25.000 $20.000 $16.640 $42.600 $36.700 $20.000 $32.000 $31.500
REMOVING CONCRETE(MOW STRIP)
LF 1,139.000 $15.930 $8.000 $5.030 $7.300 $9.640 $6.000 $8.000 $21.000
EXCAVATION (ROADWAY)
CY 4,612.000 $33.250 $15.000 $15.620 $22.200 $21.050 $30.000 $20.000 $24.700
EMBANKMENT (FINAL)(ORD COMP)(TY C)
CY 2,039.000 $23.850 $25.000 $9.930 $27.300 $10.860 $40.000 $20.000 $24.700
COMPOST MANUF TOPSOIL (4")
SY 25,017.000 $7.410 $1.610 $3.040 $2.150 $1.560 $2.000 $2.460 $1.520
BROADCAST SEED (TEMP)(WARM OR COOL)
SY 25,017.000 $0.340 $0.150 $0.320 $0.150 $0.160 $0.250 $0.210 $0.150
VEGETATIVE WATERING
MG 392.000 $120.970 $40.000 $23.200 $36.700 $29.330 $35.000 $22.000 $24.500
SOIL RETENTION BLANKETS (CL 2) (TY F)
SY 25,017.000 $2.590 $0.990 $2.380 $0.990 $0.980 $1.000 $1.010 $0.930
PROOF ROLLING
HR 16.000 $107.460 $100.000 $77.970 $89.000 $79.390 $90.000 $81.000 $237.600
FL BS (CIP)(TY D GR 1-2, OR 5)FINAL POS
CY 496.000 $116.340 $100.000 $120.000 $134.000 $114.830 $120.000 $88.000 $181.850
PRIME COAT(MC-30 OR AE-P)
GAL 297.000 $11.190 $5.500 $9.380 $14.000 $8.920 $8.000 $5.000 $15.100
PLANE ASPH CONC PAV (2")
SY 6,068.000 $2.530 $3.300 $2.110 $3.200 $3.970 $4.000 $3.000 $5.740
CEM STABIL BKFL
CY 232.000 $217.560 $175.000 $200.270 $267.000 $155.640 $200.000 $222.000 $225.000
TEMPORARY SPL SHORING
SF 1,834.000 $58.770 $28.000 $39.060 $42.300 $51.160 $72.000 $50.000 $105.410
DRILL SHAFT (18 IN)
LF 120.000 $158.680 $155.000 $130.300 $114.000 $141.990 $250.000 $230.000 $113.150
DRILL SHAFT (36 IN)
LF 1,278.000 $355.320 $265.000 $265.140 $250.000 $255.550 $340.000 $375.000 $307.090
CL C CONC (ABUT)
CY 70.500 $1,633.650 $1,314.600 $1,488.960 $1,340.000 $1,297.930 $1,200.000 $1,500.000 $2,000.000
CL C CONC (CAP)
CY 111.500 $1,610.310 $1,639.400 $2,463.260 $1,660.000 $2,186.770 $1,800.000 $1,800.000 $2,000.000
CL C CONC (COLUMN)
CY 69.000 $2,736.620 $1,209.600 $1,435.500 $1,640.000 $2,174.210 $1,400.000 $1,800.000 $2,000.000
REINF CONC SLAB
SF 29,000.000 $23.960 $24.080 $27.000 $26.700 $29.130 $26.000 $27.000 $36.000
APPROACH SLAB
CY 77.000 $872.350 $1,003.800 $650.620 $858.000 $869.440 $750.000 $900.000 $750.000
PRESTR CONC GIRDER (TX46)
LF 4,039.000 $229.490 $185.000 $201.590 $227.000 $201.520 $200.000 $192.000 $205.000
RIPRAP (CONC)(CL B)(RR8&RR9)
CY 215.000 $385.360 $465.000 $547.930 $610.000 $621.480 $500.000 $750.000 $760.000
RIPRAP (MOW STRIP)(4 IN)
CY 54.000 $759.130 $475.000 $540.400 $772.000 $796.320 $700.000 $627.000 $637.210
RAIL (TY T223)
LF 1,224.000 $188.310 $137.200 $167.210 $116.000 $178.610 $120.000 $95.000 $164.510
SEALED EXPANSION JOINT (4 IN) (SEJ - M)
LF 196.000 $257.410 $195.000 $210.710 $235.000 $189.350 $220.000 $175.000 $75.730
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
EA 1.000 $33,340.600 $65,000.000 $45,152.570 $74,100.000 $49,964.130 $50,000.000 $20,236.910 $139,591.670
