| Control Number | County | Highway | Bid Date | Low Bidder | Pay Estimates | % of Contract | Amount | % Complete | Contract Amount |
|---|---|---|---|---|---|---|---|---|---|
| 6489-67-001 | WISE | US0380 | 11/05/2025 | SHORT-LINE CORPORATION | 04/26 | 03/26 | 02/26 | 42.79% | $488,603.07 | 34.00% | $1,141,862.74 |
| 6481-85-001 | TARRANT | US0081 | 07/01/2025 | T&L CLEANING SERVICES LLC | 04/26 | 03/26 | 02/26 | 01/26 | 12/25 | 0.00% | $0.00 | 47.00% | $1,434,062.00 |
| 6464-66-001 | JOHNSON | IH0035W | 06/05/2025 | T&L CLEANING SERVICES LLC | 04/26 | 03/26 | 02/26 | 01/26 | 12/25 | 0.00% | $0.00 | 41.00% | $865,191.00 |
| 6460-21-001 | PARKER | IH0020 | 05/03/2024 | SHORT-LINE CORPORATION | 04/26 | 03/26 | 02/26 | 01/26 | 12/25 | 0.00% | $0.00 | 88.00% | $1,599,047.00 |
| 6460-15-001 | PALO PINTO | IH0020 | 05/03/2024 | SHORT-LINE CORPORATION | 04/26 | 03/26 | 02/26 | 01/26 | 12/25 | 0.00% | $0.00 | 61.00% | $1,145,494.00 |
| 6439-76-001 | TARRANT | IH0820 | 06/28/2023 | SHORT-LINE CORPORATION | 03/26 | 02/26 | 01/26 | 12/25 | 11/25 | 50.00% | $1,182,423.50 | 153.00% | $2,364,847.00 |
| 6399-85-001 | JOHNSON | IH0035W | 06/29/2022 | SHORT-LINE CORPORATION | 10/25 | 09/25 | 08/25 | 07/25 | 06/25 | 0.00% | $0.00 | 90.00% | $1,803,904.00 |