TxDOT Subcontracts for CATO ELECTRIC COMPANY
| Control Number | County | Highway | Bid Date | Low Bidder | Pay Estimates | % of Contract | Amount | % Complete | Contract Amount |
|---|---|---|---|---|---|---|---|---|---|
| 0915-00-253 | BEXAR | VA | 02/02/2023 | E-Z BEL CONSTRUCTION, LLC | 08/25 | 06/25 | 05/25 | 04/25 | 03/25 | 0.13% | $2,283.70 | 93.00% | $1,756,689.75 |
| 0915-12-693 | BEXAR | CR | 06/30/2022 | E-Z BEL CONSTRUCTION, LLC | 11/24 | 09/24 | 08/24 | 07/24 | 06/24 | 0.41% | $6,993.79 | 100.00% | $1,705,802.68 |
| 0915-12-624 | BEXAR | CS | 06/29/2022 | D&G ENERGY CORPORATION | 04/26 | 03/26 | 02/26 | 01/26 | 12/25 | 0.13% | $2,933.88 | 77.00% | $2,256,831.50 |
| 0915-00-224 | BEXAR | VA | 02/05/2021 | RELMCO, INC. | 07/25 | 06/25 | 05/25 | 04/25 | 03/25 | 0.00% | $0.00 | 93.00% | $2,780,797.53 |