REMOV STR (BRIDGE 100 - 499 FT LENGTH)
EA 1.000 $88,474.500 $235,000.000 $151,663.410 $165,000.000 $181,365.990 $220,000.000 $250,000.000 $139,591.670
REMOV STR (SMALL FENCE)
LF 588.000 $3.900 $6.000 $5.290 $2.000 $5.530 $2.000 $8.000 $9.260
MOBILIZATION
LS 1.000 $398,460.690 $450,000.000 $470,000.000 $433,000.000 $565,239.560 $500,000.000 $523,000.000 $605,116.780
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 16.000 $6,267.870 $5,500.000 $1,623.310 $3,020.000 $1,973.180 $7,500.000 $8,250.000 $12,000.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 450.000 $45.000 $31.801 $51.290 $31.800 $31.300 $32.000 $46.000 $29.950
ROCK FILTER DAMS (INSTALL) (TY 3)
LF 50.000 $94.000 $93.960 $142.410 $94.100 $91.810 $90.000 $128.000 $88.490
ROCK FILTER DAMS (REMOVE)
LF 500.000 $15.910 $14.360 $15.390 $14.400 $13.920 $15.000 $14.000 $13.530
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 567.000 $23.310 $27.060 $26.420 $27.100 $26.020 $26.000 $24.000 $25.490
CONSTRUCTION EXITS (REMOVE)
SY 567.000 $11.890 $10.270 $8.600 $10.300 $9.990 $10.000 $8.000 $9.680
CONSTRUCTION PERIMETER FENCE
LF 1,368.000 $3.520 $18.000 $4.180 $4.250 $4.030 $5.000 $4.000 $10.360
TEMP SEDMT CONT FENCE (INSTALL)
LF 1,372.000 $4.780 $2.880 $4.330 $2.900 $2.830 $3.000 $4.000 $2.710
TEMP SEDMT CONT FENCE (REMOVE)
LF 1,372.000 $1.360 $1.570 $0.550 $1.550 $1.580 $1.500 $1.560 $1.480
ONE-WAY TRAF CONT (PILOT CAR)
HR 100.000 $292.030 $80.000 $173.400 $234.000 $122.600 $100.000 $115.000 $198.000
ONE-WAY TRAF CONT (PORT TRAF SIG)
MO 15.000 $5,657.470 $2,500.000 $4,476.550 $4,760.000 $3,886.400 $4,000.000 $5,811.000 $2,800.000
PORT CTB (FUR & INST)(SGL SLOPE)(TY 1)
LF 1,440.000 $60.060 $28.000 $25.450 $57.300 $28.710 $35.000 $23.000 $48.000
PORT CTB (MOVE)(SGL SLP)(TY 1)
LF 1,170.000 $23.520 $8.000 $2.160 $5.800 $11.900 $10.000 $9.000 $26.000
PORT CTB (REMOVE)(SGL SLP)(TY 1)
LF 1,440.000 $26.110 $20.000 $13.100 $21.700 $13.370 $20.000 $18.000 $20.000
DRIVEWAYS (ACP)(TYPE 1)
SY 110.000 $59.140 $105.000 $65.940 $139.000 $89.290 $140.000 $86.000 $55.200
MTL W-BEAM GD FEN (TIM POST)
LF 950.000 $29.150 $25.330 $27.770 $25.400 $24.290 $28.000 $25.000 $26.800
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 4.000 $1,979.370 $1,580.200 $2,443.990 $2,000.000 $1,534.800 $2,400.000 $1,529.500 $2,036.690
REMOVE METAL BEAM GUARD FENCE
LF 1,175.000 $2.320 $4.400 $2.780 $4.500 $4.360 $6.000 $3.000 $0.700
RM MTL BM GD FEN TRANS (T101)
EA 4.000 $264.000 $254.320 $277.690 $255.000 $269.190 $300.000 $246.080 $535.970
GUARDRAIL END TREATMENT (INSTALL)
EA 3.000 $3,115.870 $2,409.360 $3,332.430 $2,420.000 $2,335.080 $2,800.000 $2,331.310 $3,215.830
GUARDRAIL END TREATMENT (REMOVE)
EA 4.000 $286.950 $127.160 $277.690 $128.000 $147.810 $200.000 $123.040 $375.180
