TxDOT Subcontracts for DOUBLE S CONSTRUCTION
| Control Number | County | Highway | Bid Date | Low Bidder | Pay Estimates | % of Contract | Amount | % Complete | Contract Amount |
|---|---|---|---|---|---|---|---|---|---|
| 0581-01-161 | DALLAS | SL 12 | 04/04/2024 | YUNEX LLC | 04/26 | 03/26 | 02/26 | 01/26 | 12/25 | 2.69% | $85,181.35 | 43.00% | $3,166,592.95 |
| 0918-24-267 | COLLIN | CS | 02/02/2024 | FNH CONSTRUCTION, LLC | 04/26 | 03/26 | 02/26 | 01/26 | 12/25 | 0.21% | $10,231.90 | 80.00% | $4,872,332.75 |
| 0918-47-342 | DALLAS | CS | 05/05/2023 | FNH CONSTRUCTION, LLC | 04/26 | 03/26 | 02/26 | 01/26 | 12/25 | 0.36% | $9,944.51 | 89.00% | $2,762,362.50 |
| 0091-03-031 | COLLIN | SH 289 | 05/04/2023 | WG ENGINEERING & CONSTRUCTION, LLC | 11/25 | 10/25 | 09/25 | 08/25 | 07/25 | 1.16% | $29,292.20 | 101.00% | $2,525,189.59 |
| 0094-01-032 | TARRANT | SH 183 | 03/07/2023 | RAGLE CONSTRUCTION, INC. | 05/26 | 04/26 | 03/26 | 02/26 | 01/26 | 0.09% | $24,887.44 | 62.00% | $27,652,709.03 |
| 0500-03-625 | HARRIS | IH 45 | 12/02/2020 | HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC. | 04/26 | 03/26 | 02/26 | 01/26 | 12/25 | 2.39% | $83,970.13 | 105.00% | $3,513,394.65 |
| 3510-05-043 | HARRIS | SH 99 | 08/07/2019 | HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC. | 09/25 | 08/25 | 07/25 | 06/25 | 05/25 | 1.05% | $117,710.09 | 102.00% | $11,210,484.61 |