| Control Number | County | Highway | Bid Date | Low Bidder | Pay Estimates | % of Contract | Amount | % Complete | Contract Amount |
|---|---|---|---|---|---|---|---|---|---|
| 0008-03-133 | PARKER | IH 20 | 05/03/2024 | ZACHRY CONSTRUCTION CORPORATION | 05/26 | 04/26 | 03/26 | 02/26 | 01/26 | 0.28% | $276,847.21 | 60.00% | $98,874,005.22 |
| 0918-46-327 | DENTON | CS | 08/03/2023 | DURABLE SPECIALTIES, INC. | 04/26 | 03/26 | 02/26 | 01/26 | 12/25 | 0.95% | $24,493.78 | 78.00% | $2,578,292.40 |
| 0135-10-050 | DENTON | US 380 | 08/04/2021 | ZACHRY CONSTRUCTION CORPORATION | 05/26 | 04/26 | 03/26 | 02/26 | 01/26 | 0.06% | $88,901.74 | 98.00% | $148,169,572.58 |