CRASH CUSH ATTEN (MOVE & RESET)
EA 2.000 $894.290 $572.220 $178.110 $574.000 $599.060 $750.000 $553.690 $2,143.890
CRASH CUSH ATTEN (REMOVE)
EA 6.000 $298.890 $423.870 $324.400 $425.000 $422.220 $750.000 $410.140 $1,071.940
CRASH CUSH ATTEN (INSTL)(R)(N)(TL3)
EA 1.000 $22,500.000 $28,500.000 $28,363.310 $31,200.000 $6,930.700 $30,000.000 $30,334.450 $27,870.520
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
EA 6.000 $10,000.000 $7,200.000 $7,722.700 $8,160.000 $7,782.690 $8,500.000 $7,871.840 $8,039.570
WIRE FENCE (TY C)
LF 646.000 $20.000 $20.000 $38.230 $12.700 $17.430 $20.000 $18.000 $17.150
GATE (TY 1)
EA 2.000 $1,913.500 $2,000.000 $2,804.820 $2,120.000 $1,441.440 $2,000.000 $1,600.000 $1,071.940
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 18.000 $748.580 $797.500 $805.340 $584.000 $709.990 $700.000 $725.000 $546.690
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 5.000 $961.630 $825.000 $833.100 $676.000 $803.320 $800.000 $750.000 $632.450
IN SM RD SN SUP&AM TYS80(1)SA(U)
EA 3.000 $1,220.000 $1,017.500 $1,027.490 $1,030.000 $992.320 $1,000.000 $925.000 $964.750
IN SM RD SN SUP&AM TYS80(1)SA(U-1EXT)
EA 4.000 $1,274.000 $1,100.000 $1,110.800 $1,150.000 $1,155.070 $1,100.000 $1,000.000 $1,071.940
IN SM RD SN SUP&AM TYS80(1)SA(U-2EXT)
EA 1.000 $1,380.000 $1,210.000 $1,221.900 $1,430.000 $1,207.570 $1,200.000 $1,100.000 $1,339.930
IN SM RD SN SUP&AM TYS80(1)SA(U-WC)
EA 1.000 $1,400.000 $1,320.000 $1,332.960 $1,320.000 $1,086.820 $1,100.000 $1,200.000 $1,232.730
REMOVE SM RD SN SUP&AM
EA 34.000 $110.380 $110.000 $111.090 $74.500 $122.690 $110.000 $100.000 $69.680
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
EA 14.000 $33.250 $30.800 $22.210 $28.600 $33.480 $20.000 $28.000 $26.800
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 13.000 $34.360 $38.500 $26.660 $40.100 $34.640 $20.000 $35.000 $37.520
WK ZN PAV MRK NON-REMOV (Y)6"(SLD)
LF 572.000 $0.240 $1.590 $1.110 $1.550 $1.710 $2.000 $1.450 $1.450
WK ZN PAV MRK REMOV (W)6"(SLD)
LF 5,190.000 $0.870 $1.590 $1.110 $1.550 $1.540 $2.000 $1.450 $1.450
WK ZN PAV MRK REMOV (W)24"(SLD)
LF 24.000 $9.030 $13.200 $3.330 $12.700 $17.000 $20.000 $12.000 $12.000
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 88.000 $1.270 $4.400 $5.670 $1.750 $1.620 $3.000 $2.000 $1.630
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 852.000 $1.550 $4.400 $1.660 $1.750 $1.550 $3.000 $2.000 $1.630
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 430.000 $1.770 $2.200 $3.180 $2.100 $2.350 $2.000 $2.000 $2.000
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 59.000 $10.250 $13.750 $6.050 $13.200 $14.920 $20.000 $13.000 $12.500
REFL PAV MRK TY I (W)(ARROW)(100MIL)
EA 3.000 $185.920 $233.200 $188.830 $224.000 $257.830 $225.000 $212.000 $212.000
REFL PAV MRK TY I (W)(WORD)(100MIL)
EA 3.000 $207.430 $247.500 $205.510 $238.000 $271.480 $225.000 $225.000 $225.000
PAVEMENT SEALER 6"
LF 7,962.000 $0.600 $0.600 $0.550 $0.580 $0.590 $0.750 $0.550 $0.550
PAVEMENT SEALER 8"
LF 430.000 $1.710 $1.150 $0.590 $1.100 $1.350 $1.500 $1.050 $1.050
PAVEMENT SEALER (ARROW)
EA 3.000 $67.370 $66.000 $55.530 $63.500 $98.230 $100.000 $60.000 $60.000
PAVEMENT SEALER (WORD)
EA 3.000 $72.090 $66.000 $61.080 $63.500 $98.230 $100.000 $60.000 $60.000
REF PROF PAV MRK TY I(W)6"(SLD)(100MIL)
LF 3,700.000 $2.290 $1.810 $2.220 $1.750 $1.760 $1.750 $1.650 $1.650
REF PROF PAV MRK TY I(Y)6"(SLD)(100MIL)
LF 4,262.000 $1.110 $1.810 $2.220 $1.750 $1.760 $1.750 $1.650 $1.650
REFL PAV MRKR TY I-C
EA 22.000 $5.830 $8.800 $5.550 $8.500 $13.200 $10.000 $8.000 $8.000
REFL PAV MRKR TY II-A-A
EA 124.000 $8.190 $8.250 $5.550 $7.900 $8.730 $10.000 $8.000 $7.500
ELIM EXT PAV MRK & MRKS (4")
LF 4,089.000 $0.840 $1.150 $0.490 $2.150 $1.130 $1.250 $1.050 $1.050
ELIM EXT PAV MRK & MRKS (8")
LF 287.000 $1.800 $1.980 $0.540 $4.150 $2.260 $2.000 $1.800 $1.800
FULL - WIDTH MOWING
CYC 6.000 $993.670 $3,500.000 $722.010 $1,530.000 $1,863.540 $2,400.000 $2,345.000 $4,000.000
LITTER REMOVAL
CYC 16.000 $695.580 $2,000.000 $138.850 $912.000 $1,165.980 $500.000 $1,426.000 $2,000.000
DEBRIS REMOVAL (CNTR MEDIANS/MAINLANES)
CYC 16.000 $183.820 $2,000.000 $722.020 $912.000 $1,165.980 $1,000.000 $1,426.000 $2,000.000
CLEANING / SWEEPING (OUTSIDE MAIN LANE)
CYC 16.000 $314.620 $2,000.000 $722.020 $847.000 $858.470 $1,200.000 $1,245.000 $2,000.000
TREE AND BRUSH REMOVAL
AC 4.000 $10,000.000 $3,500.000 $3,127.150 $16,500.000 $4,343.250 $10,000.000 $6,936.060 $22,000.000
D-GR HMA TY-B PG64-22 (EXEMPT)
TON 418.000 $129.670 $165.000 $160.000 $159.000 $155.300 $180.000 $150.000 $232.100
D-GR HMA TY-C SAC-A PG76-22 (EXEMPT)
TON 1,026.000 $150.000 $192.500 $145.000 $185.000 $137.050 $190.000 $175.000 $178.200
TACK COAT
GAL 205.000 $4.760 $4.400 $9.080 $4.250 $9.730 $6.000 $4.000 $3.560
UNDERSEAL COURSE
GAL 1,089.000 $4.720 $4.950 $5.240 $4.750 $12.110 $6.000 $5.000 $6.800
INSTALL BRIDGE IDENTIFICATION NUMBERS
EA 2.000 $447.150 $350.000 $213.770 $399.000 $945.350 $500.000 $748.000 $500.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 342.000 $168.560 $200.000 $33.150 $76.100 $46.710 $110.000 $53.000 $166.700
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $12,878.830 $15,000.000 $11,494.340 $13,800.000 $19,748.420 $4,000.000 $18,000.000 $15,267.810
TMA (STATIONARY)
DAY 4.000 $235.000 $300.000 $315.080 $235.000 $741.620 $750.000 $417.000 $508.930
TMA (MOBILE OPERATION)
DAY 15.000 $198.740 $300.000 $652.790 $623.000 $584.210 $1,100.000 $687.000 $1,017.850
Totals: $5,427,205.240 $4,880,363.380 $4,886,754.210 $5,068,912.090 $5,079,458.400 $5,241,890.500 $5,427,000.000 $6,135,593.240